South Florida East Coast Corridor Transit Analysis Study
Document Sample


South Florida East Coast Corridor
Transit Analysis Study
Miami-Dade, Broward and Palm Beach Counties
Existing Structure Characteristics
Financial Project ID No.41703112201
Prepared for:
Prepared by:
BCC Engineering, Inc.
In association with:
Gannett- Fleming, Inc.
August 2006
South Florida East Coast Corridor Transit Analysis
TABLE OF CONTENTS
1.0 INTRODUCTION 1
2.0 EXISTING CHARACTERISTICS FEC RAILROAD BRIDGES 1
3.0 BRIDGE INSPECTION REPORTS & LOAD RATINGS 17
4.0 EXISTING CHARACTERISTICS OVERPASS BRIDGES 17
5.0 SUMMARY 30
South Florida East Coast Corridor Transit Analysis
1.0 INTRODUCTION
The Florida East Coast Railroad (FECRR) traverses through Miami-Dade, Broward and
Palm Beach Counties and is generally parallel to Dixie Highway and US-1. Currently, in
the tri-county area, the FECRR is used exclusively for freight movement. As
redevelopment and infill in the older eastern communities of South Florida has been
encouraged, discussion of returning passenger service to the FECRR has emerged.
After some individual efforts, the three counties agreed to embark on a regional study of
the feasibility of using the FECRR for passenger service. The Florida Department of
Transportation, District 4, was selected as the appropriate agency to manage the
project and in October 2005, the South Florida East Coast Corridor Study (SFECC)
study was initiated.
The study area follows the FECRR right-of-way from approximately West Flagler Street
in Downtown Miami to Indiantown Road in Jupiter.
The SFECC study includes assessing the complex relationships among existing and
future freight and goods movements with the need to develop new transit travel capacity
in South Florida. The study corridor is undergoing significant redevelopment and
densification that is likely to continue given the projected increase in population in the
next thirty years in the region. At the same time, the three ports (Port of Miami, Port
Everglades, and Port of Palm Beach) serving the region have focused on the FECRR to
meet increasing demand for intermodal freight capacity. The SFECC study area is
served by existing Tri-County Commuter Rail (Tri-Rail) service that could be
complemented and enhanced by new service and/or connections to employment and
residential centers that are adjacent or near to the FECRR right-of-way.
There are a total of 30 bridge structures along the study corridor. The FECRR owns
and maintains a total of 17 these bridges. The bridges are numbered from north to
south according to their milepost location along the FECRR. The remaining 13 bridges
are overpasses. Figure Nos. 1, 2, and 3 present the general location of the bridge
structures in each of the three Counties (Palm Beach, Broward, and Miami-Dade
County). The purpose of this report is to provide relevant general information regarding
the characteristics of these bridges.
2.0 EXISTING CHARACTERISTICS FEC RAILROAD BRIDGES
The following is a brief description of each of the FECRR bridges located along the
study corridor. The bridges are presented in order from north to south starting with the
FECRR crossing over the Loxahatchee River in northern Palm Beach County to the
FECRR crossing over the Little River which is located just north of Downtown Miami.
-1-
South Florida East Coast Corridor Transit Analysis
-2-
South Florida East Coast Corridor Transit Analysis
-3-
South Florida East Coast Corridor Transit Analysis
-4-
South Florida East Coast Corridor Transit Analysis
2.1 - FECRR over Loxahatchee River (Mile Post 282.58)
The existing FECRR crossing over the
Loxahatchee River was originally
constructed in 1935. The bridge has an
overall length of 548’-4” and is comprised
of ten (10) spans. The bridge is one of two
(2) lift bridges within the study limits. The
span arrangement from north to south
is:1@66’-10”, 1@7’-6”, 1@54’-0”, 1@60’-
0”, and 6@66’-0”.
The superstructure is an open deck with
wood ties supported on steel girders. The
machinery pit is located under Span 2.
FECRR over Loxahatchee River
Span 3 is a heel trunion lift span with
variable depth steel thru girders.
The bridge is on a tangent alignment and provides for two (2) tracks, however, the
west track is out of service.
2.2 - FECRR over Earman River (Mile Post 291.86)
The existing FECRR crossing over the
Earman River was constructed in 1979.
The bridge has seven (7) simply
supported spans of 25’-0” and an overall
length of175’-0”. It is on a tangent
alignment and provides for a single track
only. The open deck consists of wood ties
which are supported on steel wide flange
beams (W36x170). The superstructure is
supported on pile bents (reinforced
concrete pile caps on prestressed square
concrete piles). A single row of four (4)
piles is provided at each bent. FECRR over Earman River
-5-
South Florida East Coast Corridor Transit Analysis
2.3 - FECRR over C-51 Canal (Mile Post 304.05)
The existing FECRR crossing over the C-
51 Canal was constructed in 1984. The
overall bridge length is 200’-0” with eleven
(11) simply supported spans. Span
arrangement is 2@15’-0”, 7@20’-0”, and
2@15’-0”. The bridge is on a tangent
alignment and provides for a single track
only. The open deck consists of wood ties
which are supported on steel wide flange
beams (W36x170). The superstructure is
supported on pile bents (reinforced
concrete pile caps on prestressed square
FECRR over C-51 Canal concrete piles). A single row of four (4)
piles is provided at each bent.
2.4 - FECRR over Boynton Beach Canal
(C-16) (Mile Post 311.45)
The existing FECRR crossing over the
Boynton Beach Canal was constructed in
1963. Twin bridges are provided with each
having an overall length of 142’-0”. Each
bridge consists of twelve (12) simply
supported spans. Span arrangement is
1@11’-0”, 10@12’-0”, and 1@11’-0”. The
bridges are on a tangent alignment and
provide for a single track on each bridge.
