SECTION 5.1
Document Sample


2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
SECTION 5.1
MACHINERY MAINTENANCE AND REPAIR ITEMS
All repair and maintenance items in Section 5.1 shall be invoiced separate from its
respective inspection item. Any additional repair items shall be added to this section to
ensure separate billing. All staging, rigging, crane charges, transportation, and
administrative overhead charges are to be broken out of each item when invoice is made.
It is understood that the above mentioned charges shall be considered incorporated in the
bid price requested and received for the following items.
[5-1] - 1
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
SECTION 5.1 - MACHINERY MAINTENANCE AND REPAIR ITEMS
5.1-1 Asbestos Abatement
(Do not start unless specifically directed by Port Engineer)
a. No later than seven (7) days prior to the projected vessel arrival to the shipyard,
supply qualified personnel to board the vessel and take insulation samples of all areas in
way of the specified repair and inspection areas as determined by the “A” & “B” Priority
items on the drydock worklist.
Samples shall be taken and labeled at each location; packaged in a two (2) small plastic
bags that shall be labeled as per the sample location, with one (1) bag being left to the
Chief Engineer while the other bag is sent out for analysis by the shipyard.
No later than three (3) days after sampling, provide a full written report to the SL office.
Consider meeting the vessel either in Elizabeth, NJ or Jacksonville, Fla..
Consider fifty (50) samples to be taken and analyzed.
Price $________________________
b. Upon vessel arrival to yard make necessary asbestos removal in way of those
areas deemed hazardous as per the samples taken and analyzed.
Note: Removal of Contaminated Insulation as described herein pertain only to
those areas in which removal of insulation is not already covered by the repair or
inspection item.
Two methods of removal to be considered. Each method may require wetting down of
area. Provide proper protection to pump motors to avoid motor damage.
b1. Glove bagging - In small local areas where glove bagging is the safest and will
prevent extensive contamination to the environment, proceed by wetting down and
removing
b1 Price per 100 CU FT _______________________
b2. Curtaining - Curtain off larger area for removals. Wet down effected areas and
remove contamination
b2. Price per 100 CU FT _______________________
[5-1] - 2
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
c. Disposal of Asbestos Removals
Provide pricing to dispose of removed asbestos whether from the original repair and
maintenance items or from additional areas as described in Note above.
Price to include disposal of coveralls and related removal consumbales.
c. Price per 100 CU FT. _______________________
5.1-2 Main Condenser Anodes
(Do not start unless specifically directed by Port Engineer)
Fabricate and install six (6) Main Condenser Anodes in the inlet head. Six (6) anodes of
approximate size of 12" x 12" square are required.
Anodes are to be fabricated out of 1" thick Swedish Steel; anodes are to be drilled with a
13/16" hole. After 3/4" N.C. threaded holes are cleaned out with a bottom tap, anodes are
to be installed with new 3/4" N.C. stainless steel bolts and washers.
Price $ _________________
5.1-3 Services for Boiler Repairs
(Do not start unless specifically directed by Port Engineer)
Certain boiler repairs will be accomplished by outside contractors. This item is to be
used for any assistance required by the yard.
The shipyard shall provide necessary burning equipment (oxy-acetylene gas), and welding
machines (arc and TIG welding), and argon gas. Crane service shall be provided for
movement of boiler maker tools, equipment and material to and from vessel. This is to
include any and all labor and transportation from boiler maker‟s container storage in yard
to and from vessel. The shipyard also shall provide container or other means to discard
the removed boiler tubes (steel scrap) and all scrap refractory material; this includes the
crane service and man-power to remove from engine room. Boiler repair items covered
in section 5.2.
Note: All services work requests shall be issued by the Port Engineer in writing.
Compressed air, welding gases, and arc welding machines must be supplied on an
around- the-clock basis while repairs are underway, 7 days per week.
Price per day $______________
Erect Staging: Both boilers will require internal staging to access upper tube area for
refractory work (corbels and baffle replacement), seal box repair and tube work..
Staging will have to be erected after water washing and scrap-out for flooring is
completed.
