					     Special Feature - Southern Cross Building



                                                          Shining
                                                          Example
                                                   Orchestrating an innovative and welcoming
                                                    structure in the Southern Cross Building




50                                                                                                                                             51
       VIC Special Feature - Southern Cross Building                                           VIC Special Feature - Southern Cross Building
                                                               Multiplex’s reputation is undisputed in
                                                               the arena of multi-storey construction
                                                                          and development


                                                     I   t’s development on the site of the former Southern Cross Hotel in
                                                         Melbourne’s CBD epitomises the style of ‘the most liveable city in the
                                                     world’. The recently-completed 40 level East Tower, also known as SX1 (121
                                                     Exhibition Street) is adorned with a stunning double glazed glass façade and
                                                     incorporates the latest in sophisticated building technologies.

                                                     During peak construction of the building, which comprises 78,167sqm of
                                                     Net Lettable Area (NLA) there were roughly 500 workers on site. Once the
                                                     22 level West Tower SX2 (111 Bourke Street) is completed, total NLA for
                                                     the entire Southern Cross redevelopement will be in excess of 120,000sqm
                                                     of office space, and approximately 4,000sqm of retail space, with parking
                                                     for 950 cars and a minimum of 150 bicycles and 100 motor bikes. An esti-
                                                     mated 40,000m3 of concrete and 6,500 tonnes of steel went into the con-
                                                     struction of the East Tower.

                                                     The Victorian State Labor Government had been searching for much need-
                                                     ed office space in the Melbourne CBD and they certainly have found a luxu-
                                                     rious patch of real estate in the $300 million, Southern Cross East Tower
                                                     development. Those set to occupy it are staff from the Department of In-
                                                     frastructure, State Revenue Office, Department of Innovation, Industry and
                                                     Regional Affairs, and the Department of Justice.

                                                     Multiplex worked in close association with Project Architect, Gordana Ticak
                                                     of Woods Bagot, in the design and construction of the angled double glazed



                                                                                                                                      A solid performance
                                                     façade.

                                                     Among many other beneficial features, this creation allows the new govern-
                                                     ment tenants to take full advantage of the radiant city views. Under the el-


                                                                                                                                      A
                                                     egant exterior of the East Tower, an un-propped steel frame with metal deck
                                                     formwork was erected. The two podium floors, above ground level, provide                business stemming from two family trusts, PlanIT Design Group of-
                                                     3,500sqm of office area each. The double height ground level provides the               fers reputable service that travels to extreme heights. Partner’s Ricky
                                                     main entries, foyer and secured lift lobbies. The vacant space between the       Hains and Tom Caine have a company history dating back to January 1988.
                                                     East and West Towers, at the top of their podium levels, will be enclosed by     They realized then, the importance of promoting the entire steelwork and
                                                     a ‘gingerly constructed’ transparent canopy, joining the two buildings over      steel detailing industry was essential in order to assist their own business in
                                                     a soon to be vibrant retail and civic precinct, aptly named Southern Cross       progressing to the towering levels it continues to surpass. While proudly
                                                     Lane.                                                                            marketing itself as one of the leading steel detailers on multi-storey build-
                                                                                                                                      ings in Australia, PlanIT has exercised its services on major developments
                                                     Southern Cross East Tower is one of Melbourne’s first buildings designed to      including BHP Billiton Headquarters and Latitude World Square. Their
                                                     obtain a 4.5 stars SEDA rating.                                                  most recent undertaking was the East Tower of Melbourne’s Southern
                                                     Environmental initiatives include:                                               Cross building.