However, the tracks on the mainline bridge
have been removed and the mainline track
alignment shifted over to the siding. The
Mainline Bridge
mainline bridge has been out of service since Out of service
September 15, 2002. The superstructures
consist of steel wide flange beams (W12x96).
The deck provided for the siding is open
wood ties.
Independent pile bents are provided for each
of the structures. The pile bents consist of
precast concrete pile caps on prestressed
square concrete piles. A single row of three
(3) piles is provided at each bent.
FECRR over Boynton Beach Canal
-6-
South Florida East Coast Corridor Transit Analysis
2.5 - FECRR over C-15 Canal
(Mile Post 319.55)
The existing FECRR crossing over the C-
15 Canal was constructed in 1962 and is
on a tangent alignment. The bridge has
six (6) spans of 28’-6” for an overall length
of 171’-0”. The existing bridge is wide
enough to provide for double tracking, but
only one (1) track is currently provided.
The superstructure consists of a ballast
deck with wood ties supported on
prestressed concrete slabs. Slab units
are 28” or 30” in depth. The FECRR over C-15 Canal
superstructure is supported on pile bents
and all intermediate bents have two (2)
rows of piles. Twelve piles are provided
at each bent.
Exist. bridge can accommodate
a second track
Int. Bents with double row of piles
-7-
South Florida East Coast Corridor Transit Analysis
2.6 - FECRR over Hillsboro River
(Mile Post 326.58)
The existing FECRR crossing over the
Hillsboro River was constructed in 1982.
The bridge has a total of eight (8) spans
with two (2) continuous units of four (4)
spans each. Unit 1 has four (4) spans
@25’-0”, and Unit 2 has two (2) spans
@27’-10”, and two (2) spans @25’-0”. The
overall bridge length is 205’-8”. The bridge
is on a tangent alignment and provides for FECRR over Hillsboro River
a single track only. The open deck consists
of wood ties supported on steel wide flange
beams. Steel beams are either W36x170 or
W36x230. As per the latest inspection
report, the FECRR noted that the anchor
bolts have been lifting and recommended
that the bridge be modified from continuous
spans to simply supported spans. The
superstructure is supported on pile bents
(reinforced concrete pile caps on
prestressed square concrete piles). A
single row of four (4) piles is provided at
each bent. Inspection reports noted spalls
along the underside of the caps where the FECRR noted maintenance issues due
piles frame into the cap. to continuous spans
2.7 - FECRR over Cypress Creek Canal (Mile Post 334.93)
The existing FECRR crossing over the
Cypress Creek Canal was constructed in
1960. The bridge has five (5) simply
supported spans and an overall length of
148’-6”. Span arrangement is as follows:
1@28’-6”, 3@30’-6”, and 1@28’-6”. The
existing bridge is on a tangent alignment
and provides for a single track only. The
superstructure consists of a ballast deck
with concrete ties supported on prestressed
concrete slabs. The superstructure is
supported on pile bents.
FECRR over Cypress Creek Canal
-8-
South Florida East Coast Corridor Transit Analysis
2.8 - FECRR over North Fork of Middle River
(Mile Post 337.91)
The existing FECRR crossing over the
North Fork of the Middle River was
constructed in 1957. The overall bridge
length is 204’-0” with 17 spans of 12’-0”
each. The bridge is on a tangent
alignment and provides for a single track
only. The bridge also supports an open
grate walkway which runs adjacent to the
mainline track. The open deck consists of
wood ties supported on steel wide flange
beams (W12x96). FECRR over North Fork of
Middle River
The superstructure is supported on timber
pile bents with steel caps. A single row of
five (5) timber piles is provided at each
bent. Several of the bents have been
retrofitted with a double cap consisting of
a timber tie placed under the existing
steel wide flange cap. The top of the
existing timber piles were cut-off to
provide for the double cap.
In addition, there are existing timber bents
adjacent to the mainline bridge.
Currently, these bents are only supporting
Exist. Timber Bents adjacent to mainline
some existing utilities. However, the
existing bents could potentially support an
additional track.
Existing double capped bents
-9-
South Florida East Coast Corridor Transit Analysis
2.9 - FECRR over South Fork of Middle River
(Mile Post 338.52)
The existing FECRR crossing over the
South Fork of the Middle River was
constructed in 1959. The overall
bridge length is 192’-0” with 16 spans
of 12’-0” each. The bridge is on a
tangent alignment and provides for a
single track only. The open deck
consists of wood ties supported on
steel wide flange beams (W12x96).
FECRR over South Fork of Middle River
The superstructure is supported on
timber pile bents with steel caps. A
single row of five (5) timber piles is
provided at each bent. Several of the
bents have been retrofitted with a
double cap consisting of a timber tie
placed under the existing steel wide
flange cap. The top of the existing
timber piles were cut-off to provide for
the double cap.
In addition, there are existing timber
bents adjacent to the mainline bridge.
Double Capped Timber Bents
Currently, these bents are only
supporting some existing utilities.
However, the existing bents could
potentially support an additional track.
Existing Timber Bents adjacent to Mainline
- 10 -
South Florida East Coast Corridor Transit Analysis
2.10 - FECRR over New River (Mile Post 341.26)
The existing FECRR crossing over the New
River was originally constructed in 1977.