Price: $______________
[5-1] - 3
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
5.1-4 Water Wash Port and Stbd Boilers
(Do not start unless specifically directed by Port Engineer)
Provide labor and services (staging) to high-pressure water jet wash the Port and
Starboard Boiler firesides. Pressure wash of 10,000 psi required. All slag material shall
be removed commencing from the stack to the lower drums including the superheater
tubes, generating tubes, screen tubes, wall tubes, air heaters and baskets.
Caustic soda shall be introduced in the water to neutralize the effects of the water on the
tubes when combined with the soot.
A pump must be available to remove all water during the cleaning operation.
Do not commence this work until all refractory is removed from the furnace. Supply
portable air heaters to aid in drying out boilers after washing is complete.
Yard to dispose of all waste water resulting from boiler cleaning.
Price $ _________________
5.1-5 L.O. Pumps, Main and Emergency, Motor Overhaul
(Do not start unless specifically directed by Port Engineer)
Emergency LO Pump Motor - Emergency LO Pump
MFG DeLaval Turbine Inc. MFG Westinghouse Electric Corp
Type 3KX-410 Type SK
RPM 230 Frame 284AD
GPM 900 HP 5
Disch press 10 psi RPM 900
Serial No 317151 Volt 120VDC - 41 Amps
Main & Standby LO Service Pumps Motor - Main & Standby LO Service Pumps
MFG DeLaval Turbine Inc. MFG Reliance Electric Co
Type 3KTX-412 Frame 286TD
RPM 1750 HP 30
GPM 450 RPM 1800
Disch press 55 psig Volt 440/3ph/60 cycle
Serial No 317148 Serial No 14893795A1 KU Stbd
317147 14893795A9 KU Port
The intent of this item is to remove, overhaul and reinstall the vessel's three (3) L.O.
Pump motors. All required spares are to be owner furnished.
[5-1] - 4
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
a. Motors - Make all electrical and mechanical disconnection. Rig motor ashore to
shop. Motor to be Megger tested, disassembled, cleaned, re-coated, balanced, baked and
bearings renewed. Bearings will be owner furnished.
Clean motor/pump coupling for inspection by CSX Lines Representative. Coupling to be
changed with owner furnished coupling if required. Pump/motor coupling to be repacked
with grease prior to being assembly. Pump sleeve coupling (#013) to be renewed along
with keys if required. Special care shall be taken so as not to damage pump/motor thrust
bushing. Bushing is made of aluminum and can break easily. Chief Engineer to witness
the disassembly and assembly of the pump/motor couplings.
Upon completion of shop work, motor to be returned to vessel, rigged into place and
reconnected both electrically and mechanically. Alignment must be within 0.003 in. and
shall be witnessed by owner‟s representative.
Motor shall be pump tested to prove correct rotation. Pump shall be tested to the
satisfaction of owner‟s representative.
Price $ _________________
5.1-6 Main Circuit Breakers
(Do not start unless specifically directed by Port Engineer)
Disconnect two (2) breakers from main switchboard, and rig out of vessel for
transportation to service shop for repairs and testing under Owner's account.
When directed, take delivery of reconditioned units and reinstall in switchboard.
Price $ _________________
5.1-7 Electrical Circuit Repairs
(Do not start unless specifically directed by Port Engineer)
The intent of this item supply labor and material to repair problem circuits, i.e. grounded
etc., that were discovered during Switchboard and Controller Inspection and Testing on a
separate item. Work may also be put in hand from Vessel Thermograph survey at an
earlier date.
General Notes:
No work is to commence without a written report to and approval from CSX Lines
Representative. This item is to be worked during day shift only, as practical.
A report is to be submitted daily to CSXL Representative, on status of repairs.
Quote on Electrician per 8 hour shift,
Price $ _______________
[5-1] - 5
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
5.1-8 Engineroom Supply and Exhaust Vent Fans and Louvers
(Do not start unless specifically directed by Port Engineer)
Axial Flow Fan - System 1-179-2
Service Machinery Space Exhaust
MFG Joy Manufacturing Co.
Capacity Special
CFM 55000
RPM 1150/575
Motor - Axial Fan (02-180-1/2) Motor - Axial Fan (1-179-1&2&3)
MFG Reliance Electric Co. MFG Reliance Electric Co.
