                                                                                                                           PROJECT PROFILE FOR GUNDAGAI MEAT PROCESSORS
          PROJECT OBJECTIVE
          Gundagai Meat Processors (GMP) is a leading lamb processor and supplies exclusively to
          Coles Supermarkets. GMP has expanded steadily to continue to meet Coles order
          requirements. Following the development of a site masterplan by Wiley, GMP identified the
          need to expand their boning room. GMP previously managed projects with a combination of
          in-house responsibilities and consultants. They moved to a Wiley approach of single point of
          responsibility for building and process.

          PROJECT CHALLENGES
             Design for future expansion
             Cope with space restrictions in the boning room
             Improve ergonomics, OH&S and materials handling
             Tight timeframe of project to meet Coles deadlines for change-overs

          WILEY DELIVERED
          Advice
             A boning room concept consistent with the master plan developed by Wiley
          Design
             Various design options for the boning room layout with 3D virtual modelling
             Developed innovative tote handling system never used previously in the meat industry
             Building extension to accommodate an expanded boning room
          Engineering
             Design, tendering and procurement of conveyors, including an innovative hygienic
             overhead conveyor
             Preparation of specifications for PLC programs
             Coordination of major contractors
          Construction
             Supervision of construction & process subcontractors
             Manage interface with existing operations
             Responsibility for trim, cost and quality parameters
          PROJECT RESULT
          A new boning room with a quick change-over within a 4 day period to coincide with Coles
          supply chain changes of moving away from cartons to packing into totes.
GUNPP01




                                                  ADVICE   DESIGN   ENGINEERING   CONSTRUCTION
                                WILEY & CO PTY LTD LEVEL 3, 100 IPSWICH RD WOOLLOONGABBA Q 4102 AUSTRALIA
                           PHONE 1300 385988 FAX 1300 385989 innovate@wiley.com.au INT 61 7 3859 8888 ABN 40 010 604 869

				
DOCUMENT INFO
Shared By:
Categories:
Stats:
views:37
posted:4/17/2010
language:English
pages:1
Description: Gundagai Meat Processors new boning room