					Mosman Municipal Council

  RISK MANAGEMENT
     ACTION PLAN
                  Mosman Municipal Council
                  RISK MANAGEMENT ACTION PLAN


                                             CONTENTS
SECTION   TOPIC                                                                                                    PAGE

 1.       SCOPE .............................................................................................................1

 2.       APPLICATION OF RISK MANAGEMENT ........................................................1

 3.       DEFINITIONS ...................................................................................................1

 4.       OBJECTIVES: ..................................................................................................2

 5.       RISK MANAGEMENT PROCESS ....................................................................3
                 5.1      Establish the Context ......................................................................3
                 5.2      Identify Risks...................................................................................3
                 5.3      Analyse Risks..................................................................................3
                 5.4      Evaluate Risks ................................................................................3
                 5.5      Treat Risks ......................................................................................3
                 5.6      Monitor and Review ........................................................................3
                 5.7      Communicate and Consult..............................................................3
 6.       ROLES & ACCOUNTABILITIES.......................................................................4
                 6.1      All Employees Generally .................................................................4
                 6.2      General Manager ............................................................................4
                 6.3      Director Corporate Services............................................................4
                 6.4      Directors..........................................................................................4
                 6.5      Managers and Supervisors .............................................................4
 7.       RISK ASSESSMENTS .....................................................................................5

 8.       RISK REGISTRATION, TREATMENT AND REPORTING...............................5

 9.       REVIEW STRUCTURE ....................................................................................6

 10.      ASSOCIATED COUNCIL POLICIES AND DOCUMENTS ...............................6

 Appendix 1      Risk Definition and Classification..............................................................7

 Appendix 2      Risk Register...........................................................................................22

                  Template 1 - Identifying and Analysing Risks ........................................22

 Appendix 3      Risk Treatment Schedule & Plan ............................................................23

                  Template 2 - Risk Treatment Schedule and Action Plan .......................23
                     Mosman Municipal Council
                     RISK MANAGEMENT ACTION PLAN

1.   SCOPE

     This policy applies to all areas of Council’s operations, and covers risk of financial loss,
     injury to employees and/or members of the public, damage to equipment and property,
     and loss of reputation.

2.   APPLICATION OF RISK MANAGEMENT

     The risk management process will apply to the following areas:
     a)       strategic, operational and business planning processes, including policy
              development and project management;
     b)       asset management and resource planning;
     c)       management of ethics, fraud, security and probity issues;
     d)       business interruption and continuity management;
     e)       management of significant change issues – eg. organisational and technological
              changes;
     f)       public risk and general liability risks;
     g)       occupational health and safety risks;
     h)       environmental management;
     i)       purchasing and contract management;
     j)       financial management

3.   DEFINITIONS

     Residual risk

     The remaining level of risk after risk treatment measures have been taken into account.

     Risk

     The chance of something happening that will have an impact upon objectives.            It is
     measured in terms of consequences and likelihood

     Risk acceptance

     An informed decision to accept the consequences and the likelihood of a particular risk.

     Risk analysis

     A systematic use of available information to determine how often specified events may
     occur and the magnitude of their consequences.

     Risk assessment

     The overall process of risk analysis and risk evaluation.




                                            Page 1 of 25
                    Mosman Municipal Council
                    RISK MANAGEMENT ACTION PLAN


     Risk control

     That part of risk management that involves the implementation of policies, standards,
     procedures, and physical changes to eliminate or minimise adverse risks.

     Risk evaluation

     The process used to determine risk management priorities by comparing the level of risk
     against predetermined standards, target risk levels or other criteria.

     Risk identification

     The process of determining what can happen, why and how.

     Risk management

     The culture, processes, and structures that are directed towards the effective
     management of potential opportunities and adverse effects.

     Risk management process

     The systematic application of management policies, procedures and practices to the tasks
     of establishing the context, identifying, analysing, evaluating, treating, monitoring and
     communicating risk.

     Risk treatment

     Selection and implementation of appropriate options for dealing with risk.

