									 1           IN THE CITY HALL OF SUMNER COUNTY,
                      STATE OF TENNESSEE
 2   ____________________________________________________

 3

 4                  TDOT COUNCIL MEETING

 5

 6                 Case No.83950-1552-04

 7

 8

 9

10
     ____________________________________________________
11

12

13                TDOT SUMNER COUNTY MEETING

14
               BE IT REMEMBERED that the above-captioned
15   cause came on for hearing, on this, the 25th day of
     September, 2007, when and where the following
16   proceedings were had, to wit:

17

18

19

20

21   _____________________________________________________

22                 ELITE REPORTING SERVICES
                          MISTY BRIGHAM
23                    Associate Reporter
                        P.O. Box 292382
24                Nashville, Tennessee 37229
                     missam624@yahoo.com
25                       (615) 595-0073



          Elite Reporting Services * (615) 595-0073
         1
 1

 2


 3
       A P P E A R A N C E S

 4


 5

                  MR.   JOE CARPENTER

 6
               MR.   SHANE HESTER

                  MR.   DAN DOWNS

 7
               MR.   NICK TUTTLE

                  MR.   AARON ALLISON

 8


 9


10


11


12


13


14


15


16


17


18


19


20


21


22


23


24


25




      Elite Reporting Services * (615) 595-0073
   2
 1                                     * * *


 2                P   R    O   C   E     E    D   I   N    G   S

 3                    (WHEREUPON, the following proceedings

 4   were in a council meeting to the open public:)

 5                        JOE CARPENTER:          My name is Joe            05:57:04

 6   Carpenter and I'm the civil engineering manager for                    05:57:04

 7   TDOT Design Division.         Again, thank you for coming              05:57:04

 8   out.     We kind of got an informal start because the                  05:57:10

 9   mayor is in a city council meeting and they wanted a 05:57:12

10   short briefing here, so I apologize for any                            05:57:12

11   inconvenience on that.                                                 05:57:18

12                        What we're going to do is we're going 05:57:21

13   to make just a short presentation of the proposed                      05:57:23

14   improvements of what we're doing and then we're                        05:57:23

15   going to open it up and we'll take any of your                         05:57:27

16   questions that you would like to put forward at that 05:57:30

17   time.     And then, we will -­ after all the questions                 05:57:32

18   have been voiced from the floor, we'll go ahead and                    05:57:36

19   we'll just let everybody look around and look at the 05:57:40

20   drawings, and we'll respond one on one at that                         05:57:42

21   point.                                                                 05:57:46

22                        We are out here tonight for the Big               05:57:46

23   Station Camp Boulevard project with Cages Bend tying 05:57:48

24   into State Route 6, Gallatin Road.                   We do seek your   05:57:48

25   comments tonight on this.               Any input you have, if         05:57:55