The bridge has an overall length of 216’-0”
and is comprised of seven (7) spans. The
bridge is one of two (2) lift bridges within
the study limits. The span arrangement
from north to south is: 3@25’-0”, 1@13’-0”,
1@78’-0”, and 2@25’-0”.
The superstructure is an open deck with
wood ties supported on steel girders. The
machinery pit is located under Span 4.
Span 5 is a heel trunion lift span with
variable depth steel plate thru girders. The
girders for Spans 1 thru 3, 5 and 6 are
W36x170. The girders for Span 4 are
FECRR over New River
W18x106.
The bridge is on a tangent alignment and
provides for two (2) tracks, the mainline and
a siding.
2.11 - FECRR over Tarpon River, (Mile Post 342.00)
The existing FECRR crossing over the Tarpon River was constructed in 1947. The
overall bridge length is 36’-0” with three (3) spans of 12’-0” each. The bridge is on a
tangent alignment and carries two (2) tracks, the mainline and a siding. The open
deck consists of wood ties supported on steel wide flange beams (W12x106).
FECRR over Tarpon River Double Capped Bents
- 11 -
South Florida East Coast Corridor Transit Analysis
The superstructure is supported on timber pile bents with steel caps. A single row of
four (4) piles is used under each of the tracks. The timber piles have concrete
jackets and the bents have been double capped. The double caps consist of a built-
up section with a timber tie placed under and steel wide flange beam. The ends of
the bridge are supported on a Steel “H” pile bent.
As per discussion with FECRR, this bridge is scheduled to be replaced in 2006. The
new bridge will have a ballast deck supported on prestressed concrete slabs.
2.12 - FECRR over Dania Cut-Off Canal (Mile Post 345.41)
The existing FECRR crossing over the Dania Cut-Off Canal was constructed in
1927. The bridge is 76’-0” long with a single span supported on concrete
abutments. The superstructure consists of
two (2) steel thru girders with steel floor
beams and stringers to support the rails.
Currently there is one (1) track over the
FECRR over Dania Canal Thru Plate Girder & Floor Beam
Superstructure
bridge only, even though the width of the existing bridge can provide for two (2)
tracks. Decking consists of open wood ties.
2.13 - FECRR over Oleta River
(Mile Post 353.74)
The existing FECRR crossing over the
Oleta River was built in 1963. The overall
length is 82’-0”. The bridge has a total of
seven (7) spans consisting of 11’-0” long
end spans and 12’-0” long interior spans.
The bridge is on a tangent alignment and FECRR over Oleta River
- 12 -
South Florida East Coast Corridor Transit Analysis
provides for a single track only. The open deck consists of wood ties supported on
steel wide flange beams (W12x96).
The superstructure is supported on timber pile bents with steel caps. A single row of
five (5) timber piles is provided at each
bent. All the bents have been retrofitted
with the top of the timber piles cut-off to
provide for a double cap. The double
caps consist of a built-up section with a
timber tie placed under a steel wide
flange beam. Additionally, at Bent No.5, a
helper pile has been driven on the east
side, and a steel I-beam placed under the
cap.
There are also existing timber bents
immediately adjacent to the mainline
bridge. Currently, these bents support
Additional Bents adjacent to
existing utilities, but they could also
Mainline Bridge
support an additional track.
2.14 - FECRR over Royal Glades Canal
(Mile Post 354.51)
The existing FECRR crossing over the
Royal Glades Canal was constructed in
1956. The bridge has seven (7) simply
supported spans and an overall length
of 160’-0”. Span Nos. 1 and 7 are 20’-0”
long and Span Nos. 2 thru 6 are 24’-0”
long. The existing bridge is on a
tangent alignment and provides for a
single track only. The superstructure
consists of a ballast deck with concrete
ties supported on concrete slabs. The
superstructure is supported on pile FECRR over Royal Glades Canal
bents (reinforced concrete pile caps on
prestressed square concrete piles).
2.15 - FECRR over Arch Creek (Mile Post 356.53)
The existing FECRR crossing over Arch Creek was constructed in 1930. The bridge
has a single 50’-0” span supported on concrete abutments. The mainline track is
- 13 -
South Florida East Coast Corridor Transit Analysis
FECRR over Arch Creek
supported by wood ties (open deck) and
two (2) steel plate girders. The existing
abutments are wide enough to provide for Existing Girders for sidingl
two (2) tracks with two (2) additional steel
girders in place adjacent to the mainline track. However, the deck and rails for the
siding are not in place.
2.16 - FECRR over Biscayne Park Canal (Mile Post 358.78)
The existing FECRR crossing over the Biscayne Park Canal was constructed in
1981. Twin bridges are provided. Each bridge consists of seven (7) spans and the
overall bridge length is 134’-0”. The span arrangement is 1@17’-0”, 5@20’-0”, and
FECRR over Biscayne Park Canal Golf cart path under end span
1@17’-0”. Golf cart paths cross under each of the end spans while Span Nos. 2 thru
6 are over the water. The bridges are on a tangent alignment and provide for two (2)
tracks with open decks on concrete ties. FECRR inspection reports call for the
concrete ties to be replaced with wood ties. The superstructures consist of steel
- 14 -
South Florida East Coast Corridor Transit Analysis
wide flange beams with W24x146 beams for the end spans and W 36x170 beams
for the interior spans.
Independent pile bents are provided for each of the structures. Each bent consists
of a reinforced concrete cap supported by a single row of four (4) precast
prestressed concrete piles.
2.17 - FECRR over Little River (Mile Post 360.27)
The existing FECRR crossing over the Little River was constructed in 2003 and has
an overall length of 120’-0” with six (6) simply supported spans of 20’-0”. The bridge
provides for two (2) tracks on a curved alignment (degree of curvature of 3° 23’).