4.   OBJECTIVES:

     The objectives of Council’s risk management action plan are to:
     a)       formalise and enhance existing risk management practices within Council;
     b)       demonstrate compliance with relevant legislation and regulatory requirements;
     c)       to integrate the management of risk across key Council functions and areas of
              responsibility;
     d)       raise the profile of risk management at all levels of Council, including elected
              members;
     e)       to reduce the cost of risk, including injury, cost of insurance premiums, damage
              and loss to Council and the community;
     f)       to develop and retain a risk register to facilitate the understanding of Council’s
              risks;
     g)       to demonstrate and promote good corporate governance;
     h)       to improve community confidence and trust;
     i)       to achieve a proactive rather than a reactive approach to risk management.




                                          Page 2 of 25
                       Mosman Municipal Council
                    RISK MANAGEMENT ACTION PLAN

5.    RISK MANAGEMENT PROCESS

      The main elements of the risk management process are the following:

5.1   Establish the Context

      Establish the strategic, organizational and risk management context in which the rest of
      the process will take place. Criteria against which risk will be evaluated should be
      established and the structure of the analysis defined.

5.2   Identify Risks

      Identify what, why and how things can arise as the basis for further analysis.

5.3   Analyse Risks

      Determine the existing controls and analyse risks in terms of consequence and likelihood
      in the context of those controls. The analysis should consider the range of potential
      consequences and how likely those consequences are to occur. Consequence and
      likelihood may be combined to produce an estimated level of risk.

5.4   Evaluate Risks

      Compare estimated levels of risk against the pre-established criteria. This enables risks
      to be ranked so as to identify management priorities. If the levels of risk established are
      low, then risks may fall into an acceptable category and treatment may not be required.

5.5   Treat Risks

      Accept and monitor low-priority risks. For other risks, develop and implement a specific
      management plan which includes consideration of funding and introduces strategies to
      ensure new risks are not introduced.

5.6   Monitor and Review

      Monitor and review the performance of the risk management system and changes which
      might affect the performance.

5.7   Communicate and Consult

      Communicate and consult with internal and external stakeholders as appropriate at each
      stage of the risk management process and concerning the process as a whole.




                                           Page 3 of 25
                     Mosman Municipal Council
                     RISK MANAGEMENT ACTION PLAN


6.    ROLES & ACCOUNTABILITIES

6.1   All Employees Generally

      All staff have responsibilities for managing the risks in their activities and workplace and
      are accountable through their individual work plans and within MOSPLAN.

      It is recognised that all Council staff are fully involved and best informed as to the risks
      associated with their designated activities. All employees are required to cooperate and
      be actively involved in the development and implementation of the risk management
      program. This collaborative approach will ensure a quality system delivering measurable
      outcomes.

6.2   General Manager

      The General Manager is responsible for ensuring that a risk management system is
      established, implemented and maintained in accordance with this policy, and for the
      assignment of responsibilities in relation to risk management.

6.3   Director Corporate Services

      The Director Corporate Services, being the Risk Manager, is responsible for oversight of
      the risk management process and compliance with Risk Management Action Plan; for
      support of Management and their staff in implementing risk management initiatives; for
      establishment of a Risk Register; for facilitating the provision of training and education of
      Council employees; and status reporting to senior staff in regards to risk profile and
      mitigation strategies.

6.4   Directors

      Facilitating and resourcing to enable their Departments compliance with Risk
      Management Action Plan, measuring performance of staff against strategies in MOSPLAN
      and KPI’s in individual work plans.

6.5   Managers and Supervisors

      Managers and Supervisors are responsible for the implementation of the Risk
      Management Policy and Risk Management Action Plan within their respective areas of
      responsibility. This includes the identification, assessment, recording and reviewing of
      risks, establishment of controls through systems and processes and the assignment and
      completion of risk control actions.

      Managers will report to their Director on the status of the implementation of their
      respective Risk Management Action Plan at their regular Manager’s Meetings and refer
      matters to Directors when additional resourcing is required on an as needs basis.




                                            Page 4 of 25
                    Mosman Municipal Council
                    RISK MANAGEMENT ACTION PLAN

7.   RISK ASSESSMENTS

     Council is committed to identify, eliminate and manage its risks.

     All managers have a responsibility to involve their staff within this process.