                                                     •           Reduced air conditioning and heating loads created by the double     PlanIT detailed all of the steel members for fabrication on this prominent
                                                     skin façade which naturally heats in winter and cools in summer                  redevelopment. The 3D model created by their team, using ProSteel 3D
                                                     •           A 60 per cent reduction in the use of potable water through the      detailing software, also provided assistance in the construction of the double
                                                     introduction of an on-site black water treatment and recycling plant             glazed façade. Chief Executive Officer Ricky Hains states, “I enjoy the chal-
                                                     •           Natural light access into the building’s floor space, coupled with   lenge of taking conceptual type working drawings and creating an accurate
                                                     intelligent lighting, substantially reducing lighting energy use                 functional 3D model, which is then used to produce workshop drawings
                                                     •           Double-glazing throughout                                            from which the steelwork is fabricated”. Working closely with structural
                                                                                                                                      engineers Bonacci Group, and steel contractors GVP Fabricators, experi-
                                                     Multiplex’s reputation is undisputed in the arena of multi-storey construc-      ence and pre-planning were relied upon to assure this project met time and
                                                     tion and development. They have the ability to oversee the smallest to largest   budget requirements. Before installing the structural flooring system, an ini-
                                                     residential or commercial projects with delicate execution and remarkable        tial assembly of steelwork was completed at GVP’s plant in order to test the
                                                     professionalism. They have orchestrated an innovative and welcoming struc-       amount of precamber being applied to the floor beams. As one can imagine,
                                                     ture in the Southern Cross East Tower, while maintaining every bit of the        projects of this giant magnitude involve the compression and settling of
                                                     site’s original prestige.                                                        materials which need to be calculated with the utmost precision. PlanIT
                                                                                                                                      Design Group’s twelve highly skilled individuals working on the tower en-
                                                                                                                                      joyed the task, of implementing the innovative design concept contributed
                                                                                                               Multiplex Limited      by Bonacci Group.                                                                                          PlanIT Design Group
                                                                                               Level 2, 32 Lincoln Square North                                                                                                             Unit 2a 14-16 Garden Bld
                                                                                                                         Carlton      Due to its sheer size and volume of steel, PlanIT Design Group found their                                       Dingley Village
                                                                                                                       VIC 3053       nine month tenure on this redevelopment to be very rewarding. As the                                                  VIC 3172
                                                                                                                                      public continues to voice its appreciation of this stunning new landmark, the
                                                                                                                 p. 03 8341 4500      industry will hopefully observe a much needed increase in the use of steel in                                    p. 03 9551 6666
                                                                                                                  f. 03 9347 0031     the construction of multi level commercial buildings.                                                             f. 03 9551 6077
52                                                                                                                                                                                                                                                                        53
     VIC Special Feature - Southern Cross Building                                                                                                                                                                      VIC Special Feature - Southern Cross Building
     Rule of plumb




     T      he Southern Cross Project is a landmark development for Victori-
            an infrastructure Situated on the iconic Southern Cross Hotel site,
     (which once hosted the Beatles) on the western side of Exhibition Street
                                                                                         go far beyond average expectations. CDC bid on a wide variety of projects,
                                                                                         the adaptability and the flexibility of their workforce ensures that no job is
                                                                                         too small or too large. They are experts and industry leaders in commercial,
                                                                                         industrial, and multi-storey hydraulics, specialising in all areas of sanitary
                                                                                                                                                                          For the hot water service, CDC installed six solar panels and two solar tanks
                                                                                                                                                                          on the roof with a Demand Duo skid package boost system consisting of
                                                                                                                                                                          six Rinnai instantaneous water heaters and two storage tanks. This, along
                                                                                                                                                                          with the (BWTP) has ensured the strong environmental credentials of the
                                                                                                                                                                                                                                                              this aspect of our involvement in the project… In fact, everything on the
                                                                                                                                                                                                                                                              project went very smoothly.”