Type T.E.W.T. Type T.E.W.T.
Frame 324T Frame 364T
HP 25 HP 35/4.37
RPM 1150 RPM 1150/580
Volt 440 Volt 440
Serial No 8MA880737G1/4 Serial No 1MA880737G3
a. Provide labor and material required to remove welded vent louvers on main deck
level aft end of house (Fr180/179). Louvers are approximately (12ft x 4.5ft) fixed vane
type. Mechanically and electrically disconnect the fan housing, motor and fan impeller.
Rig unit to shop for overhauls. While fan units are in the shop for overhaul, make
necessary preparations for installation of the louvers whether the original or owner
furnished louvers are to be installed.
Upon completion of repairs rig assembled unit and install using new fasteners and gaskets
as required. Refit and weld up vent louvers. Test run motor and fan to ensure proper
rotation. All touch up coatings as required.
a. Price per fan unit - (removal, transport install) $_______________
b. While unit is in shop, overhaul fan motor. Overhaul to include disassembly,
cleaning, insulation coating repairs, baking, and balancing. Assemble unit using owner
furnished bearings.
b. Price per motor overhaul $_______________
c. While unit is in the shop remove fan propeller blading. Thoroughly clean blading.
Perform dye-penetrant check at blade roots. After blading is cleaned and dye - penetrant
shows no indications of failure, balance fan blading. Install onto shaft and prepare fan
unit to be transported to vessel.
c. Price per fan blade maintenance $_______________
[5-1] - 6
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
5.1-9 DC Heater Spray Nozzles
(Do not start unless specifically directed by Port Engineer)
DC Heater - Aqua Chem - Model 240
During inspection of DC Heater as found earlier in this specification, while all (11) spray
nozzles are removed, replace same with owner furnished spares. Ensure and prove that
all spring tensions and pressure settings are as per Aqua-Chem recommendations.
Price $_______________
5.1-10 Removal and Replacement of the (Fwd) LP/LS Quill Shaft Coupling
(Do not start unless specifically directed by Port Engineer)
The intent of this specification is to disconnect and remove the Low Pressure (LP)
Turbine Low Speed (LS) Coupling Quill shaft and corresponding Hub for renewal with
Owner furnished spare. The quill shaft is located within the hollowed low speed pinion
and will require lifting of the Main Reduction Gear Casing.
Note: As a precaution, all machinists working this item shall be sure to remove all items
from their shirt pockets before commencing any work near or around open gear and
coupling covers.
All work areas shall be clean and remain clean throughout the replacement process, so as
not to contaminate engine parts, gearing, bolting etc. Tenting may be required if boiler
work is in progress overhead.
Gear inspection covers shall only be opened in the presence of the Owner Representative.
All gear inspection covers shall be cleaned and promptly restored to their respective
positions upon completion of inspections. All items shall be left covered when not being
worked on. Good, sound and proper machinist practices shall apply.
Remove all necessary interference‟s. Interference‟s include but are not limited to; piping,
deck plating, vent duct work, electrical cables, lighting fixtures, handrails, etc. All oil
and steam piping shall be protected at either end to maintain a contaminant -free
environment. Carefully disconnect control cables all monitoring equipment wiring .
Equipment, wiring etc. shall be labeled to expedite proper and accurate installation upon
completion of the inspections.
All necessary bearing clearances, axial, radial and thrust clearances shall be taken and
records provided as required by Owner‟s Representative.
[5-1] - 7
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
a. LP LS Coupling Replacement and Renewal
Prior to disassembly, check and record axial movement and spline backlash. All
clearances must be taken, recorded and supplied to the Owner‟s Representative. All
coupling pieces are to be properly match-marked before lifting them out and returned to
this position when installing.
Unbolt and remove necessary end covers to access the LP LS flexible coupling hubs.
Unbolt and remove necessary quill shaft upper and lower covers in way of the forward
and after quill shaft flanged joint. Clean as practical.
Upon completion of inspection and when directed, rig coupling covers in-place and
install using new gasketing and approved sealant as required..
