									FORM 85
\
EXTENSION OF TIME CLAIM
mainbrace
084.0361.0011.0110
CLAIM NO. 003
TO: Dexter Properties P/L	
PROJECT: 176 South Creek Road -
Dee Why	
ATTENTION:
John Phillpott
23/04/01
No. 253
DATE:
DATE OF DELAY DELAY CLAIMED REFERENCE DOCUMENTS
CAUSE OF DELAY
VARIATION
AS2124- 1992 Clause
35.5 (a)		
20/4/01
1/2 Day
INCLEMENT WEATHER
■ . .-.v.
SUPPLY OF INFORMATION
AS2124 -1992 Clause
35.5 (a) 	
18/4/01
1 Day
INDUSTRIAL/SAFETY
OTHER
1 >2 Days
THIS CLAIM
DETAILS:
In accordance with the General conditions of contract AS2124 - 1992, we submit the
above claim for Extension of Time.
•	The Workers Compensation Dispute included a stoppage on-site on
Wednesday 18th April 2001. Mainbrace Constructions lost a full day due to
these industrial conditions.	
•	Inclement Weather delayed the lifting of tilt panels on Friday 20th April 2001.
ARE COSTS APPLICABLE TO THIS CLAIM? YES /-NO
f
t
HAVE THE COSTS BEEN INCLUDED IN A VARIATION YES / NO
WW
Mainbrace Constructions Pty Ltd
30/08 / 01
SUMMARY
ORIGINAL COMPLETION DATE:
30/08/01
EOT APPROVED
AMENDED CONTR. COMPL DATE:
5 Days
AWAITING APROVAL
1 Vz Days
THIS CLAIM
6 Vz Days
TOTAL TO DATE
CLIENT USE
APPROVAL REF NO.
TIME APPROVED
AUTHORISED BY
DATE
,^\ MAINBRACE CONSTRUCTIONS PTY LTD A.C.N. 002 970 658
64 CHANDOS STREET, ST. LEONARDS NSW 206S
P.O. BOX 1620, CROWS NEST 1620
TELEPHONE (02) 9438 1666 FACSIMILE: (02) 9438 1777
FORM 85
Page 1 of 1
Amend
Date
Issue
-3
0
02.06.98
A
M AiNflfi * C.
i

								
To top