					                                                                                  DNREC’s Brownfield Development Program Process and Associated Templates  

                                             Technical Track                                                 (Based on Value Stream Mapping)                                                 Legal Track 

1                             Prospective Developer inquires about a property 
                                                                                                                                                   A           Prepare draft legal notice for Brownfield 
                                                                                                                                                   Development Agreement (BDA) Negotiations 
   
2                         Brownfield Application Received by DNREC (application online)                                                            *  Notice the negotiations are occurring at the site 
   
3                        A site number is given & DNREC project officer assigned                           
                                   Brownfield Application Evaluated                                                                                B           Project officers approve the legal notice 
   

4                    Brownfield Certification/Funding Eligibility Letter Sent
   
                                                                                                                                                   C           Legal notice is published (20 day Comment period) 
   
5                   Conceptual Site Model_Site Summary (CSM_SS) submitted to DNREC 
*  At least a week prior to scoping meeting 
                                       (CSM_SS Template)                                                                                           D              Draft BDA received (blackline preferred)   
                                                                                                                                                                    BDA Template and BVCP Template 
6                                       Project Teams review the CSM_SS 
   
*  Project team gets clarification if needed & Project officer visits site, if feasible 
                                                                                                                                                   E                    Develop & negotiate the BDA 
   
7                                                   Scoping Meeting 
*  Use the CSM_SS as the guide to develop sampling plan and other data collection 
   
requirement and prepare the Statement of Intent at the meeting                                                                                     F    Deputy Attorney general (DAG) approves & Paralegal        
                                                                                                                                                                                                gets BDA 
   
8              Draft Brownfield Investigation (BFI) Work Plan submitted & reviewed 
*  Based on the CSM_SS which includes the Statement of Intent. 
                                                                                                                                                    G     BDA signed by DNREC Site Investigation & Restoration 
                              (BF Investigation Work Plan Template)
                                                                                                                                                        Branch (SIRB) Program Manager II (PMII) or Director 
                                                                                                                                                         (No Brownfield Reimbursement until BDA is signed) 
9                                      DNREC approves BFI Work Plan 
   
10                                BFI field work takes place 
                                                                                                                                                   H                  Legal Notice prepared and submitted 
11                                Interim Action takes place (if needed) 
   
                                                                                                                                                   I                            20 day comment period 
12                           Draft BFI Report Submitted to DNREC 
  
                                            (BFI Report Template) 
   
                                                                                                                                                   J                           Copy and Distribute BDA 
13     Draft BFI Report reviewed & comments prepared by DNREC 
  
*  Meeting to discuss comments, if needed 

                                                                                                                                                   K            Receive Draft Environmental Covenant
14                                              BFI Report Finalized                                                                                                  Environmental Covenant Template 
   
15                  Proposed Plan drafted by consultant & reviewed by DNREC 
                                     (Proposed Plan Template)                                                                                      L                  DAG Review Environmental Covenant 

   
16                       Proposed Plan signed by the DNREC‐AWM Director 
                                                                                                                                                   M                PM II signs Environmental Covenant 
   
17                       Proposed Plan noticed for public comments (20 days)
   
18                                     Public Hearing (if requested) 
                                                                                                                                                   N         Mail Environmental Covenant to BF Developer 
   

19                                              Final Plan Signed 
   
*  SIRB Program Manager II (PMII) signs if no comments received on proposed Plan                                                                  O              Owner, DNREC, & Holder Sign & Record 
*  Director Signs if significant comments received and addressed 
   
                                                      (Final Plan Template) 
   
20                            Final Plan noticed (20 day appeal period) 
                                                                                                                                                   P                 Certificate of Completion of Remedy 
21                    Brownfield (BF) Remedial Design & Action Work Plan submitted                                                                                                 (COCR) Requested 
  
                          (BF Remedial Design and Action Work Plan Outline)                                                                                                         COCR Template
   
22     BF Remedial Design and Action Work Plan reviewed and approved by DNREC
   
                                                                                                                                                   Q                                     COCR drafted 
23                                     Remedial Action implemented 
   
*  Draft Environmental Covenant and Groundwater Management Zone (GMZ), if needed

                                                                                                                                                   R                                       COCR signed
24  Construction Completion Report (CCR) & Operations & Maintenance (O&M) Plan 
Submitted, Certification of Completion of Remedy (COCR) requested by developer 
  
                 (COCR Check list, CCR Outline, & O&M Plan Guidance) 

                                                                                                                                                   S                              COCR recorded and issued 
25     CCR approved, O&M Plan approved, and Environmental Covenant signed
   
26                                                            COCR Issued 
   
*  Site closed in no LTS/O&M requirements 


27                                           O&M, Long‐Term Stewardship (LTS) 



28                                                                 Site Closed 
*  If all cleanup is done and no restrictions needed