					                                                                                   MN No. 10-016

                         u.s. NUCLEAR REGULATORY COMMISSION
                                        REGION I
                               NOTICE OF LICENSEE MEETING


                                          March 29, 2010




Licensee:             Entergy Nuclear Operations, Inc.

Facility:             Vermont Yankee Nuclear Power Station

Docket No.            50-271

Date and Time:        April 12, 2010
                      1:00 p.m. -8:00 p.m.

Location:             Ramada Inn - Autumn Room
                      1380 Putney Road
                      Brattleboro, VT 05301-9063

Purpose:              To answer the public's questions concerning tritium, and to provide a
                      perspective on the potential public health risk. To inform the public of the
                      regulatory requirements relating to tritium, and how the NRC fulfills its
                      mission. Finally, the NRC will listen to and respond to concerns from the
                      public concerning the tritium issue at Vermont Yankee. Separately,
                      Entergy will be hosting an informational meeting regarding Vermont
                      Yankee.
Attendees:

        NRC:          C. Casto, Deputy Regional Administrator, Region IV
                      D. Roberts, Director, Division of Reactor Safety, Region I
                      D. Jackson, Chief, Projects Branch 5, Region I
                      J. White, Chief, Plant Support Branch 2, Region I
                      U. Shoop, Chief, Health Physics & Human Performance Branch, NRR
                      S. Garry, Senior Health Physicist, NRR
                      Others as assigned

Public Participation': This is a Category 3 Meeting (Open House). The open house will provide
                       the public the opportunity to talk with the NRC staff on an informal basis
                       to ensure that issues and concerns may be presented, understood, and
                       considered by the NRC.
                                              2

The NRC's Groundwater Contamination Task Force Charter can be located in ADAMS with
Accession Number ML 100640188. ADAMS is accessible from the NRC Web Site at:
http://www.nrc.gov/reading-rm/adams.html.

Meeting Contact:       Donald E. Jackson, Chief
                       Projects Branch 5
                       (610) 337-5306
                       E-mail: donald.jackson@nrc.gov

*The NRC provides reasonable accommodation to individuals with disabilities where
appropriate. If you need a reasonable accommodation to participate in this meeting, or need
this meeting notice or the transcript or other information from the meeting in another format (e.g.
braille, large print), please notify the NRC meeting contact no later than 2 business days prior to
the meeting. Attendance by NRC personnel at this meeting should be made known by April 5,
2010, via telephone to the NRC meeting contact.

                                             Approved by:


                                             iLtJ c:~""'--
                                             Donald E. Jacks n, Chief
                                             Projects Branch 5
                                             Division of Reactor Projects

cc:    Distribution via ListServ
                                                                                  2

The NRC's Groundwater Contamination Task Force Charter can be located in ADAMS with
Accession Number ML 100640188. ADAMS is accessible from the NRC Web Site at:
http://www.nrc.gov/reading-rm/adams.html.

Meeting Contact:                   Donald E. Jackson, Chief
                                   Projects Branch 5
                                   (610) 337-5306
                                   E-mail: donald.jackson@nrc.gov

'The NRC provides reasonable accommodation to individuals with disabilities where
appropriate. If you need a reasonable accommodation to participate in this meeting, or need
this meeting notice or the transcript or other information from the meeting in another format (e.g.
braille, large print), please notify the NRC meeting contact no later than 2 business days prior to
the meeting. Attendance by NRC personnel at this meeting should be made known by April 5,
2010, via telephone to the NRC meeting contact.

                                                                             Approved by:

                                                                             IRA!

                                                                             Donald E. Jackson, Chief
                                                                             Projects Branch 5
                                                                             Division of Reactor Projects


Distribution (via email)
See attached

SUNSI Review Complete: _ _-"J"'H'--_ _ (Reviewer's Initials)

DOC NAME: G:IDRPIBRANCH511-VY\2010 TritiumlTritium Workshop MeetinglTritium workshop Mtg Notice 4_12_10.doc

After declaring this document "An Official Agency Record" it will be released to the Public.                                          ML100880269

To receive a copy of this document, indicate in the box:   'e   n
                                                                    = Copy without attachment/enclosure liE" =Copy with attachment/enclosure "N" = No copy



                 OFFICE            RI/DRP                              I      RI/DRP                   I                             I
                 NAME              JHeinly/JH                                 DJackson/DJ
                 DATE              03/29/10                                   03/29/10




                                                                OFFICIAL RECORD COPY
                                                    3

Distribution: (Via E-Mail):

Executive Director for Operations, OEDO                                  (RIDSEDOMAILCENTER RESOURCE)
Deputy Executive Director for Reactor Programs, OEDO                     (RIDSEDOMAILCENTER RESOURCE)
Director, Office of Nuclear Reactor Regulation, NRR                      (RIDSNRROD)
Deputy Director, Office of Nuclear Reactor Regulation, NRRlADPR          (RIDSNRROD)
Associate Director, Office of Operating Reactor Oversight and Licensing,NRRlADRO (RIDSNRRADRO)
Director, Division of Inspection and Regional Support, NRR              (RIDSNRRDIRS)
Director, Division of Operating Reactor Licensing, NRRlDORL            (RIDSNRRDORL)
Ass!. General Counsel Materials Litigation and Enforcement,OGC         (RIDSOGCMAILCENTER RESOURCE)

S. Collins, RA                       N. McNamara, SLO                      G. Matakas, ORA
M. Dapas, DRA                        D. Tifft, SLO                         DRS Div Secretary, RI
D. Lew, DRP                          D. Spindler, DRP, SRI                 DRP Div Secretary, RI
J. Clifford, DRP                     H. Jones, DRP, RI                     R. Barkley, ORA
D. Roberts, DRS                      A. Rancourt, DRP, OA                  RI Receptionist
P. Wilson, DRS                       L. Trocine, RI, OEDO                  PMNS
D. Jackson, DRP                      J. Lubinski, NRR                      ROPreportsResource@nrc.gov
T. Setzer, DRP                       M. Kowal, NRR                         Region I Docket Rm
J. Heinly, DRP                       J. Kim, PM, NRR                       L. Pinkham, DRP
D. Screnci, PAO                      J. Boska, PM, NRR                     D. Bearde, DRS
N. Sheehan, PAO                      J. Thompson, NRR

				