              Elite Reporting Services * (615) 595-0073
                      3

 1   you like it, dislike it, or any other questions you     05:57:58

 2   have.    And there's several methods we're using        05:58:01

 3   tonight to get your comments.    One, we have a court   05:58:04

 4   reporter here to my left, she will take your            05:58:06

 5   comments.    She will also be recording part of the     05:58:09

 6   transcript and the questions.    So, when we do get to 05:58:09

 7   the questions and answers, if you would before you      05:58:09

 8   ask a question state your name so she can hear you.     05:58:09

 9                    Also, in the handouts that we have     05:58:18

10   tonight with some information in it for you, we also 05:58:20

11   have a comment card.    And these are tri-fold, so you 05:58:23

12   can fold them up.    If you don't want to leave them    05:58:26

13   tonight at the sign-in table, you can just fold it      05:58:29

14   up and put a stamp on it and send it to us and it       05:58:33

15   will become part of the transcript as well.    And      05:58:36

16   you're free to take extra of these when you leave       05:58:36

17   out if there's other people and they would like to      05:58:39

18   voice comments, you are free to pick them up and do     05:58:39

19   that.                                                   05:58:47

20                    Again, this project is a partnership   05:58:48

21   between the City of Gallatin and TDOT.    It's a        05:58:49

22   local-interstate connector road.    It's approximately 05:58:53

23   two-tenths of a mile.    Most all of the work, 99       05:58:53

24   percent of it, is going to be taking place on Big       05:58:53

25   Station Camp Boulevard and Cages Bend.    The only      05:59:02



             Elite Reporting Services * (615) 595-0073
        4

 1   work on Gallatin Road essentially will be                05:59:05

 2   reinstalling the signal equipment and then milling       05:59:05

 3   the top surface and re-striping it for the               05:59:13

 4   appropriate turn lane with the relocation of the         05:59:18

 5   intersection.                                            05:59:21

 6                   Also, as well, just a side light of      05:59:22

 7   information, this project right now is tentatively       05:59:25

 8   scheduled for sometime in the calendar year of 2009. 05:59:27

 9   So probably towards the summer or latter fall of         05:59:32

10   that, of 2009 is when it will go to construction.        05:59:32

11                   Again, this is a partnership with        05:59:39

12   TDOT and the City of Gallatin splitting the cost         05:59:41

13   50/50 for this improvement.     At this time, I'm going 05:59:44

14   to ask Shane Hester to come up and briefly describe      05:59:48

15   the improvements to you.                                 05:59:52

16                   SHANE HESTER:    Thanks, Joe.   As Joe   05:59:56

17   stated, the work starts here on Big Station Camp         05:59:57

18   Boulevard.   It was about a thousand foot from the       06:00:00

19   intersection of State Route 6 and Gallatin Road.         06:00:03

20   What we're proposing to do is to tye into the            06:00:03

21   existing which is three lanes and come here a            06:00:03

22   thousand feet and go past a soccer complex and           06:00:03

23   transition out to five-lane section which has been       06:00:09

24   recommended by our traffic design people.                06:00:09

25                   And over here on Cages Bend Road, to     06:00:18



           Elite Reporting Services * (615) 595-0073
           5

 1   start here about 500 feet back from the intersection 06:00:18

 2   and work ourselves towards Gallatin Road.      And we're 06:00:18

 3   going to fork out the road and it's going to be          06:00:27

 4   three lanes and two for the traffic lane.      Here on   06:00:29

 5   the alignment as you can see -­ I know everybody         06:00:35

 6   can't see this, but the existing Big Station Camp        06:00:41

 7   Boulevard and Cages Bend Road, they kind of tangle       06:00:44

 8   the intersection here in State Route 6 and Gallatin      06:00:49

 9   Road.    And I will propose to realign both roads so     06:00:51

10   they intersect at 90-degree angles (indicating)          06:00:53

11   which will increase our safety and operation.            06:00:59

12                    Mainly, on this property, and I just    06:00:59

13   heard Joe state to the mayor that this property here 06:00:59

14   is on the historic registers and has not been listed 06:00:59

15   as a historic property, just potentially historic on 06:01:19

16   the nursery here (indicating).    And we're staying      06:01:19

17   off of that.    The alignment moves this way             06:01:26

18   (indicating) to kind stay off of that, and we're         06:01:29

19   using this slope in construction that's here with        06:01:31