The superstructure consists of a ballast deck with wood ties supported on precast
concrete slabs. Walkways and handrails are provided along both sides of the bridge.
FECRR over Little River
Pile bents are provided for the substructure Walkway and Handrail
with reinforced concrete caps on
prestressed square concrete piles. Bent
Nos 3 and 5 have double rows of piles (16 piles per bent) while all other bents have
a single row of piles (10 piles per bent). Brackets have been doweled into the pile
caps to provide lateral restraint of the concrete slabs.
- 15 -
South Florida East Coast Corridor Transit Analysis
- 16 -
South Florida East Coast Corridor Transit Analysis
3.0 BRIDGE INSPECTION REPORTS AND LOAD RATINGS
The FECRR provided Bridge Inspection Reports for each of their bridges located within
the study area. Copies of the reports are included in Appendix A. Required
maintenance and repairs are noted in the comment sections of the report, and the
priority need for the repairs are designated by a letter grade. The highest priority is
designated as “A”.
The FECRR also provided a summary of Cooper E80 Live Load Ratings for several of
the bridges. The data is presented in Appendix B and summarized in Table 2 below.
SOUTH FLORIDA EAST COAST CORRIDOR TRANSIT ANALYSIS STUDY
TABLE 3-1 SUMMARY OF COOPER E80 LIVE LOAD RATINGS - FECRR BRIDGES
Equivalent
Cooper E Live Load Rating
Location Cooper E-Live
Values
Load Ratings
Crossing
Strength 286,000 lb.
County Mile Post Normal Live Maximum Gross Weight
Load Live Load Car
Palm Beach 282.58 Loxahatchee River E48 (S) E82 E53
Broward 341.26 New River E85 (M) E123 E61
Broward 345.41 Dania Cut-Off Canal E61 (M) E90 E61
Miami-Dade 354.51 Royal Glades Canal E62 (S) E74 E63
Miami-Dade 356.53 Arch Creek E73 (M) E107 E57
LEGEND: M = Moment Controlled
S = Shear Controlled
Freight trains using the FEC currently run cars with a gross weight of 286,000 lb on their
tracks. The weight of passenger trains is expected to be less than the weight of the
existing freight cars using the FEC’s tracks. However an analysis should be performed
if existing bridges are to be used for passenger trains.
4.0 EXISTING CHARACTERISTICS OVERPASS BRIDGES
The following is a brief description of each of the Overpasses along the study corridor
that span over the FECRR. The bridges are presented in order from north to south
starting with the SW Ramp over the FECRR (PGA Blvd. and SR 811 Interchange) in
north Palm Beach County to the I-395 crossing over the FECRR located in Downtown
Miami. Relevant existing Bridge Plans and Bridge Inspection Reports have been
included in Appendix C and Appendix D, respectively.
- 17 -
South Florida East Coast Corridor Transit Analysis
4.1 – Ramp SW over the FEC Railway (Bridge # 930493)
The SW Ramp over the FEC Railway is part of
the SR 786 and SR 811 Interchange (FPID
229771-52-01). The single lane ramp provides
a connection from southbound SR 811 (Old
Dixie Highway) to westbound SR 786 (PGA
Blvd.). The structure is a three (3) span
continuous curved steel box girder with a cast
in place concrete deck. Overall length is 657’-
0” with span lengths of 179’-7½”, 297’-9”, and
179’-7½” for spans 1,2, and 3 respectively.
The bridge is on a curved horizontal alignment
with a radius of 656’-2”, a ∆ = 74°54’09” to the
left, and a maximum superelevation rate of Ramp SW over the FECRR
0.081ft/ft. The out-to-out bridge width is 33’-
7½” and the typical section consists of twin steel boxes supported on single column
hammerhead piers.
The FEC is centered under Span No. 2 with a
single track on a bearing of N 14° 05’ 30” W.
The bridge plans also show that the FEC has
planned for two (2) future tracks. The FEC Right
of Way measures 100’-0” and the future tracks
are located approximately 42’-0” to each side
and parallel to the existing. Piers were
constructed radial to the bridge and outside the
FEC Right of Way. Plans do not show the
minimum horizontal clearance; however field
survey measured approximately 57’-6” to the
FEC crossing under span #2 face of Pier No. 2@ and 3.
The minimum vertical clearance measures 23’-615/16” over the FEC’s west Right of
Way, 25’-25/8” over the existing track, and 26’-3” over the FEC’s east Right of Way.
4.2 – PGA Boulevard /SR 786 over the FECRR (Bridge # 930491, and 930492)
The structure consists of twin bridges carrying PGA Blvd. (SR 786) over the FECRR
and Old Dixie Highway (SR 811).
The eastbound bridge (930491) has an out-to-out width of 78’-11¼” that provides for
four (4) traffic lanes, shoulders, bike lane, sidewalk, and traffic barriers. The
westbound bridge (930492) has an out-to-out width of 58’-213/16” that provides for
three (3) traffic lanes, shoulders, bike lane, and traffic barriers. The eastbound and
westbound structures are separated by a 12’-0” opening between bridges.
- 18 -
South Florida East Coast Corridor Transit Analysis
Overall bridge length is 411’-11/16” with span lengths of 118’-15/16”, 137’-99/16” and
155’-23/16”. The bridge is on a tangent alignment on a bearing of N 75°56’42” E.
