Commercial Building Permit Application Checklist - PDF

VIEWS: 36 PAGES: 2

  • pg 1
									                                             CITY OF NANAIMO
                                              T H E        H A R B O U R     C I T Y




                                             D EVELO PM EN T           SERVI C ES
                                                  Building Inspection Division

       Commercial/Multifamily/Industrial Building Permit Application Checklist
  Completed by                                                Phone/E-Mail

      Appointment of Agent (if applicant is other than owner or Coordinating Registered Professional)
      Coordinating Registered Professional (Architect/P. Eng.) Letter of Assurance (Schedule A)
      Architectural Drawings – 2 sealed sets
          Letters of Assurance (B1 & B2)
          Site Plan by BC Land Surveyor – 2 copies
          Parking Layout
          Landscaping: working drawings and estimate (for security bonding)
          BC Building Code Review
      Building Envelope Professional – 2 sealed sets of drawings
          Letters of Assurance (D)
      Structural Drawings – 2 sealed sets
          Letters of Assurance (B1 & B2)
      Mechanical Drawings – 2 sealed sets
          Letters of Assurance (B1 & B2)
      Plumbing Drawings – 2 sealed sets
          Letters of Assurance (B1 & B2)
      Electrical Drawings – 2 sealed sets, fire alarm and emergency lighting.
          Letters of Assurance (B1 & B2)
      Sprinkler Drawings – 2 sealed sets
          Letters of Assurance (B1 & B2)
          Hydraulic calculations 2 sealed sets
      Civil Drawings – 3 sealed sets
          Design of on-site servicing
          Design of off-site servicing and access
          Engineering Requirements Checklist
          Letters of Assurance (B1 & B2 Plumbing Item 4.2 and 4.3, Fire Suppression Items 5.4 and 5.11)
      Alternative Solution Reports (as required) – sealed
          Letters of Assurance (B1 & B2)
      Geotechnical Report – 2 sealed originals
          Letters of Assurance (B1 & B2)
      Home Owner Protection Office Documents (for residential occupancies) – sealed
      Truss, floor and beam layouts (for Multi-family Part 9 buildings)
      Plumbing Declaration Form (for Part 9 buildings)
      Unit (suite) Addressing (where building will not be stratified) – 2 copies
      Street Names and Phasing Plan (for Multi-family developments) – 2 copies

Works and Services are applicable to most projects where the value of construction exceeds $100,000.00.
Requirement varies in industrial zones. Coordinate with Development Engineering – Design Stage
Acceptance must be complete prior to BP issuance.

Revised: 2009-Jan-26                                                                    City of Nanaimo Guidelines
G:\DSDSystem\Handouts\Building\CommercialApplicationChecklist.doc                                      Page 1 of 2
Development Permit (DP) is required for alterations where the value of construction exceeds $100,000.00
and all new construction. Coordinate with Current Planning – DP must be in place prior to BP issuance.

In accordance with the duties of a Coordinating Registered Professional (CRP) as per the BC Building Code
Schedule A, it is the responsibility of the CRP to collect and submit all Schedules B1, B2 and D with the
building permit application and Schedules C at project completion. We will be directing all correspondence
to the CRP with copies to the owner.

Development Cost Charges are applicable to most projects where the value of construction exceeds
$50,000.00. Development Cost Charges are calculated on gross floor area and vary according to use (i.e.,
residential, commercial, industrial, etc.).

Building Permit Fees:

An application fee equal to 10% of the estimated Building Permit fee is due with submission of application.

The charge for building permit is based on market value of the finished project

Market value $500.00 or less ..........................................................................................................$ 40.00
Market value $501.00-$1000.00...................................................................................................... 65.00
Each additional $1000.00 to $100,000.00 ....................................................................................... 10.00
Each additional $1000.00 to $500,000.00 ....................................................................................... 7.00
Each additional $1000.00 over $500,000.00 ................................................................................... 4.50
Alternative Solution Report review (up to 4 solutions) .................................................................... 200.00

Bond fee:
- against damage to City property during construction
- refundable upon occupancy
When bonding is not collected for off-site Works and Services...................................................$1000.00
When Works and Services apply, the bond will be established
   by the Engineering Division and the project Civil Engineer

Plumbing inspection fees:
Plumbing fixtures each ....................................................................................................................$ 8.00
Minimum plumbing fee .................................................................................................................... 40.00
                2
Sprinklers per m GFA .................................................................................................................... 0.50
Minimum sprinkler fee ..................................................................................................................... 40.00

On-site services:
Water domestic and fire line........................................................................... $20.00 first 15m
....................................................................................................................... 7.00 each additional 15m
Sanitary sewer................................................................................................ 20.00 first 15m
....................................................................................................................... 7.00 each additional 15m
Storm sewer ................................................................................................... 20.00 first 15m
....................................................................................................................... 7.00 each additional 15m
Catchbasin/sump/manhole............................................................................. 15.00
Foundation drain ............................................................................................ 20.00 each building
Rainwater leaders; interior ............................................................................. 15.00 each
Manhole.......................................................................................................... 15.00 each
Fire hydrants................................................................................................... 15.00 each

Service connection fees vary according to off-site design

Access............................................................................................................................................. $25.00


If you have any questions or require clarification, please contact a commercial plans reviewer at our office at 755-4429.

This guideline should not be used as a substitute for existing building codes and other regulations. The building owner is
responsible for compliance with all codes, bylaws and other regulations whether or not described in this guideline.
Revised: 2009-Jan-26                                                                                                                                 City of Nanaimo Guidelines
G:\DSDSystem\Handouts\Building\CommercialApplicationChecklist.doc                                                                                                   Page 2 of 2

								