Disconnect hub coupling bolts at the forward end. Rig aside both forward and after hubs.
Transport hubs to workshop for inspection. While in workshop, hubs shall be cleaned
and dye-penetrant checked in way of all contact surfaces.
Disconnect coupling bolts between forward and after quill shafts.
Release and remove gear box top cover bolting. Lift up gear box cover. Care shall be
taken to lift gear box simultaneously at all four corners. Eventually gear box shall be
lifted slightly higher on the port side to allow for access to remove hollow pinion gear
shaft and corresponding after quill shaft.
Open up both forward and after bearing housing top covers, for access to support 2nd
Reduction pinion. Confirm initial bearing clearances. When shaft is supported, roll out
bottom halves of these bearings.
Rig out 2nd Reduction pinion to gain access for removal of forward inner quill shaft.
Draw out after inner quill shaft from the hollow pinion gear shaft and transport to work
shop for inspections.
While in workshop, after quill shaft shall be set up in a lathe for trueness confirmation.
Dye-penetrant check at shaft ends for fretting indications. Upon completion of
inspections, polish contact surfaces as necessary and return shaft to vessel for installation.
Draw out defective forward inner shaft from the 1st Reduction pinion for the LP Turbine
reduction gear box and transport to workshop for inspection.
While in workshop, forward quill shaft shall be dye-penetrant checked in way of spline
teeth and shaft ends. Upon completion of inspections, the forward quill shaft shall be
[5-1] - 8
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
covered in preservative, crated and returned to vessel. Crate provided for transporting
newly furnished spare may be used for this purpose.
Temporarily protect all openings with plastic sheet and remove afterwards.
After completing surveys and inspections as outlined in parts (b & c) of this specification,
collect from workshop Owner‟s supplied spare forward quill shaft with coupling hub.
Transport to vessel for installation.
Install Owner‟s supplied spare forward inner shaft to its corresponding 1st Reduction
pinion. Install after quill shaft into 2nd Reduction pinion. Install 2nd Reduction pinion
assembly into main propulsion gear train. Verify seating of shafting and pinion within
the gear train.
Refit bottom halves of bearings and closing up top halves ensuring that all clearances
remain even. Final bearing clearances to be measured and recorded.
Clean and prepare top and bottom edges of the gear casing joint. Lower down top cover
and tighten up all connecting bolts.
Install and tighten all coupling bolts between forward and after inner quill shafting.
Return forward and aft coupling hubs and rig into place. Secure all hub coupling bolts.
Coupling and Hub securing bolts shall be safety wired. Prove proper coupling float and
confirm final backlash readings to Owner‟s Representative.
Refit forward and aft hub covers.
Refit all interference‟s in way of the main propulsion gear box.
Price $ _________________
b. Take delivery of Owner furnished spare forward LP LS quill shaft and
corresponding hub. Prior to installation, clean all preservatives, confirm trueness and
dye-penetrant check all shaft spline and hub gear teeth. Check for hub to shaft backlash
and record findings. Present all inspection information in writing to Owner‟s
Representative.
Price $ _________________
c. While in the workshop, confirm that all bored holes for the forward and aft quill
shaft to be installed match their respective dimensions and locations. If holes are found
to be different, re-drill and/or ream holes to fit all hardware as necessary. For estimating
purposes use (12) holes x (1.5)inches diameter.
Price $ _________________
[5-1] - 9
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
d. Take delivery of Owner furnished spare aft LP LS quill shaft and corresponding
hub. Prior to installation, clean all preservatives, confirm trueness and dye-penetrant
check all shaft ends and contact areas. Present all inspection information in writing to
Owner‟s Representative.
Price $ _________________
e. Open bolted reduction gear inspection covers as required to survey all gears.
Check spray pattern of all oil nozzles. Any nozzles found plugged are to be removed
and cleaned.
Upon completion of inspection and when directed, install reduction gear inspection
covers. Bolt and lock in the presence of the owner‟s representative.
Price $ _________________
5.1-11 Third and Forth Stage Heater Breech Lock and Partition Plate Gasket
(Do not start unless specifically directed by Port Engineer)
The intent of this item is to open the steam side of the third and forth stage heater to
permit access to the heater partition cover for possible change out or repair of same.