FEC crossing @ PGA Boulevard Aesthetic towers adjacent to piers
The bridge is located at the crest of a 1049’-107/16“vertical curve with grades of
+4.4% and -4.4%. The bridge decks have a cross-slope of 0.02 ft/ft to the outside.
The typical section of each bridge consists of a cast-in-place concrete deck and
Florida U-Beam superstructure supported on multi-column piers on pile foundations.
The eastbound bridge has eight (8) girder lines and three (3) columns piers. The
westbound bridge has six (6) girder lines and two (2) column piers.
The bridges also have several aesthetic elements. Pier columns are fluted, fascia
panels have been provided on the outboard faces of the spans, decorative lighting is
attached to the bridge, and decorative pylons and towers have been constructed
adjacent to the piers and end bents.
The FEC crosses under Span No. 2 with a single track that is nearly perpendicular to
the bridge. The bridge plans also show that the FEC has planned for two (2) future
tracks. The FEC Right of Way measures 100’-0” and the future tracks are located
approximately 42’-0” to each side and parallel to the existing. Pier Nos. 2 and 3 are
perpendicular to the bridge and outside the FEC Right of Way. The minimum
horizontal clearance from the centerline of the existing track to the face of Pier No. 2
is 65’-69/16“. The minimum horizontal clearance from the centerline of the existing
track to the face of Pier No. 3 is 65’-113/8“. However, the horizontal clearance to
Towers 1 and 2 which are adjacent to Pier 3 controls and is approximately 53’-83/8“
(field measured).
The minimum vertical clearance measures 25’-4” over the FEC’s east Right of Way.
- 19 -
South Florida East Coast Corridor Transit Analysis
4.3 – 12th Street Overpass (Bridge # 937709)
The existing 12th Street Overpass was
constructed by the City of West Palm
Beach in 1965. Overall bridge length is
980’-0” and there are a total of 22
spans that range from 40’-0” to 109’-0”
in length. The bridge has a mix of
superstructure types including pre-
stressed sono-void units or AASHTO
girders with a reinforced concrete
bridge deck. Except for over the
FECRR, the out to out bridge width is
48’-6” and provides for two (2) 11’-0”
traffic lanes in each direction. Over the
12th Street overpass FECRR a 5’-6” walkway is provided
along the north side and the out-to-out
width is 53’-0”. Stairs are located on
either side of the railroad to access this walkway. Substructure consists of
reinforced concrete caps supported on 36” Φ concrete columns.
The FECRR crosses under Span No. 11 with six (6) tracks. The skew angle, as
measured from the bridge perpendicular to the centerline of the tracks, is 9° 15’ 00”
to the left. Span 11 is 109’-0” in length with nine (9) Type IV AASHTO girders. The
vertical alignment is on a tangent of +0.425%, and the vertical clearance is 23.74’
over the highest rail elevation (19.74’). The piers located adjacent to the FECRR
(Pier 10 and Pier 11) are three (3) column piers supported on 14” square piles. The
piers are located just outside the railroad right of way and crash walls are provided
between the columns. The minimum horizontal clearance was not provided in the
plans.
The 2004 Bridge Inspection Report shows the bridge to be in overall good condition
with a sufficiency rating of 67.6.
4.4 – Pedestrian Bridge over the FECRR
Plans were not available for this structure and the following description is based on a
cursory field investigation. The structure is pedestrian bridge connecting a parking
garage on the west side with the Palm Beach County Courthouse on the east side.
The bridge has three (3) spans and is a thru truss made up of standard I shapes
supporting a pre-cast concrete plank walkway. The FECRR crosses under Span
No.2. The horizontal clearance to Pier No. 2 and Pier No. 3 is approximately 50’-0”
and 48’-6½” respectively (field measured). The vertical clearance over the railroad
was not provided on the bridge but seems adequate.
- 20 -
South Florida East Coast Corridor Transit Analysis
4.5 – SR 80 / Southern Boulevard over the FECRR (Bridge # 930053)
The existing SR 80 Bridge over the FECRR
was originally constructed in 1939 and
subsequently widened in the 1970’s. Overall
bridge length is 1171’-6” and there are a total
of 37 spans that range from 30’-0” to 60’-0” in
length. The bridge has a mix of
superstructure types including reinforced
cast-in-place beams, AASHTO girders, and
Steel I-Girders. The out to out bridge width is
63’-3” and provides for two (2) 12’-0” traffic
lanes in each direction along with raised
sidewalks and traffic barriers. Substructure
FEC crossing at span #20
consists of reinforced concrete caps
supported on 2’-3” square concrete columns
and spread footings.
The FECRR crosses under Span Nos. 20 and
21 with three (3) tracks. The North Bound and
South Bound Tracks cross under Span 20 and
a Spur Track crosses under Span 21. Span
lengths are 49’-6” and 42’-0” for Span 20 and
Span 21 respectively. The superstructure in
these spans consists of the original reinforced
concrete beams combined with Type II girders
for the widening. Span 20 has eight (8)
reinforced concrete beams and six (6) Type II
girders. Span 21 has seven (7) reinforced
concrete beams and four (4) Type II girders. Southern Boulevard over FECRR
The reinforced concrete bridge deck is 7” thick.
The minimum vertical clearance provided is 22.42’ over the South Bound Track.
The Piers adjacent to the railroad have five (5) columns and crashwalls have been
provided. Horizontal Clearances are as follows:
South Bound Track to Pier 19 Horizontal Clearance = 21’-0”
North Bound Track to Pier 20 – Horizontal Clearance = 8’-8”
Spur Track to Pier 20 – Horizontal Clearance = 26’-8 ¾”
Spur Track to Pier 21 – Horizontal Clearance = 8’-4”
The 2005 Bridge Inspection Report shows the bridge to be in overall good condition
with a sufficiency rating of 69.3.