20   anything we're doing that affects the nursery.           06:01:31

21                    Basically, that's -­ we've extended     06:01:31

22   the box here that comes to meet State Route 6            06:01:39

23   (indicating) and like Joe said, 99 percent of the        06:01:39

24   work occurs on both Big Station Camp Boulevard and       06:01:46

25   Cages Bend Road.    The other 1 percent is minority      06:01:47



             Elite Reporting Services * (615) 595-0073
         6

 1   work here on State Route 6.      That pretty much covers 06:01:47

 2   it.                                                       06:01:47

 3                   JOE CARPENTER:     And again, the         06:01:47

 4   traffic -­ the existing traffic will be maintained        06:02:04

 5   during the whole construction process.      Just to       06:02:06

 6   point some things out before question and answer,         06:02:12

 7   when you come up here we have this area where you         06:02:13

 8   can see the improvements.     This is a bond copy, just 06:02:16

 9   in plan format that shows the same type thing with        06:02:20

10   the proposed typical sections, how many lanes             06:02:20

11   through there -­                                          06:02:20

12                   And then this to my right over here       06:02:21

13   at the acquisition table which we'll color the            06:02:21

14   different tracts that are affected in different           06:02:21

15   colors and you can look up here and see how much we       06:02:21

16   estimate the acquired right-of-way easement for that 06:02:26

17   as well.   That's, in essence, all that we have for       06:02:41

18   presentation for such a small project.      But at this   06:02:47

19   point we would open it up for any questions that you 06:02:50

20   may have, and again we will ask if you would stand        06:02:52

21   up and state your name and then your question.            06:02:52

22                   DAN DOWNS:    My name is Dan Downs and    06:02:52

23   my question is two-fold.     One having to do with the    06:02:59

24   extension of the box culvert which is going to            06:03:03

25   extend the drainage area that's at the south of           06:03:03



           Elite Reporting Services * (615) 595-0073
            7

 1   Cages Bend Road.     How exactly are you going to         06:03:03


 2   handle that?     I don't understand when you said you     06:03:03

 3   were going to extend the box culvert how far back         06:03:03

 4   are you going to extend it.        And I guess, in        06:03:03

 5   essence, I'm asking will that take out that drainage 06:03:03

 6   ditch there on the side of the road or will that all 06:03:03

 7   be boxed now?                                             06:03:03

 8                     JOE CARPENTER:     No, sir.   We will   06:03:03

 9   extend this approximately -­ looking at this -­           06:03:03

10   about 125 feet diagonally to get it over to where -­ 06:03:03

11   a new ditch.     We will relocate that channel on the     06:03:03

12   side of Cages Bend Road and tie it back into where        06:03:03

13   we tie into the existing channel.        Because of the   06:03:03

14   feature and for environmental permits, we can't           06:03:03

15   close all of this in box.      And we will pay a high     06:03:51

16   enough permit fee which is necessary to do this with 06:03:54

17   this box culvert.                                         06:03:57

18                     But from the other aspect of it down    06:03:57

19   Cages Bend, we will have to replicate that and            06:04:00

20   probably plant trees back in there to get a permit.       06:04:01

21   Does that answer your question?                           06:04:01

22                     DAN DOWNS:   Uh-huh, in that regard.    06:04:01

23   The second question is someone had mentioned that         06:04:01

24   you had done a hydrology study on that area in            06:04:12

25   there.     Is my understanding, if I'm correct, that      06:04:12



              Elite Reporting Services * (615) 595-0073
         8

 1   that road is below -- the existing Cages Bend Road      06:04:22


 2   is below the hundred year flood plane, is that an       06:04:22

 3   accurate statement?                                     06:04:29

 4                  NICK TUTTLE:     Well, the flood study   06:04:29

 5   in the area shows the flood plane to be completely      06:04:29

 6   on the other side of 31E.     However, the elevation    06:04:29

 7   shows probably about 455 feet and the current road      06:04:29

 8   elevations are a little bit lower than that.            06:04:29

 9                  JOE CARPENTER:     And our last          06:04:39

10   speaker's name was?                                     06:04:39

11                  NICK TUTTLE:     I'm Nick Tuttle with    06:04:29

12   the City of Gallatin.