Third Stage Heater Data:
Mfr Aqua Chem
Type HP Feedwater Heater
Model 4V - 136C
S/N SP70-10404
The breechlock design makes use of the high pressure feedwater to form a leak proof seal.
The incoming feedwater forces the cover up against an annealed copper gasket. The
copper gasket, similar to a piston ring, is expanded radial between the channel barrel and
the cover to form a seal. The pressure differential between the inlet and outlet water seals
the pass partition cover to seal the pass partitions.
Prior to disassembly of the breech lock, the heater shall be secured from service and
completely drained and vented. All work on the cover and breechlock will be from below
the unit, therefore it is imperative that suitable rigging is provided, that will hold the
cover and keep it from falling. Make necessary removals for access to heater, cover and
breechlock
Remove the channel bar. Carefully pry the Positioning ring loose form the cover. Loosen
all capscrews on the Split Retaining Ring and remove all but two from each of the four
sections. These remaining capscrews will hold the split ring in place as the cover is
jacked to relieve the pressure.
[5-1] - 10
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
Set up suitable staging for fitting a jack beneath the heater cover plate. The jack is to be
used to press the cover up into the heater to release the pressure holding the split rings in
place. When the cover has been backed off sufficiently to gain allow for the removal of
the split ring, remove split retaining ring sections.
Remove channel ring. If copper gasket is free remove it and remove cover as follows:
Rig cover to prevent it from falling (est. weight - 400lbs). Carefully, pull cover straight
out ensuring that the cover is square at all times and does not get cocked or else it will
jam.
If the copper gasket is not free, the four sections of the retaining ring must be set up to be
used as strong backs to allow for the careful pulling of the cover.
NOTE: It is extremely important to keep the cover square and even as it is
removed. The tolerances between the cover and the heater shell are extremely tight. Any
deviation will cause the cover to jam. A jammed cover will make disassembly and
assembly IMPOSSIBLE!
With the cover removed only the inlet pass of the tubes are revealed. Remove the bolts
from the pass partition plate. Remove partition plate and gasket.
Take possession of owner furnished spare gaskets and renew. Assemble partition plate
and breechlock in reverse of above. Use Molycoat G Lubricant or a similar lubricant on
the cover and inside of the channel to assist with assembly. Hi Temp Anti-seize to be
applied to all bolting.
Upon completion hydrostatically test heater to prove that the breechlock is leak-free.
Restore all removals to original.
Price / heater (3rd or 4th) $ _________________
5.1-12 Main Condenser Maintenance
(Do not start unless specifically directed by Port Engineer)
Main Condenser Data:
Mfr: Foster Wheeler
Design: MARAD C6-5-85A FL1
MARAD C6-5-85B APL
Condensing Surface 21,750 sq.ft.
Number of Passes [1]
Number of Tubes 5,540
Tube Size 3/4 in. O.D. x 18 BWG
Tube Material 90/10 CUNI Mil - T - 1005
Eff. Tube Length 20 ft - 0 in.
[5-1] - 11
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
Provide labor equipment and materials to perform main condenser maintenance as
described below. In all cases condenser doors shall be open for entry into both the water
box and tube nest areas as required.
Condenser shall not be left unattended while doors are off.
Box up condenser doors upon completion of repairs, using new gaskets.
a. Take delivery of owner furnished tube end shields. Shields shall be of 70/30
CuNi in construction and approximately 10 inches in length. Shields shall be installed
over existing tube ends on the condenser inlet side by deep rolling.
All tube areas in way of the tube inserts shall first be made clean by wire brush polishing.
When a clean surface is achieved, insert the shield into the tube. For CuNi insert deep
rolling at the inner end of the shield and shallow rolling at the tube sheet shall be required
to hold the end shields in place.
