					                                                                                          OVIEDO PUBLIC WORKS FACILITY

                                                                                                  MEETING DATE: NOVEMBER 24, 2008                                             ACTION ITEM AGENDA
                     MTG.
           DATE                                     WHAT                               WHO          WHEN                                 NOTES                                    COMPL. DATE
                     ITEM
          11/10/08    1.01   OBTAIN DECISION ON CISTERN- IS IT TO BE INSTALLED OR   OWNER/ PAUL       ASAP     11-24-08 -UPDATE - THE CITY HAS DECIDED THAT THE CISTERN
                             NOT                                                     CARLSON                   SYSTEM WILL NOT BE INCLUDED IN THE PROJECT. THE DESIGN OF
                                                                                                               THE WASTE WATER WILL HAVE TO BE CHANGED SO THAT IT CAN BE
                                                                                                               PRICED AND APPROVED. THIS DESIGN IS REQUIRED IMMEDIATELY
                                                                                                               SO THAT THE PROJECT WILL NOT BE DELAYED.

          11/10/08    1.02   GET THE OWNER TO SCHEDULE THE INSTALLATION OF THE      OWNER/ PAUL     DECEMBER   11/20/08 - STILL NO ANSWER FROM OWNER/ ARCH FOR DELIVERY
                             CUBICLES FOR THE WALL SWITCHES TO BE INSTALLED          CARLSON         19 ROJ    DATE OR INSTALLATION DURATION


          11/10/08    1.03   VERIFY WITH SUBS THE INSTALLATION OF THE F/A , IT ,    PAUL CARLESON     ASAP
                             PHONE, CABLE/CCTV

          11/10/08    1.04   DECIDE ON THE EXTERIOR FIRE STROBE LOCATIONS            OWNER/ARCH     11/15/08   11-13-08 - THE DECISION AND LOCATIONS ARE TO BE DETERMINED
                                                                                                               AFTER THE MEETING IS CONCLUDED, AN RFI IS TO BE ISSUED TO
                                                                                                               GET THE RESOLUTION OF THE ISSUE

          11/10/08    1.05   GET A DETAIL ON CANOPY #1 STRUCTURAL ATTACHMENTS         ARCH/ENG      11/15/08   11-13-08 -- AN RFI IS TO BE ISSUED TO GET THE ATTACHMENT
                                                                                                               DETAIL SPECIFIED

          11/10/08    1.06   GET THE FRAMING OF THE CURTAINWALL COMPLETED AT         STRUCT ENG/    11/15/08
                             THE WEST END OF THE NORTH ELEVATION                       OWNER


          11/13/08    1.07   THE EXISTING DRAINAGE STRUCTURE ELEVATION IS NOT       PAUL CARLSON/   11/19/08
                             PER PLAN, AN RFI HAS BEEN ISSUED TO GET THE               OWNER/
                             CORRECTIVE ACTION TO BE PERFORMED REGARDING THE          ENGINEER
                             ELEVATION DIFFERENCE

          11/20/08    1.08   VERIFY THAT THE FLOOR SYSTEM CAN BE INSTALLED USING        PAUL        11/19/08
                             A MECHANICAL FASTENER IN LIEU OF ADHESIVE THE          CARLSON/ARCH
                             STANCHIONS IN PLACE

          11/20/08    1.09   GET THE SILL FLASHING DETAIL REVISED TO REFLECT THE        PAUL        11/19/08
                             SPLIT FACE BLOCK SITUATION                             CARLSON/ARCH

          11/20/08    1.10   RESOLVE ELEVATION CONFLICT AT EXISTING STRUCTURE       PAUL/ OWNER     11/21/08

          11/20/08    1.11   GET THE RESOLUTION OF THE CONDENSATE LINE, TAYLOR      PAUL/ TAYLOR/   11/27/08   TAYLOR TO DETERMINE CURRENT ELEVATION OF LINE, SITE
                             WILL STUB OUT 5' FROM BLDG, RESOLVE ELEVATION OF TIE   MECH ENGINEER              CONTRACTOR TO DETERMINE ELEVATION OF STORM STRUCTURE
                             AND LOCATE                                                                        INLET

          11/20/08    1.12   DETERMINE AND CONTRACT THE CURB INSTALLATION AT          PAUL/ SITE/   11/27/08
                             THE EMPLOYEE BREAK AREA                                   CAROLYN
          11/20/08    1.13   DETERMINE SOD CONTRACTOR/ SCOPE                        PAUL/ CAROLYN   11/27/08
          11/20/08    1.14   SCHEDULE THE CITY TO CLEAN UP THE NORTH AREA FOR       PAUL/ OWNER     11/27/08
                             THE NEW FENCE TO BE INSTALLED DECEMBER 15 & 16