13                  JOE CARPENTER:     Okay.   Thank you.    06:04:52

14                  As far as that our hydraulic             06:04:52

15   section -­ looking at this -­ because mainly the        06:04:54

16   work we're doing on Cages Bend is strictly an           06:04:54

17   intersection and we're just trying to tie it back       06:04:54

18   down to the existing.   So we're not looking to make    06:04:54

19   any improvement back down to Cages Bend except          06:05:05

20   strictly at Gallatin Road.                              06:05:05

21                  And so the hydraulics that we look       06:05:05

22   at, what our hydraulic section looks at, is that        06:05:12

23   this waterflow coming in and being transferred          06:05:14

24   underneath Gallatin Road.     So their hydraulics,      06:05:14

25   they're not looking back here at Cages Bend.            06:05:18



           Elite Reporting Services * (615) 595-0073
          9

 1                     DAN DOWNS:     Well, even at the          06:05:19

 2   intersection there, it's still below the hundred            06:05:26

 3   year flood plane and the road does flood there.             06:05:28

 4                     JOE CARPENTER:     Well, what I           06:05:28

 5   recommend too besides your comment here on this is          06:05:32

 6   if you would make out a comment card with that we           06:05:32

 7   can direct that again.     Because this process will        06:05:37

 8   continue with our hydraulic section as we continue          06:05:40

 9   with the development, they continue to do detail            06:05:40

10   study.     So, if there's some question along that way      06:05:42

11   or the City of Gallatin wants to look at this.              06:05:47

12   We're doing a partnership with them, so I would             06:05:49

13   encourage you to turn in a comment card along that          06:05:53

14   way and we'll pass that on to them.                         06:05:56

15                     NICK TUTTLE:     With your hydraulic      06:05:56

16   study, are you actually going to make a map                 06:05:59

17   amendment to the map?                                       06:05:59

18                     JOE CARPENTER:     I can't answer that.   06:06:00

19   John Zircle who is over our hydraulic section will          06:06:07

20   have to do that.     But again, if you would like to        06:06:09

21   add that in there, you know, and comment, we can            06:06:13

22   look at that and see.     But they're the ones that         06:06:16

23   will be addressing that.       So we would funnel that      06:06:18

24   question with them because they are the ones that           06:06:20

25   would provide those analysis for us.        We're capable   06:06:20



              Elite Reporting Services * (615) 595-0073
          10

 1   of doing that, but we're structured and set up that      06:06:20

 2   way where we have a specific hydraulic section.          06:06:20

 3                    When it gets to this size structure     06:06:21

 4   they're supposed to do that work for us.      We can     06:06:21

 5   look at that with John, so you can make a comment        06:06:35

 6   card.    Any comment you have from the City of           06:06:37

 7   Gallatin we can funnel to him as well.                   06:06:37

 8                    Good questions.    Any other questions? 06:06:37

 9   Well, you can ask us on an individual basis, you can 06:06:54

10   also make any comments to the court reporter, and        06:06:57

11   also I encourage you, if you don't fill it out           06:06:59

12   tonight, take a comment card or several of them with 06:07:03

13   you and mail it back in to us.      I'm going to give    06:07:04

14   you one last call on questions.                          06:07:10

15                    AARON ALLISON:    My name is Aaron      06:07:11

16   Allison and I heard you say that this is expected to 06:07:11

17   be 2009.    Is there any possibility of that being       06:07:16

18   moved up through this partnership with the city, or      06:07:19

19   is there a particular reason why it's late of 2009       06:07:24

20   and why that couldn't happen sooner?                     06:07:28

21                    JOE CARPENTER:    That's a good         06:07:30

22   question.    Typically the process that we still have    06:07:32

23   to go through to develop this is we have to develop      06:07:32

24   a set of right-of-way plans which they will acquire      06:07:32

25   the property and negotiate that.      But also while     06:07:39



             Elite Reporting Services * (615) 595-0073
        11

 1    that's going on, we have to secure permits.       And     06:07:42


 2
   part of that right-of-way process will be                 06:07:43


 3
   negotiations with the Corps of Engineers and that's       06:07:46


 4
   not been a speedy process, typically for us.              06:07:50


 5
                    And so, these timeframes are             06:07:51


 6
   estimated into this project-development schedule and 06:07:55


 7
   also time to allow us to work it out with them to         06:07:56


 8
   get the permits for this reconstruction along Cages       06:08:01


 9
   Bend and this relocation.    So that's why it's           06:08:02


10
   targeted to '09.    Theoretically if those things went 06:08:07


11
   as expeditiously as they could, it possibly could be 06:08:07


12
   moved up, but the standard procedure normally it          06:08:13


13
   doesn't happen that way.    Normally there's more         06:08:18


14
   snags that pop up than we anticipate.      But those are 06:08:19


15
   the main two things that we're dealing with.       It's   06:08:22


16
   going to have to deal with the Corps of Engineers         06:08:25


17
   and their requirements are going to have to deal          06:08:27


18
   with them for this extreme location.                      06:08:27


19
                    AARON ALLISON:   Okay.   You might have 06:08:31


20
   addressed this with your comments to Dan and I might 06:08:34


21
   not have understood completely.     You talked about      06:08:36


22
   the boring underneath the road, are you working with 06:08:37


23
   a utility district on that -­                             06:08:37

24
                    JOE CARPENTER:   Boring under what       06:08:43

25
   road?                                                     06:08:43



              Elite Reporting Services * (615) 595-0073
         12

 1                     AARON ALLISON:   Underneath that road, 06:08:46


 2
   do you have any talks about that?                           06:08:46


 3
                    JOE CARPENTER:   Well, we have an          06:08:38


 4
