					State of California - Department of Transportation
EXTRA WORK BILL (SHORT FORM)
                                                                                                                                 Contract No.                CCO NO.
Date Performed :d: 12/272007                         Date of Report : 01/07/2008                        Cont. Job No.:           Cont. RPT NO.
WORK PERFORMED BY : Elijah Electric
DESCRIPTION OF WORK: Instal hot melt on top asphault lift due to staging confliction                                     versus asphault emulsion per original bid
                                             EQUIPMENT                                                                                                        LABORERS, FOREMANS, etc.

     Equip             EQUIPMENT            Code              Hours/               Hrly/Dly   Delay       Extended        P.R.                 LABOR              Hours             Hourly Rate             Extended
      No.             CLASS/MAKE                               Units                Rate      Factor       Amount         No.                                  Reg     O.T.       Reg       O.T.            Amount
                   Hot Melt Machine                             1                  $289.00                     $289.00
     TK-09         truck                                        10                  $23.63                     $236.30




                                                     Equipment Sub-Total                                   $525.30                                                              Sub-Total

                                       MATERIAL and/or WORK done by specialists
                                                                                                                         Labor Surcharge                       Reg.       17%     O.T.            16%
                     Description                               Units               Unt Cst             Total             Subsistence
Hot Melt Bricks                                                 6                    35                     $210.00
             credit asphault emulsion                           -3                   45                    -$135.00
                  propane 20 gallons                            1                    45                      $45.00

                                                                                                                         Travel Expense
                                                                                                                         Other
                                                                                                                         Total Cost of Labor
                                                                                                                         Total Cost of Equipment                                                                  $525.30
                                                                                                                         Total Cost of Material                                                                   $120.00
                                                                                                                         Markup on Labor Cost (33%)
                                                                                                                         Markup on Equipment (12%)                                                                    $63.04
                                                     Material & Specialist Sub-Total                       $120.00       Markup on Material (15%)                                                                     $18.00


                                                                                                                         Total This Report                                                                     $726.34




      193ca8b8-13ea-44cb-b97a-dc5f02d71151.xlsForce Account Analysis                                                                                                                              4/23/201010:42 AM
                                                                          Sheet1



DATE                               10/18/1996 10/21/1996 10/22/1996 10/23/1996 10/24/1996 10/25/1996 10/26/1996 11/2/1996 11/5/1996 11/6/1996 11/7/1996 11/12/1996   TOTAL

LAB         DRILLER       $35.95          10          3          8         8          8          6         6          3         7         9.5       6.5        10        85
            HELPER        $30.83          11          3          8         8          8          6         6          3         7         9.5       6.5        10        86
            LABORER       $30.83                      3                                                               3                                                   6

EQUIPMENT   DRIL. RIG.   $100.00          10          3          8         8          8          6         6          3         7         9.5       6.5        10        85
            TRUCK          $6.67          11                                                                                                                             11
            TRUCK         $11.61          10          3          8         8          8          6         6          3         7         9.5       6.5        10        85
            WATER TANK     $2.82                      3                    8          8          6         6          3         7         9.5       6.5        10        67

MATERIAL    PIPE           $0.75         250          0       500          0          0       450       1500        300       600          0        600      1800      6000