For estimating purposes figure 5,540 tube shields to be installed.
a. Price $_________________
b. Upon completion of inserting tube end shields, the Condenser shall be shored up
and supported from below („cribbing‟). Fill condenser on the condensate side with water
to just below the LP Turbine Blading. Perform a blue light hydro to prove the condenser
tight. Upon successful hydro drain condenser and make ready for light off.
b. Price $_________________
c. After identifying a leaking tube, identify both ends of the tube and prepare for
tube plugs. Plug leaking tube.
c. Price $_________________ (per tube)
d. Upon completion of a satisfactory hydro test, drain all water from the condensate
side and dry out the inlet and outlet water boxes. Prepare the tube sheet for coating by
sandblasting to SA 2.5 near white. Fill in all pits with tube sheet rebuilding compound.
Apply (2) coats of (2) part epoxy, allowing sufficient time for drying between coats and
before immersion as required by manufactures product data sheet. Heat lamps may be
required to accelerate cure time, provide heat lamps as required.
d. Price $_________________
Note: Owner reserves right to use owner furnished subcontractor for main
condenser tube work.
[5-1] - 12
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
5.1-13 Combined First Stage Heater, Gland condenser & Drain Cooler Packing Renewal
(Do not start unless specifically directed by Port Engineer)
The first stage heater, gland condenser and drain cooler are combined together as (1) one
unit. Unit data as described below:
Combined 1st Stg Htr, Gland Cond., & Drn Cooler Data:
Mfr: Foster Wheeler
Design: MA C6-S-85a
Dwg. No. 58-849-4-6/7
No. of Tubes:
1st stage heater 432
Gland Condenser 72
Drain Cooler 72
Total 576
Tube Size: 0.675 inch O.D. x 18 BWG x 9 ft - 5.5 inches
Hydro Press. Shell side 45psig
Tube side 188psig
a Provide necessary materials, equipment and labor to perform packing and ferrule
renewal on the combined heat exchanger described above.
Remove both water box covers to expose tube ends. Drill out old ferrules and pull old
packing. Tap new holes for new owner furnished ferrules. (approx. size of ferrule -
0.675 in OD). Insert a minimum of two (2) pieces of owner supplied packing. Screw in
ferrule and make secure.
Upon completion of packing renewal hydrostatically test the heat exchanger in the
presence of the owner‟s representative, to prove heat exchanger is leak-free. Install water
box covers using new packing and gaskets as appropriate.
a. Price $________________[total 576 tubes]
b. Tube plugging - If discovered during hydro test that a tube or tubes are leaking,
identify both ends of the leaking tube and plug same. Water box removal and restoration
required.
Upon completion of tube replacement, hydro test heat exchanger in the presence of the
owner‟s representative to prove leak-free installation. Install water boxes and make ready
for light off.
b. Price $_________________[per tube]
[5-1] - 13
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
c. Tube renewal. If requested, renew tube as per preferred method below. While
both water boxes are removed, carefully crimp each expanded joint until the tube is loose
and free ensuring that the tube sheet does not get damaged. Remove packing on packed
end of tube. Insert tube replacement rod and withdraw old tube. Clean surface of the
tube hole removing all burrs. Polish the ends of the new tube and insert same over the
lead rod, guiding it through the support plates into the far tube sheet. Allow 0.066 inches
to extend beyond the tube sheet on the packed end of the tube.
Hold new tube in place by slipping a spacer or ring of packing over the tube at the
discharge end. Expand the tube on the inlet end, finish packing the discharge end.
Complete the inlet end by belling the tube end. Care should be taken when rolling and/or
expanding and belling so as not to damage the new tube.
Upon completion of tube replacement, hydro test heat exchanger in the presence of the
owner‟s representative to prove leak-free installation. Install water boxes and make ready
for light off.
c. Price $_________________[per tube]
5.1-14 HP Turbine Nozzle Block Replacement
(Do not start unless specifically directed by Port Engineer)
a. While the HP turbine casing is open and HP Turbine rotor is lifted as described in
Item No. 4.1-1, remove the HP Nozzle block from the casing for renewal.
Nozzle block is in four (4) segments. Each segment must be unbolted from the casing.
Take delivery of the owner furnished nozzle block segments. Lap segments into casing.
Check nozzle block fit by blue checking. Fit must be 100% contact. Fitting shall be
witnessed and to the satisfaction of the Port Engineer and Owner‟s Representative.