     The following areas have been identified in which to conduct and document risk
     assessments:
     •   Assets & Infrastructure
            !     Buildings
            !     Roads
            !     Footpaths
            !     Drainage
            !     Street furniture
     •   Contract Management
     •   Corporate Governance
     •   Legislative compliance
     •   Plant & Equipment
     •   Tasks & Functions
     •   New Projects & Special Events

8.   RISK REGISTRATION, TREATMENT AND REPORTING

     Relevant staff will be trained to use the necessary tools to undertake risk assessments.
     These tools include:
          •   Risk assessment process
          •   Risk assessment template
          •   RiskEMap

     The risk assessment process is defined in the form of a detailed flowchart which includes
     the following:

         •    Identify the item to be assessed
         •    Establish the consultation group
         •    Identify the hazard/risks and existing controls
         •    Undertake risk rating
         •    Identify if required, additional controls/actions
         •    Sign off or acceptance by Director.
         •    Allocate action/controls and schedule review period
         •    Review assessment




                                           Page 5 of 25
                      Mosman Municipal Council
                      RISK MANAGEMENT ACTION PLAN


9.    REVIEW STRUCTURE

      This policy shall be reviewed annually to ensure that it meets the requirements of
      legislation and the needs of Council.

      The respective risk assessments will be reviewed in accordance with scheduled review
      identified for each assessment. This review will vary from six months to a maximum of 3
      years depending on the level of risk.

      Unplanned reviews may be triggered by incident, new technology, legislation/regulation
      changes, and variation in resources or community use/demand.

      All reviews will take into account hazard and incident reports, complaints and any other
      information affecting the risk.

10.   ASSOCIATED COUNCIL POLICIES AND DOCUMENTS
      MOSPLAN
      Future Mosman
      Risk Register
      OH&S Policy
      Hazard/Incident Reports
      Code of Conduct
      Code of Meeting Practice
      Statement of Business Ethics
      Complaints Handling Policy
      Customer Response Policy
      Protected Disclosures Act 1994 – Internal Reporting System
      Work Place Harassment
      Handling Workplace Grievance
      Corporate Sponsorship Policy
      Email Policy
      Privacy and Personal Information Protection Act
      1998 – Privacy Management Plan
      Procurement Policy




                                          Page 6 of 25
                    Mosman Municipal Council
                    RISK MANAGEMENT ACTION PLAN


Appendix 1            Risk Definition and Classification
Risk Analysis Matrix

                                                   Consequences

Likelihood         Insignificant       Minor             Moderate       Major          Catastrophic

Almost Certain        Medium            High               High        Extreme           Extreme

Likely                Medium          Medium               High          High            Extreme

Possible                Low           Medium               High          High             High

Unlikely                Low             Low              Medium        Medium             High

Rare                    Low             Low              Medium        Medium             High

             (Adapted from Australian Standard on Risk Management AS/NZS 4360:2004)

Risk Level Action

Risk Level     Action Required

Extreme Risk Develop specific Management Plan for immediate implementation to address
             extreme risks
               Allocate actions and budget for implementation within one month
               Report immediately to Senior Management; regular internal reporting required

High Risk      Develop and implement a specific Management Plan for high risks
               Allocate actions and budget to minimise risk; monitor implementation
               Report to Senior Management within one month; regular internal reporting required

Medium Risk    Develop and implement a specific Management Plan for medium risks
               Allocate actions and budget to minimise risk where existing controls deemed
               inadequate; monitor implementation
               Report to Senior Management within the quarter;
               Management to consider additional controls; report within the quarter

Low Risk       Accept and Monitor low-priority risks
               Manage via routine procedures where possible; Monitor via normal internal
               reporting mechanisms




                                          Page 7 of 25
                                         Mosman Municipal Council
                                      RISK MANAGEMENT ACTION PLAN

                                        RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY        FACTOR        SCALE NAME       DESCRIPTION

Environment & Public
                       Likelihood    Rare             Only ever occurs under exceptional circumstances
Health
Environment & Public
                       Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents
Health
Environment & Public
                       Likelihood    Possible         Not generally expected to occur but may under specific circumstances
Health
Environment & Public
                       Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents
Health
Environment & Public
                       Likelihood    Almost Certain   Event expected to occur most times during normal operations
Health


Environment & Public
                       Consequence   Insignificant    Minimal environmental impact; isolated release only
Health
Environment & Public
                       Consequence   Minor            Minor environmental impact; on-site release immediately controlled
Health
Environment & Public
                       Consequence   Moderate         Significant environmental impact; on-site release contained with assistance
Health
Environment & Public
                       Consequence   Major            Major environmental impact; release spreading off-site; contained with external assistance
Health
Environment & Public
                       Consequence   Catastrophic     Fatalities occur; extensive release off-site; requires long term remediation
Health