- 21 -
South Florida East Coast Corridor Transit Analysis
4.6 – I-595 Viaduct SW 12th Avenue to FECRR (Bridge # 860478)
The existing I-595 Viaduct was
constructed in 1987. Overall bridge
length is 5814’-0” and there are a total of
48 spans ranging from 86’-10” to 122’-6”
in length. Out to out bridge width varies.
The minimum out-to-out width is 140’-9”
and provides for four (4) lanes in each
direction, 10 ft. shoulders and traffic
barriers. At begin and end bridge,
however, the out-to-out width is
considerably wider. At begin bridge the
I-595 Viaduct over FECRR structure provides for six (6) eastbound
lanes and five (5) westbound lanes. At
end bridge the structure provides for the ramps to and from US-1 (Ramp K, L, and
N).
The FEC is located near the end bridge under Span No. 47 and Span No. 48 and
between Pier Nos. 47 and 48 and End Bent 49. The FEC has two (2) tracks under
Span 47 and four (4) tracks (West Main, East Main, and spur tracks) under Span 48.
The bridge in this area is on a curved alignment with a radius of 8490.39’ and a ∆ of
8°22’13” to the right. The deck has a variable width, is superelevated at 0.027 ft/ft,
and the profile is on a vertical curve with a length of 560.25’ and grades of +0.70%
and -0.894%.
Span Nos. 47 and 48 are part of a four (4) span unit. The superstructure consists of
prestressed concrete girders and a 7” thick reinforced concrete deck. Girder depth
is 6’-1½”. The girders are simply supported but the bridge deck has been poured
continuous for live load. There are 18 girders in Span 47 and 21 girders in Span 48.
The substructure consists of multi-column piers with reinforced concrete caps.
Columns are round with a 3’-6” diameter. Pier 47 has six (6) columns and Pier 48
has seven (7) columns. A single 5’ diameter drilled shaft is provided at each column.
End Bent 49 is also supported on drilled shafts and there is a wrap around retaining
wall at the End Bent (Retaining Wall No.2). Pier No. 48 and End Bent 49 are parallel
to the FEC’s East and West Mains. Pier No. 47 and Pier No. 48 are skewed to the
tracks that run under Span 47.
Horizontal Clearances are as follows:
SPAN NO. 47
C.L. FECRR to Pier No. 47 Horizontal Clearance = 34.06’
C.L. FECRR to Pier No. 48 Horizontal Clearance = 11.96’
- 22 -
South Florida East Coast Corridor Transit Analysis
SPAN NO. 48
C.L. West Main to Pier No. 48 Horizontal Clearance = 37.00’
C.L. East Main to Retaining Wall No. 2 Horizontal Clearance = 50.64’
The minimum Vertical Clearance under Span No. 47 is 26.60’ and the minimum
Vertical Clearance under Span No. 48 is 23.79’.
2005 Bridge Inspection Report shows the bridge to be in overall good condition with
a sufficiency rating of 82.0.
4.7 – Ramp K over the FEC Railway (Bridge # 860633)
Ramp K over the FEC Railway is part of
the Fort Lauderdale Hollywood
International Airport Interchange (FPID
403635-01-58-01). Overall length is 402’-
3” with span lengths of 105’-0”, 165’-9”,
and 131’-6” for Span Nos. 1,2, and 3
respectively. The bridge is on a curved
horizontal alignment and a superelevation
varies from 0.058ft/ft to 0.02416 ft/ft.
The superstructure consists of a single
Ramp K over FECRR cell concrete segmental box. The top
flange width varies from 33-31/8” to 49’-
73/8”. The bottom flange is 17-1½“ wide
and the depth of the box is 8’-0 ½”.
The FEC has five (5) tracks crossing
under Span No. 2 between Pier No. 2 and
Pier No. 3. The substructure consists of
single column flared piers supported on
pile foundations. The footing at Pier No. 2
is 12’-6” long by 26’-0” wide and has 18
piles. The footing at Pier No. 3 is 17’-6”
square and has 16 piles. The piers are
located outside of the FEC’s Right-of-
Way. The minimum horizontal clearance
as measured from the Center Line of the
westernmost track to Pier No. 2 is 26.63’.
The minimum vertical clearance is also
over the westernmost track and measures
26.88’.
FEC crossing @span #2
- 23 -
South Florida East Coast Corridor Transit Analysis
2005 Bridge Inspection Report shows the bridge to be in overall excellent condition
with a sufficiency rating of 91.5.
4.8 – Ramp A over the FEC Railway (Bridge # 860631)
Ramp A over the FEC Railway is part of the Fort Lauderdale Hollywood International
Airport Interchange (FPID 403635-01-58-01). The bridge has five (5) Spans with an
overall bridge length of 805’-9”. The superstructure consists of twin concrete
segmental box girders. Piers supporting the boxes are staggered. The span
arrangement for the northernmost box is 127’-6”, 184’-3”, 186’-9”, 189’-3”, and 118’-
0”. The span arrangement for the southernmost box is 123’-17/8”, 194’-41/8”, 191’-9”,
190’-3”, and 106’-3”.
Ramp A FEC crossing under span #4
Twin segmental box girders
The majority of the bridge is on a curved horizontal alignment. However a portion of
Span No. 4 and all of Span No. 5 is on a tangent alignment with a bearing of S 89°
51’ 18” W. The out-to-out deck width varies from 97’-1” to 105’-7”. Superelevation
for the north box varies from +0.06 ft/ft to -0.02 ft/ft. Superelevation for the south
box varies from -0.06 ft/ft to -0.02 ft/ft.