   existing box culvert under Gallatin Road right now.          06:08:52


 5
                    AARON ALLISON:   Okay.                     06:08:54


 6
                    JOE CARPENTER:   All we're going to do 06:08:54


 7
   is extend it underneath Cages Bend to get it to line 06:08:54


 8
   up to pick up the water from the relocated ditch.           06:08:54


 9
                    AARON ALLISON:   Okay.     I just need     06:08:54


10
   clarification on that.                                      06:08:54


11
                    JOE CARPENTER:   Okay.     Does that       06:08:54


12
   answer your --                                              06:08:54


13
                    AARON ALLISON:   Uh-huh.                   06:08:54


14
                    DAN DOWNS:   Dan Downs again.     Another 06:08:55


15
   comment.   I don't see on the plans a box culvert           06:08:55


16
   shown about 300 feet back from that intersection             06:08:55


17
   which is already improved and permitted by the Corps 06:08:55


18
   of Engineers.    Is that something --                       06:08:55


19
                    JOE CARPENTER:   From what road?           06:09:25


20
                    DAN DOWNS:   On Cages Bend.                06:09:25


21
                    JOE CARPENTER:   Okay.     Well, we can    06:09:25


22
   update our survey as we get information for that.          I 06:09:25


23
   mean, the thing about this is something has to be           06:09:33


24
   shared to us from the City of Gallatin or others for 06:09:35


25
   us to be aware of that.                                     06:09:37




            Elite Reporting Services * (615) 595-0073
              13

 1                     DAN DOWNS:   All right.   Thank you.      06:09:38


 2                     JOE CARPENTER:   Good questions.    Any   06:09:42

 3   other questions?     Well, if not I encourage you           06:09:45

 4   there's other materials, come up here, make yourself 06:09:51

 5   available, looking at the drawings, ask anyone with         06:09:56

 6   name badges any questions or myself, we'll try and          06:09:57

 7   answer them.     As you leave out if you would drop         06:10:01

 8   your comment cards in the box out there on the              06:10:01

 9   table.     And we have some free material out there         06:10:03

10   that may interest you to pick up and we encourage           06:10:05

11   you to do that as well.                                     06:10:08

12                     We also have some detailed plans over 06:10:10

13   here someone can go over with you if you have any           06:10:12

14   questions.     So, other than that, we're just going to 06:10:14

15   be here to answer your questions and just ask you to 06:10:18

16   look and share your comments with us.                       06:10:21

17                     Thank you again for coming out            06:10:22

18   tonight.                                                    06:10:27

19                     (WHEREUPON, the following comments        06:10:28

20   were dictated into the record individually:)                06:10:28

21                     DAN DOWNS:   All right.   My name is      06:14:54

22   Dan Downs and I'm the owner of the property located         06:14:54

23   at Nashville Pike and Cages Bend.      It's the subject     06:15:17

24   property where the road is going to be realigned and 06:15:17

25   there are four main concerns I have:                        06:15:30



              Elite Reporting Services * (615) 595-0073
          14

 1                   The first is that the Cages Bend          06:15:33

 2   roadway and intersection is currently below the           06:15:35

 3   hundred year flood elevation.     This should be raised 06:15:35

 4   for safety sake because at the present the road           06:15:46

 5   floods and causes traffic to have to veer when they       06:15:46

 6   hit the high water.                                       06:15:55

 7                   And then the existing Big Station         06:15:56

 8   Camp Plan does not incorporate the approved access        06:16:00

 9   by the City and the Corps of Engineers for Savannah       06:16:10

10   Marketplace 300 feet from the intersection of Cages       06:16:10

11   Bend Road.   This needs to be reflected on the plans. 06:16:17

12                    Also, in this location there needs       06:16:21

13   to be an elimination of the Corps of Engineers'           06:16:31

14   property wetlands to box culvert to contain the           06:16:32

15   water currently running through the drainage in that 06:16:43

16   location at Cages Bend and Nashville Pike.                06:16:43

17                   And it's also important to keep Cages 06:16:43

18   Bend open to traffic throughout the construction          06:16:43

19   period.   The preliminary plan did not indicate           06:17:01

20   whether Cages Bend Road would be open at all times        06:17:03

21   during construction.   Thank you.                         06:17:09

22                   I would like to give you these notes      06:17:15

23   to be made a permanent part of the record in this         06:17:17

24   matter.                                                   06:17:20

25                   RON COLEMAN:    I've got a letter, it's



           Elite Reporting Services * (615) 595-0073
           15

 1    addressed to Shane Hester from Ron Coleman on behalf


 2
   of Dan Downs with American Engineers' letterhead


 3
   basically outlining concerning that Mr. Downs has


 4
   concerning the project and we'd like to make that a


 5
   part of the permanent record.


 6


 7


 8


 9


10


11


12


13


14


15


16


17


18


19


20


21


22


23


24


25




            Elite Reporting Services * (615) 595-0073
        16
 1
                  REPORTER'S CERTIFICATE

 2


 3
   STATE OF TENNESSEE


 4
   COUNTY OF SUMNER


 5


 6
                         I, MISTY BRIGHAM, Court


 7
   Reporter, with offices in Nashville, Tennessee,


 8
   hereby certify that I reported the foregoing TDOT


 9
   HEARING by machine shorthand to the best of my


10
   skills and abilities, and thereafter the same was


11
   reduced to typewritten form by me.


12
                         I further certify that I am not


13
   related to any of the parties named herein, nor


14
   their counsel, and have no interest, financial or


15
   otherwise, in the outcome of the proceedings.


16


17


18


19


20
                ________________________________

21
                MISTY BRIGHAM

                   Notary at Large

22
                State of Tennessee

          My Commission Expires: January 2, 2011

23


24


25




            Elite Reporting Services * (615) 595-0073          17

								