          11/20/08    1.15   DETERMINE SEQUENCE FOR EXTERIOR SUPPLY VENTS           PAUL/ TAYLOR/   11/21/08
                                                                                     METAL PANEL
                                                                                      INSTALLER/
                                                                                       GLASSMAN

          11/20/08    1.16   FOLLOW UP/ EXPEDITE RUBBER FLOORING TILES IN THE       ACOUSTI/ PAUL   11/21/08   11-20-08 - THE FLOORING WAS ORDERED, BUT THE COLOR
                             MECH/ BREAK ROOM                                                                  SELECTED WAS DISCONTINUED..THE COLOR WAS RESELECTED 11-18-
                                                                                                               08 AND RE-RELEASED 11-18-08- THE TILES SHOULD BE ON THE BOAT
                                                                                                               FROM JAPAN--ANTICIPTED 12/29/08

          11/20/08    1.17   FOLLOW UP ON ELECTRICAL RFI REGARDING THE LOW            OWNER/        11/27/08   11-20-08 - THE ELECTRICIAN NEEDS A CUT SHEET OR SUBMITTAL
                             VOLTAGE LIGHTING CONTROLS SHOWN IN THE CUBICLE          ARCHITECT/                FOR THE CUBICLE WALL SYSTEM
                             WALLS- A LIGHTING CONTROL DETAIL IS REQUIRED TO            PAUL
                             SHOW HOW SWITCHES ARE INSTALLED

          11/20/08    1.18   FOLLOW UP ON SK FOR ADDED DUCT IN THE WORKROOM         PAUL/ TAYLOR    11/21/08
          11/20/08    1.19   THE FENCING ORDER IS ON HOLD PENDING THE CHANGE          OWNER/         ASAP
                             ORDER APPROVAL BY THE CITY                               CAROLYN

          11/20/08    1.20   CONFIRM AND CONTRACT WITH THE METAL FABRICATOR         CAROLYN/ JOHN    ASAP
                             PREPARING THE RAIN TROUGH SYSTEM                           TOTH




11f34c48-8788-41fe-aa7a-f3d5a3da1dd3.xls                                                                                      Page 1 of 3
Creating a New Action Item Agenda
1. Open the Action Item Agenda Template
2. Select File>Save As and enter the name of the project as the project name and save to the appropriate place on the computer
3. In Row #2 enter the project name


Adding the Client Logo
1. If a client logo is available, right-click on the current logo and select "Change Picture"
2. Locate the correct logo on the computer and click on "Insert"
3. Once inserted, the logo can be resized by using the handles located around the logo
* The logo and AIA tab are pictures and will need to be moved if the size of the rows above are changed. They should both be
positioned just on top of the thick blue line

Adding/Editing Action Items
1. For each new action item:
   a. Enter the date of the meeting that the action item was created
   b. Enter the action item number as the meeting # and then two digit item number (1.01, 1.02..). If there are sub-items they are
entered letters (i.e. 1.01.a 1.01.b)
   c. Enter the action item in the What column
   d. Enter the name/acronym of the responsible organization in the Who column
   e. Enter the agreed to resolution date in the When column
   f. Enter any notes as required.*
   g. If the engineer entered a completion date, enter that date in the Completion column (see more below)

2. Increase the height of the row to allow for all text to show in addition to extra space for notes by moving the
cursor underneath the row number. A cross-hair will appear and you can drag the row height by holding down the
left mouse key and dragging the mouse.


* If you need to enter multiple lines within the notes cell (i.e. different notes for different meeting dates), go to the
end of the current text and hold the ALT key and press the ENTER key. This creates a new line within the cell
where additional notes can be entered.


Completed Action Items
1. When an action item is complete, the engineer should enter the date that the item was completed.
2. Enter the completion date and then select the entire row, righ-click and select "Format Cells"
3. In the Font tab - select "Stikethrough" and click OK
4. For action items that were completed at the previous meeting, right-click on the row and select "Hide"


Printing Action Item Agendas
1. When the AIA is ready for printing, hold down the left mouse button and highlight all rows that have action
items. Right click and select "Select Print Area".
2. Click on print preview and check that all rows with items are included and then print
3. To adjust margins/print size use PAGE SETUP within the PRINT PREVIEW SCREEN
Formatting
1. Project Name - Tahoma 16pt
2. Meeting Date - Tahoma 10 pt.
3. Action Item Text - Tahoma 9 pt.