Secure nozzle block with bolting as original. Ensure even and adequate torque on each
bolt.
a. Price $_________________
b. While the HP turbine casing is open and HP Turbine rotor is lifted as described in
Item No. 4.1-1, remove the Curtis Stage stationary blading from the casing for renewal.
Curtis stage blading shall be removed by releasing securing screws at the horizontal joint
and rolling out the upper and lower halves.
Clean out Curtis stage blading seating surface in the upper and lower casing. Fit the
Curtis blading and set at the proper height to ensure proper clearances. Complete the
installation of the owner furnished Curtis stage blading by re-securing the horizontal
locking screws
[5-1] - 14
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
Installation of the blading to be performed under the direction of the Owner‟s
Representative.
b. Price $_________________
5.1-15 M.E. Flange Gasket Renewals
(Do not start unless specifically directed by Port Engineer)
The intent of this item is to renew bleed line flange gasketing at attachment to the Main
Engine. This to include four(4) flanged attachments, three(3) at H.P. Turbine and
one(1) at the LP Turbine, as follows:
Extraction #1 (H.P. Turbine Bleed to 4th Stage Heater) ------ 3"-600#
Extraction #2 (H.P. Turbine Bleed to 3rd Stage Heater) ------ 4"-300#
Extraction #3 (H.P. Turbine X-Over Bleed to Aux Exh) ------ 6"-150#
Extraction #4 (L.P. Turbine Bleed to 1st Stage Heater) ---- 12"-150#
Removals -- Lagging and interferences to be removed as necessary.
Inspection -- upon bolting and gasket removal, gasket removed and flange surfaces to be
inspected by CSXL Representative to determine if flange surfaces are in the need of
repair.
Coordination of Work -- if flange clean-up and/or repairs to be scheduled in conjunction
with Bleed Valve removals to facilitate rigging of pipe lines for access to flange
surfaces.
Repairs -- flange surfaces that are wire-drawn, cut, and/or heavily pitted to be repaired
as/per CSXL Representatives under a separate item.
Gaskets to be made up with Vessel furnished bolting, anti-seize, gaskets and sealant as
required. All bolting to have liberal amounts of anti-seize placed on threads.
Price $_____________
5.1-16 Engine Valve Repairs
(Do not start unless specifically directed by Port Engineer)
The intent of this item is to supply the labor and material to remove several large Valves
out of Engine Room for testing and repairs as necessary, then return to Vessel and
install as/per original.
[5-1] - 15
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
(Special Note: Superheated Steam Line to Main Engine. is to be hydrostatically tested
on a separate item. Some valves will have to be back in place and made up for Test to
be performed. Boilers will also be hydro tested under a separate item and some of the
valves will be required back in for those tests.)
General Notes:
1. Work Authorization -- All work to be approved by CSXL Representative prior to
initiating.
2. Work Standards -- All work to be to the satisfaction of the ABS, USCG and
CSXL Representative.
3. Testing -- All Valve tests to be performed on both sides of the valve disk to
prove disk/seat tight and packing/bonnet gasket tight, both prior to repairs and
after repairs. Pressure tests to be witnessed by CSXL Representative.
4. Bonnet Gaskets and Packing -- to be vessel furnished.
5. Steam Flanges -- All Steam Cuts, Pitting, or other damage to be repaired as/per
CSXL Rep. Flanges to be made up, as original, with new Vessel supply gaskets
and bolting.
Valves Repairs
Write-up will be for one(1) valve but will apply to all the valves listed below.
Removals -- Lagging blankets to be remove carefully and place in plastic bags, then
labeled and stowed for replacement on valves after valve repairs and line hydrostatic
testing (to be performed on a separate item) is completed. (Note: Dilapidated and/or
damaged Insulation Blankets are to be brought to the attention of the Port Engineer or
Chief Engineer as new blanket may be installed under a separate item.)
Line Supports -- Steam Lines to be supported properly for valve to be removed from
line so that no undue stress is to be placed on associated piping, valves, and/or
machinery adjacent to valve including spring hangers/pipe supports.
Valve to be rigged properly, disconnected, and removed to Valve Shop for testing and
repairs.