Financial              Likelihood    Rare             Only ever occurs under exceptional circumstances




                                                                  Page 8 of 25
                                 Mosman Municipal Council
                                 RISK MANAGEMENT ACTION PLAN

                                   RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY   FACTOR        SCALE NAME       DESCRIPTION

Financial         Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Financial         Likelihood    Possible         Not generally expected to occur but may under specific circumstances

Financial         Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Financial         Likelihood    Almost Certain   Event expected to occur most times during normal operations



Financial         Consequence   Insignificant    Negligible financial loss (< $10,000); no impact on program or business operations

Financial         Consequence   Minor            Minor financial loss ($10,000 - $50,000); minimal impact on program or business operations

Financial         Consequence   Moderate         Significant financial loss ($50,000 - $500,000); considerable impact on program or business operations

Financial         Consequence   Major            Major financial loss($500,000 - $1M); severe impact on program or business operations

Financial         Consequence   Catastrophic     Extensive financial loss ($1M+); loss of program or business operation



OH & S            Likelihood    Rare             Only ever occurs under exceptional circumstances

OH & S            Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents




                                                             Page 9 of 25
                                 Mosman Municipal Council
                                 RISK MANAGEMENT ACTION PLAN

                                   RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY   FACTOR        SCALE NAME       DESCRIPTION

OH & S            Likelihood    Possible         Not generally expected to occur but may under specific circumstances

OH & S            Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

OH & S            Likelihood    Almost Certain   Event expected to occur most times during normal operations



OH & S            Consequence   Insignificant    First Aid only required

OH & S            Consequence   Minor            Minor medical treatment with or without potential for lost time

OH & S            Consequence   Moderate         Significant injury involving medical treatment or hospitalisation and lost time

OH & S            Consequence   Major            Individual fatality or serious long term injury

OH & S            Consequence   Catastrophic     Multiple fatalities or extensive long term injury



Other             Likelihood    Rare             Only ever occurs under exceptional circumstances

Other             Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Other             Likelihood    Possible         Not generally expected to occur but may under specific circumstances




                                                             Page 10 of 25
                                        Mosman Municipal Council
                                        RISK MANAGEMENT ACTION PLAN

                                          RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY          FACTOR        SCALE NAME       DESCRIPTION

Other                    Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Other                    Likelihood    Almost Certain   Event expected to occur most times during normal operations



Other                    Consequence   Insignificant    An isolated event, the impact of which can be absorbed during normal operations

Other                    Consequence   Minor            A minor event, the impact of which can be absorbed with specific management

Other                    Consequence   Moderate         A significant event, the impact of which can be managed but has medium term implications

                                                        A critical event, the impact of which may be endured with proper management but has long term
Other                    Consequence   Major
                                                        implications
                                                        A disaster or event with extensive impact across multiple areas of the organisation; threatens viability
Other                    Consequence   Catastrophic
                                                        of the business


Professional Indemnity   Likelihood    Rare             Only ever occurs under exceptional circumstances

Professional Indemnity   Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Professional Indemnity   Likelihood    Possible         Not generally expected to occur but may under specific circumstances

Professional Indemnity   Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents




                                                                   Page 11 of 25
                                        Mosman Municipal Council
                                        RISK MANAGEMENT ACTION PLAN

                                          RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY          FACTOR        SCALE NAME       DESCRIPTION

Professional Indemnity   Likelihood    Almost Certain   Event expected to occur most times during normal operations



Professional Indemnity   Consequence   Insignificant    Isolated, internal or minimal complaint; minimal loss to organisation

Professional Indemnity   Consequence   Minor            Contained complaint or action with short term significance; medium loss to organisation

                                                        Significant complaint involving statutory authority or investigation; prosecution possible with significant
Professional Indemnity   Consequence   Moderate
                                                        loss to organisation

Professional Indemnity   Consequence   Major            Major complaint with litigation and long term significance; very high loss to organisation

                                                        Extensive litigation with possible class action; worst case loss to organisation; threat to viability of
Professional Indemnity   Consequence   Catastrophic
                                                        program or service


Public Liability         Likelihood    Rare             Only ever occurs under exceptional circumstances

Public Liability         Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Public Liability         Likelihood    Possible         Not generally expected to occur but may under specific circumstances