For the north box the top flange of the segment measures 47’-1½”. For the south
box the top flange varies from 47-11/2” to 54’-65/8”. Bottom flanges are 17-1½“ wide
and the boxes are 8’-17/8” deep. A 3’-0” to 4’-0” closure pour was placed between
boxes.
The FEC has five (5) tracks crossing under Span No. 4 between Pier No. 4 and Pier
No. 5. The substructure consists of single column flared piers supported on pile
foundations. The footings at Pier No. 4 north and Pier No. 4 south are 22’-0” square
and have 25 piles. The footing for Pier No. 5 north is 23’-0” long by 30’-0” wide and
has 33 piles. The footing for Pier No. 5 south is 17’-6” long by 24’-0” wide and has
20 piles. The piers are located outside of the FEC’s Right-of-Way. The minimum
horizontal clearance as measured from the Center Line of the westernmost track to
Pier No. 5 north is 26.75’
- 24 -
South Florida East Coast Corridor Transit Analysis
The minimum vertical clearance is also over the westernmost track and measures
25.16’.
2005 Bridge Inspection Report shows the bridge to be in overall excellent condition
with a sufficiency rating of 88.4.
4.9 – Ramp D over the FEC Railway (Bridge # 860434)
Ramp D over the FEC Railway is part of the Fort Lauderdale Hollywood International
Airport Interchange (SPN: 86095-3495). The overall length of the bridge is 374’-
35/16” with span lengths of 125’-10¼”, 152’-6¼“, and 95’-1013/16” for Span Nos. 1,2,
and 3 respectively. The bridge is on a curved horizontal alignment with a
superelevation rate 0.09 ft/ft.
The superstructure consists of a single cell concrete segmental box. The top flange
width measures 42’-9” and provides for two (2) traffic lanes, shoulders, and traffic
barriers. The bottom flange is 16’-6“ wide and the depth of the box is 7’-3”.
FEC crossing under span #2 Ramp D over FECRR
The FEC has four (4) tracks crossing under Span No. 2 between Pier No. 2 and Pier
No. 3. The substructure consists of single column flared piers supported on pile
foundations. Footings are 28’-0” long by 30’-0” wide and have 42 piles. The piers
are located outside of the FEC’s Right-of-Way and the minimum horizontal
clearance as measured from the Center Line of the westernmost track to Pier No. 3
is 23.20’.
The minimum vertical clearance is also over the westernmost track and measures
23.51’.
The 2006 Bridge Inspection Report shows the bridge to be in overall good condition
with a sufficiency rating of 97.0.
- 25 -
South Florida East Coast Corridor Transit Analysis
4.10 – Ramp C over the FEC Railway (Bridge # 860632)
Ramp C over the FEC Railway is part of
the Fort Lauderdale Hollywood
International Airport Interchange (FPID:
403275-15401). The bridge is an eight
(8) span structure with an overall length of
1103’-6”. Span lengths are 102’-3”, 151’-
9”, 152’-9”, 154’-0”, 148’-0”, 149’-0”, 149’-
9”, and 96’-0”. The bridge is on a curved
horizontal alignment and the
superelevation varies from +0.058 ft/ft to -
0.10 ft/ft.
Ramp C over FECRR
The superstructure consists of a single
cell concrete segmental box. The top flange width measures 55’’-4½” and provides
for three (3) traffic lanes, shoulders, and traffic barriers. The bottom flange is 17’-
1½” wide and the depth of the box is 8’-17/8”.
The FEC has five (5) tracks crossing under
Span No. 2 between Pier No. 2 and Pier No. 3.
The substructure consists of single column
flared piers supported on pile foundations. The
footing for Pier No. 2 is 12’-6” long, 26’-0” wide
and has 18 piles. The footing for Pier No. 3 is
22’-0” square and has 20 piles. The piers are
located outside of the FEC’s Right-of-Way and
the minimum horizontal clearance as
measured from the Center Line of the
westernmost track to Pier No. 2 is 26.22’.
FEC crossing @ Span # 2
The minimum vertical clearance is also over
the westernmost track and measures 23.80’.
The 2006 Bridge Inspection Report shows the bridge to be in overall very good
condition with a sufficiency rating of 99.1.
4.11 – NE 203rd Street over the FECRR (Bridge # 870954)
The bridge carrying NE 203rd Street (Ives Dairy Road) over the FEC Railway is part
of the SR 5/ US 1 Interchange at NE 203rd Street (SPN: 87030-3501). The bridge
was constructed in 2001 and is a five (5) span structure which provides for the
elevated 4-leg signalized US 1/NE 203rd Street intersection. Spans Nos. 1, 2 and 3
provide for the west leg of the intersection and carry east bound NE 203rd Street
over West Dixie Highway and the FEC. Span No 4 provides for the elevated portion
- 26 -
South Florida East Coast Corridor Transit Analysis
of US-1. Span No. 5 provides the east
leg of the intersection which includes the
westbound NE 203rd Street to US-1
movement and eastbound NE 203rd
Street.
The FEC has two (2) tracks on a tangent
alignment with a bearing of N 02°07’21”
W and the bridge crosses the tracks the
FEC at Milepost 352+282.5 ft. The tracks
cross under Span No. 2 and between Int.
Bent No. 2 and Int. Bent No. 3. NE 203rd ST over FECRR
Span No. 2 has a steel plate girder superstructure. Span length is 123’-03/8” and the
depth of the web is 51”.