Valve is to be hydrostatically tested prior to repairs to ascertain extent of repairs in the
presence of a CSXL Representative. CSXL Representative and Valve Repair
Representative to agree on scope of work prior to valve being opened.
Valve “Hammer Wheel” Operators, similar to M.E. Stops, to be disassembled,
completely cleaned up, rough areas to be “dressed”, new Yard furnished bearings
installed, parts lubricated and reassembled as original.
[5-1] - 16
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
Valves to be opened and thoroughly cleaned, seat/disk contact area “blued”, inspected
for cracks, body around seats to be dye-penetrant to check for cracks, repairs to be
made as necessary.
Valve bonnet joint and inlet/outlet flanges to be thoroughly inspected for steam cuts
and/or erosion and repaired as necessary. Packing gland box on bonnet to be “dressed”
and repaired as necessary to bring area back to original dimension.
Stem is to be removed from bonnet, checked for trueness, disk to stem connection to be
checked and excess clearance to be repaired. Stem to be cleaned up and “dressed” and
repaired as necessary so that packing area is as original dimension.
New Yard Furnished, high quality, wire inserted, steam packing to be installed in valve
(similar to Chesterton 1500 Power Plant).
Valve to be reassembled as original and hydrostatically tested to CSXL Rep.
satisfaction.
Valve to be transferred back to the Vessel and installed as original.
a. M.E. (Main Engine) Steam Stop Valves
8”-900# Superheated Globe Stop Valves – Two (2), One(1) each, Port and Stbd --
Valves are as follows: Globe, flanged, stop valve, ASA B16.10 cast CrMo Stl., ASTM
A-217 GR.WC6, with press-seal bonnet, SS trim, stellite faced disc & seat, with 3/4”
bypass valve connections and bottom drain connection, similar to an Edwards
Fig.#4016, I.S. Code #19-07004-01 Item #4.
Price $______________
b. Inboard Feed Pump(#1) Discharge Stop Valves, Main and Auxiliary
6”-600# Globe Stop-Check Valves -- Two(2), one(1) Main Feed Line Discharge Valve
and one(1) Auxiliary Feed Line Discharge Valve -- Valves are as follows: Globe Stop-
Check, flanged, cast steel, ASTM-A-216 GR WCB, with SS trim, stellite faced seat and
disk, similar to an Edwards Cat.V300-R1, Fig.#604, I.C.#C21-7098-01.
Price (both valves) $______________
c. Aux. Feed to Main Feed Line Cross-Over Valve (3rd & 4th Stage Feed Heater
Bypass)
[5-1] - 17
2001 Rev-1 CSX C8e (TO_NV) DD Specification 2001
05/04/10a369aea1-e8e6-4a2e-b29d-bf66be259eec.doc
05/04/10 CJ
6”-600# Globe Stop Valve -- One(1) Feed Line Cross-Over Valve -- Valve is as
follows: cast steel, ASTM A-216 GR WCB, with SS trim, stellite faced seat and disc,
similar to an Edwards Cat.#V-300-R1 Fig.#618 Valve.
Price $______________
d. Superheater Attemperater Control Stop Valves
4”- 900# Globe Stop Valves -- Four (4), two(2) on Port Boiler Attemperater Loop and
two(2) on Stbd Boiler, Valves are as follows: Globe Stop Valve, flanged, ASA B16.10,
cast Cr-Mo steel, ASTM A-217 GR WC6, pressure seal bonnet, stainless steel trim,
stellite faced disc and seat, similar to Edwards Fig.#1028 Valve.
Price $______________
e. Turbo-Generator Stop Valves
3”-900# Superheated Stop Valves -- Two (2), one(1) Port and one(1) Stbd -- Valves are
as follows: Globe Stop Check Valve, flanged, ASA B16.10, cast Cr-Mo Stl., ASTM
A-217 GR.WC6, with press-seal bonnet, SS trim, stellite faced disc & seat, similar to an
Edwards Fig.#4006 Valve, I.S. Code #19-07004-01 II8.
Price $______________
[5-1] - 18
Related docs
Other docs by oxr14149
Get documents about "