					    ADEQ TECHNICAL GUIDE FOR DRIP IRRIGATION SYSTEM
Permit Application Package must include:
        Permit application completed and signed
        Completed and signed “Disclosure Statement” or previously submitted or N/A.
        Design Drawings issued, stamped and signed by a Professional Engineer registered in Arkansas.
        Soils Report stamped & signed by a Professional Soil Classifier (PSC) registered in Arkansas. (Note:
        PSC must be a registered Department Representative (DR) with the Arkansas Department of Health
        and Human Services or a DR can work with a PSC to prepare and submit report. DR must be
        identified in soils report.)
        Location Map
        Waste Management Plan

Design Package must include:
        1. The type of system and manufacturer name (Lotus/Bioclere-Aqua Point, Orenco, etc.)

        2. Statement regarding size of septic tank(s) used for the primary treatment, if applicable.

        3. The type of collection system (pressure, gravity, or other)

        4. The volume of the septic tank(s) (gallons) and the designed retention time (days) if applicable

        5. The design flow for the DIS system in gallons per day

        6. Design flow of at least 80 gpd/capita for a STEP (Septic Tank Effluent Pumping) system, or

            at least 100 gpd/capita for a STEG (Septic Tank Effluent Gravity) system, or 100 gpd/capita

            for standard gravity lines

        7. The number of lots in the subdivision

        8. The average number of people per home or dwelling used to calculate the design flow

        9. The total length (ft) of drip line in all zones

        10. The number of zones in drip field

        11. The total area (ft²) covered by drip field

        12. The size of the reserve drip field area(ft²)

        13. The calculation for the reserve drip field as percentage of operational drip field (%). The

            percentage of reserve (alternate) drip field must meet the ADHHS requirements.

        14. The soil in drip field sampled and classified on 100 ft. centers


ADEQ Technical Guide for Drip Systems (rev. 11/15/05)                                    Page 1 of 2
        15. A filter from the effluent treatment unit that will retain particles of 100 micron size, or

            smaller, prior to entering the drip field

        16. The tested and designed soils loading rate (gpd/ ft²)

        17. The expected designed effluent limits for CBOD (mg/l), TSS (mg/l), Ammonia-N (mg/l),

            Nitrate + Nitrite – N (mg/l), Phosphorus (mg/l), and pH

        18. Technical specifications for sewer line installation

Required Components:

            Control panel
            Septic tank effluent filter at each dwelling when a STEP or STEG system is utilized.
            Flexible PVC tubing on all corners and connection to supply and return lines
            Effluent flow meter with recorder and integrator (gpd)
            Pressure gauge available for the evaluation of pressure expanding emitter
            Drip irrigation lines are provided with root inhibitor and bactericide
            Adequate effluent sampling location provided
            Vacuum breakers provided for all drip irrigation zones
            Drip tubing with pressure compensating emitters (PCE) utilized
            Ball or gate valves utilized in the system
            Return line for filter backwash stream
            Tubing connectors utilized as specified by the manufacturer
            Zoning valves w/ inspection ports
            Lysimeters installed 4 ft. below each drip zone
            Monitoring wells around the drip field (required by ADHHS)


        For a more detailed description of the components and their function see ADHHS’s
        “Guidelines for the construction of Drip Dispersal Systems.”