The intermediate bents consist of
reinforced concrete caps supported on
two (2) 5’-0” diameter columns. Each of
the columns in turn is supported on a 6’-0”
diameter drilled shaft. The piers are
located outside of the FEC’s Right-of-
Way. The minimum horizontal clearance
as measured from the easternmost track
to the face of Intermediate Bent No. 2 is
44.67’. The minimum horizontal
clearance as measured from the
easternmost track to the face of Retaining NE 203rd ST over FECRR
Wall No. 1 is 68.32’.
The minimum vertical clearance as measured along the FEC’ westerly right of way
line is 24.31’. This vertical clearance is based on Top of Rail Elevation of 10.79’.
The 2006 Bridge Inspection Report shows the bridge to be in overall very good
condition with a sufficiency rating of 81.0.
4.12 – I-195 over the FECRR (Bridge # 870313)
The existing I-195 Viaduct was constructed in 1961 and extends from NE 1st avenue
to Biscayne Blvd. in Miami-Dade County. Overall bridge length is 1393’-5” and there
are a total of 20 spans ranging from 38’-0” to 110’-2” in length. Out to out bridge
width varies from 90’-2” to 102’-2.
The FEC has five (5) tracks located under Span No. 13 and between Pier Nos. 13
and 14. The bridge in this area is on a curved alignment with a radius of 17,188.78’
and a ∆ of 3°35’24” to the left. The deck has a cross slope of 3/16 in/ft, and the
- 27 -
South Florida East Coast Corridor Transit Analysis
profile is on a vertical curve with a length of 500.00’ and grades of +3.00% and -
2.52%.
The superstructure for Span 13 consists of Type III prestressed concrete girders and
a 7” thick reinforced concrete deck. The girders are simply supported and there are
a total of 18 girder in the span.
The substructure consists of multi-column piers with reinforced concrete caps.
Columns are round with a diameter of 3’-0” diameter. Each Pier has a six (6)
columns supported on pile foundations.
Median footings measure 8’-0” x 11’-0”
and have six (6) piles. Interior footings
measure 10’-0” x 11’-0” and have eight
piles (8) piles. Exterior footings measure
7’-0” x 8’-0” and have four (4) piles. Both
Pier No 13 and Pier No 14 are within the
FEC Right of Way. The Piers have been
constructed parallel to the tracks and the
minimum horizontal clearance is +18.00’
as measured from the outermost tracks to
Ramp I-195 over FECRR Pier No. 13 and Pier No. 14.
The minimum vertical clearance is 22.70 ft. This clearance is based on a top of rail
elevation of +14.42 ft.
2005 Bridge Inspection Report shows the bridge to be in overall very good condition
with a sufficiency rating of 81.0.
- 28 -
South Florida East Coast Corridor Transit Analysis
- 29 -
South Florida East Coast Corridor Transit Analysis
5.0 SUMMARY
• Between Jupiter and Downtown Miami, the FECRR owns and maintains a total of
17 Bridge Structures along their mainline.
• Five (5) bridges are located in Palm Beach County, six (6) bridges are in Broward
County, and five (5) bridges are in Miami-Dade County. The bridge over the
Hillsboro River is located on the Broward/Palm Beach County line.
• The bridges were constructed between 1927 and 2003. Three (3) of the
structures are more than 70 years old, eight (8) structures are between 40 and
60 years old, and six (6) structures are less than 30 years old. The FECRR over
the Tarpon River (MP 342.00) is scheduled to be replaced in 2006.
• All the FECRR bridges are low-level water crossings.
• Except over the Little River (MP 360.27), all the tracks are on a tangent
alignment. Over the Little River the tracks are on a 3°23’ degree curve.
• Two (2) of the bridges, FECRR over the Loxahatchee River (MP 282.58) and
FECRR over the New River (MP 341.26), are Lift Bridges. All the remaining
bridges are fixed bridges.
• Four (4) of the bridges provide two (2) tracks, the mainline and a siding.
• Thirteen (13) of the bridges have open decks. Four (4) bridges have ballast
decks. Fourteen (14) bridges have wood ties. Three (3) bridges have concrete
ties.
• Thirteen (13) bridges have steel girder superstructures. The FECRR over the
Arch Creek (MP 356.53) as well as the Lift Spans over the Loxahatchee River
and the New River use a Thru Plate Girder. The other steel bridges typically use
36”, 24”, or 12” Wide Flange Sections.
• Four (4) of the bridges have precast concrete slab superstructures. These are
the only superstructures that would be considered viable to be widened.
• Ten (10) of the bridges are supported on concrete pile bents. Reinforced
concrete caps on Prestressed Concrete Piles. These are the only substructures
that would be considered viable to be widened.
• Four (4) of the bridges are supported on timber pile bents. Many of these timber
pile bents have double caps (timber tie under steel cap).
- 30 -
South Florida East Coast Corridor Transit Analysis
• Freight trains using the FEC currently run cars with a gross weight of 286,000 lb
on their tracks. The weight of passenger trains is expected to be less than the
weight of the existing freight cars using the FEC’s tracks.
• Between Jupiter and Downtown Miami, there are 13 bridges crossing over the
FECRR. Bridges include AASHTO Girder Bridges, Florida U-Beam Bridges, and
Concrete Segmental Bridges, as well as steel plate girder and steel box girder
bridges.
• Existing Horizontal and Vertical Clearances at the Overpasses are summarized
in Table 5-1.
- 31 -
Related docs
Get documents about "