Public Liability         Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Public Liability         Likelihood    Almost Certain   Event expected to occur most times during normal operations




                                                                    Page 12 of 25
                                           Mosman Municipal Council
                                           RISK MANAGEMENT ACTION PLAN

                                             RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY             FACTOR        SCALE NAME       DESCRIPTION

Public Liability            Consequence   Insignificant    First Aid only required; minimal loss to organisation

Public Liability            Consequence   Minor            Some medical treatment required; medium loss to organisation

Public Liability            Consequence   Moderate         Significant injury involving medical treatment or hospitalisation; high loss to organisation

Public Liability            Consequence   Major            Severe injuries or fatality to individual; very high loss to organisation

Public Liability            Consequence   Catastrophic     Multiple fatalities or extensive long term injuries; worst case loss to organisation



Property & Infrastructure   Likelihood    Rare             Only ever occurs under exceptional circumstances

Property & Infrastructure   Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Property & Infrastructure   Likelihood    Possible         Not generally expected to occur but may under specific circumstances

Property & Infrastructure   Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Property & Infrastructure   Likelihood    Almost Certain   Event expected to occur most times during normal operations



Property & Infrastructure   Consequence   Insignificant    Isolated or minimal loss; short term impact; repairable through normal operations




                                                                       Page 13 of 25
                                           Mosman Municipal Council
                                           RISK MANAGEMENT ACTION PLAN

                                             RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY             FACTOR        SCALE NAME       DESCRIPTION

Property & Infrastructure   Consequence   Minor            Minor loss with limited downtime; short term impact; mostly repairable through normal operations

Property & Infrastructure   Consequence   Moderate         Significant loss with temporary disruption of services; medium term impact on organisation

                                                           Critical loss or event requiring replacement of property or infrastructure; long term impact on
Property & Infrastructure   Consequence   Major
                                                           organisation

Property & Infrastructure   Consequence   Catastrophic     Disaster with extensive loss and long term consequences; threat to viability of service or operation



Reputation                  Likelihood    Rare             Only ever occurs under exceptional circumstances

Reputation                  Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Reputation                  Likelihood    Possible         Not generally expected to occur but may under specific circumstances

Reputation                  Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Reputation                  Likelihood    Almost Certain   Event expected to occur most times during normal operations



Reputation                  Consequence   Insignificant    Isolated, internal or minimal adverse attention or complaint

Reputation                  Consequence   Minor            Heightened local community concern or criticism




                                                                      Page 14 of 25
                                 Mosman Municipal Council
                                 RISK MANAGEMENT ACTION PLAN

                                   RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY   FACTOR        SCALE NAME       DESCRIPTION

Reputation        Consequence   Moderate         Significant public criticism with or without media attention

Reputation        Consequence   Major            Serious public or media outcry; broad media attention

Reputation        Consequence   Catastrophic     Extensive public outcry; potential national media attention



Natural Hazards   Likelihood    Rare             Only ever occurs under exceptional circumstances

Natural Hazards   Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Natural Hazards   Likelihood    Possible         Not generally expected to occur but may under specific circumstances

Natural Hazards   Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Natural Hazards   Likelihood    Almost Certain   Event expected to occur most times during normal operations



Natural Hazards   Consequence   Insignificant    Minimal physical or environmental impact; isolated hazards only; dealt with through normal operations

Natural Hazards   Consequence   Minor            Minor physical or environmental impact; hazards immediately controlled with local resources

Natural Hazards   Consequence   Moderate         Significant physical or environmental impact; hazards contained with assistance of external resources




                                                             Page 15 of 25
                                        Mosman Municipal Council
                                        RISK MANAGEMENT ACTION PLAN

                                          RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY          FACTOR        SCALE NAME       DESCRIPTION
                                                        Major physical or environmental impact; hazard extending off-site; external services required to
Natural Hazards          Consequence   Major
                                                        manage
                                                        Extensive physical or environmental impact extending off-site; managed by external services; long term
Natural Hazards          Consequence   Catastrophic
                                                        remediation required


Information Technology   Likelihood    Rare             Only ever occurs under exceptional circumstances

Information Technology   Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Information Technology   Likelihood    Possible         Not generally expected to occur but may under specific circumstances

Information Technology   Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Information Technology   Likelihood    Almost Certain   Event expected to occur most times during normal operations



Information Technology   Consequence   Insignificant    No measurable operational impact to organisation

                                                        Minor downtime or outage in single area of organisation; addressed with local management and
Information Technology   Consequence   Minor
                                                        resources
                                                        Significant downtime or outage in multiple areas of organisation; substantial management required and
Information Technology   Consequence   Moderate
                                                        local resources
                                                        Loss of critical functions across multiple areas of organisation; long term outage; extensive
Information Technology   Consequence   Major
                                                        management required and external resources




                                                                   Page 16 of 25
                                        Mosman Municipal Council
                                        RISK MANAGEMENT ACTION PLAN

                                          RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY          FACTOR        SCALE NAME       DESCRIPTION

Information Technology   Consequence   Catastrophic     Extensive and total loss of functions across organisation; disaster management required



Political & Governance   Likelihood    Rare             Only ever occurs under exceptional circumstances

Political & Governance   Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Political & Governance   Likelihood    Possible         Not generally expected to occur but may under specific circumstances

Political & Governance   Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Political & Governance   Likelihood    Almost Certain   Event expected to occur most times during normal operations



Political & Governance   Consequence   Insignificant    Isolated non-compliance or breach; minimal failure of internal controls managed by normal operations

Political & Governance   Consequence   Minor            Contained non-compliance or breach with short term significance; some impact on normal operations

                                                        Serious breach involving statutory authority or investigation; significant failure of internal controls;
Political & Governance   Consequence   Moderate
                                                        adverse publicity at local level

Political & Governance   Consequence   Major            Major breach with formal inquiry; critical failure of internal controls; widespread adverse publicity

Political & Governance   Consequence   Catastrophic     Extensive breach involving multiple individuals; potential litigation; viability of organisation threatened




                                                                    Page 17 of 25
                                      Mosman Municipal Council
                                      RISK MANAGEMENT ACTION PLAN

                                        RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY        FACTOR        SCALE NAME       DESCRIPTION

Industrial Relations   Likelihood    Rare             Only ever occurs under exceptional circumstances

Industrial Relations   Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Industrial Relations   Likelihood    Possible         Not generally expected to occur but may under specific circumstances

Industrial Relations   Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Industrial Relations   Likelihood    Almost Certain   Event expected to occur most times during normal operations



Industrial Relations   Consequence   Insignificant    Isolated, internal or minimal impact on staff morale or performance; minimal loss to organisation

                                                      Contained impact on staff morale or performance of short term significance; medium loss to
Industrial Relations   Consequence   Minor
                                                      organisation
                                                      Significant impact on staff morale or performance of medium term significance; significant loss to
Industrial Relations   Consequence   Moderate
                                                      organisation

Industrial Relations   Consequence   Major            Major impact on staff morale or performance with long term significance; very high loss to organisation

                                                      Extensive impact on organisational morale or performance; worst case loss to organisation; threat to
Industrial Relations   Consequence   Catastrophic
                                                      viability of program or service


Contractual & Legal    Likelihood    Rare             Only ever occurs under exceptional circumstances




                                                                 Page 18 of 25
                                     Mosman Municipal Council
                                     RISK MANAGEMENT ACTION PLAN

                                       RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY       FACTOR        SCALE NAME       DESCRIPTION

Contractual & Legal   Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Contractual & Legal   Likelihood    Possible         Not generally expected to occur but may under specific circumstances

Contractual & Legal   Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Contractual & Legal   Likelihood    Almost Certain   Event expected to occur most times during normal operations



Contractual & Legal   Consequence   Insignificant    Isolated non-compliance or breach; negligible financial impact

Contractual & Legal   Consequence   Minor            Contained non-compliance or breach with short term significance and minor financial impact

                                                     Serious breach involving statutory authority or investigation; prosecution possible with significant
Contractual & Legal   Consequence   Moderate
                                                     financial impact

Contractual & Legal   Consequence   Major            Major breach with fines and litigation; long term significance and major financial impact

Contractual & Legal   Consequence   Catastrophic     Extensive fines and litigation with possible class action; threat to viability of program or service



Motor Vehicle         Likelihood    Rare             Only ever occurs under exceptional circumstances

Motor Vehicle         Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents




                                                                 Page 19 of 25
                                    Mosman Municipal Council
                                    RISK MANAGEMENT ACTION PLAN

                                      RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY      FACTOR        SCALE NAME       DESCRIPTION

Motor Vehicle        Likelihood    Possible         Not generally expected to occur but may under specific circumstances

Motor Vehicle        Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Motor Vehicle        Likelihood    Almost Certain   Event expected to occur most times during normal operations



Motor Vehicle        Consequence   Insignificant    Isolated incident or damage; minimal loss to organisation; dealt with through normal operations

                                                    Minor incident or damage with limited downtime; some loss to organisation; mostly dealt with through
Motor Vehicle        Consequence   Minor
                                                    normal operations

Motor Vehicle        Consequence   Moderate         Significant incident or damage; temporary disruption of services; high loss to organisation

Motor Vehicle        Consequence   Major            Individual critical incident requiring replacement of property; very high loss to organisation

                                                    Critical incident involving multiple property; extensive management required; worst case loss to
Motor Vehicle        Consequence   Catastrophic
                                                    organisation


Biological Hazards   Likelihood    Rare             Only ever occurs under exceptional circumstances

Biological Hazards   Likelihood    Unlikely         Conceivable but not likely to occur under normal operations; no evidence of previous incidents

Biological Hazards   Likelihood    Possible         Not generally expected to occur but may under specific circumstances




                                                                Page 20 of 25
                                    Mosman Municipal Council
                                    RISK MANAGEMENT ACTION PLAN

                                      RiskeMAP definitions for Likelihood / Consequence Scales
MASTER CATEGORY      FACTOR        SCALE NAME       DESCRIPTION

Biological Hazards   Likelihood    Likely           Will probably occur at some stage based on evidence of previous incidents

Biological Hazards   Likelihood    Almost Certain   Event expected to occur most times during normal operations



Biological Hazards   Consequence   Insignificant    Minimal physical or environmental impact; isolated hazards only; dealt with through normal operations

Biological Hazards   Consequence   Minor            Minor physical or environmental impact; hazards immediately controlled with local resources

Biological Hazards   Consequence   Moderate         Significant physical or environmental impact; hazards contained with assistance of external resources

                                                    Major physical or environmental impact; hazard extending off-site; external services required to
Biological Hazards   Consequence   Major
                                                    manage
                                                    Extensive physical or environmental impact extending off-site; managed by external services; long term
Biological Hazards   Consequence   Catastrophic
                                                    remediation required




                                                               Page 21 of 25
                                                             Mosman Municipal Council
                                                             RISK MANAGEMENT ACTION PLAN


Appendix 2                     Risk Register
Template 1 - Identifying and Analysing Risks

Department / Section: ........................................................................... Date of Review: .................................................................................................

Function / Activity / Planning Task: ...................................................... Compiled By: .....................................................................................................

Next Review Date: ...............................................................................


Ref         Category                      Hazard                   Hazard / Risk Description                         Existing Controls                                    Impact                      Risk Rating
  #                                                                                                                                                        Consequence            Likelihood
         (eg. OHS, PL)               Source of risk?                    What can happen?                       Measures already in place?                                                            As per Matrix




                                                                                                 Page 22 of 25
                                                        Mosman Municipal Council
                                                        RISK MANAGEMENT ACTION PLAN


Appendix 3               Risk Treatment Schedule & Plan
Template 2 - Risk Treatment Schedule and Action Plan
 Department:              .................................................................................   Date of Review:                              ....................................................................................

 Section:                 .................................................................................   Compiled by:                                 ....................................................................................

 Function / Activity:     .................................................................................   Reviewed by:                                 ....................................................................................


                  POTENTIAL TREATMENT OPTIONS                      COSTS &              TREATMENT TO              TARGET RISK                             RESPONSIBLE
                                                                                                                                                                                     TIMETABLE                   MONITORING
                                                                   BENEFITS            BE IMPLEMENTED                LEVEL                                  PERSON
                                                                                               (Y / N)
       RISK




                                                                                                                                                                                                               STRATEGIES TO




                                                                                                                             CONSEQUENCE

                                                                                                                                           TARGET LEVEL
                                                                                                                LIKELIHOOD
                                                                                                                                                                                                                  MEASURE
                                                                                                                                                                                      FOR
                                                                                                                                                                                                               EFFECTIVENESS
                                                                                                                                                                                 IMPLEMENTATION
              R




                                                                                                                                                                                                                  OF RISK
                                                                                                                                                                                                                TREATMENTS




                                                                                                 Page 23 of 25

				