                                                                                                                                                                                                                                                              CDC Plumbing is currently working on a number of projects including
     and adjoining the corner of Bourke Street and Little Collins Street. Southern
                                                                                         plumbing including, design and construct.                                        development.                                                                        Freshwater Place, Victoria Point and College Square. They have also suc-
     Cross is well located at the eastern precinct of the Melbourne Central Busi-
                                                                                                                                                                                                                                                              cessfully completed projects in China, New Zealand and various states of
     ness District.
                                                                                         Utilising their extensive experience CDC were able to present a compelling       CDC used Grundfos pumps, and Caroma tap-ware and sanitary ware                      Australia. The skills CDC brought to the Southern Cross Redevelopment
                                                                                         tender to the developers of the Southern Cross Project (SCP). The success        throughout; chosen not only for their accent towards style, quality and reli-       are not only innovative in design, implementation of all contract works was
     Multiplex Constructions along with the developer, Multiplex Developments
                                                                                         of this bid resulted in them being awarded the design and construct con-         ability, but also due to project policy ensuring that as much of the develop-       accomplished professionally within program and budgets.
     were keen to ensure not only the quality of the project, but also utilised the
                                                                                         tract for the all hydraulic plumbing works, including siphonic stormwater        ment as possible remained Australian made.
     application of environmentally sustainable design principles of construc-
                                                                                         drainage, and the Black Water Treatment Plant (BWTP). CDC began their
     tion, design and operation of the major landmark building.
                                                                                         involvement in the project in 2003 with the completion of the project end-       CDC managed and engaged Walter J Pratt (WJP) for the design and instal-
     CDC Plumbing was founded 36 years ago in 1970. Since the company’s in-
                                                                                         ing in 2006. During the course of the project CDC had over 180 employees         lation of the (BWTP), which was incorporated into the building plumbing                                              CDC Plumbing & Drainage (Vic) Pty Ltd
                                                                                         involved across all their projects.                                              system. It operates by collecting all the sewerage and wastewater from within                                                              2 Ovata Drive
     ception, they have continually strived to create a culture of excellence with-
                                                                                                                                                                          the building, treating it through a number of processes before returning the                                                                  Tullamarine
     out compromise and their success and longevity in the fluctuating climate of
                                                                                         An interesting aspect of the development was the use of stainless steel pip-     treated water through a pump station to the roof top storage tanks which are                                                                    VIC 3043
     the past four decades is testament to their skill in achieving this.
                                                                                         ing. As Chadd Cooke, the Construction Manager for CDC explained, “Due            12,500ltr each , from which it is gravity fed for use in the flushing of toilets.
                                                                                         to the height of the building at 160 metres, and the water pressures gener-      Safeguards ensure that when the treatment plant is full or non-operational
     Through their demonstrated ability to accomplish excellence, and their wide
                                                                                         ated, we used stainless steel piping instead of copper (which wouldn’t have      there are two pneumatic knife gate valves to divert the flow to the standard                                                                 p. 03 9335 5800
     ranging, but thorough focus on OH&S, quality assurance and industrial rela-                                                                                                                                                                                                                                        f. 03 9335 5811
                                                                                         handled the pressure), for both the domestic cold water and non-potable          sewer system which discharges at street level. As Chadd Cooke explained,
     tions, CDC have been able to take challenges and opportunities as they pres-                                                                                                                                                                                                                              e. cdc@cdcplumbing.com
                                                                                         risers…”                                                                         “It’s a simple system in theory but does involve some high tech compo-
     ent themselves and create industry ‘best practice’ results for their clients that
                                                                                                                                                                          nents…” He went on to say that, “We are very happy with the outcome of                                                                  www.cdcplumbing.com
54                                                                                                                                                                                                                                                                                                                                          55
         VIC Special Feature - Southern Cross Building                                                                                                                                                                                                                                     VIC Special Feature - Southern Cross Building
     Wired for speed




                                                                                                                                                                       Current inovations
                                                                                                                                                                        F      or the passed few years, Apps Electrics Pty Limited has watched its
                                                                                                                                                                               team of capable technicians swell to over 175 and then settle back to
                                                                                                                                                                        100. “It’s a really tough business to be in,” director Terry Apps comments
                                                                                                                                                                        about the hardships of laying-off some 70 professionals. When you’re as
                                                                                                                                                                        sought after as this 60 year old Melbourne company however, you might
                                                                                                                                                                        have more than one multi-storey building running simultaneously, and there-
                                                                                                                                                                        fore must temporarily recruit more talent. Apps Electrics have an extensive
                                                                                                                                                                        history in commercial, industrial, residential, and hospital developments,
                                                                                                                                                                        which affords them a renowned reputation for excellence. They are ac-
                                                                                                                                                                        customed to tailoring every installation to meet the specific needs of each
                                                                                                                                                                        client and project.

                                                                                                                                                                        Project Manager David Jonker and Site Foreman Jim Sarkies, along with 60
                                                                                                                                                                        other team members of Apps Electrics, have recently completed a two and
                                                                                                                                                                        one half year commitment to the new Southern Cross Building. The SX1
                                                                                                                                                                        (or East Tower) accounts for half of the elegant redevelopment and offers
                                                                                                                                                                        76,700 square metres over 40 floors. This family owned business installed
                                                                                                                                                                        four off 2000 KVA main switchboards, coupled to a standby generating
                                                                                                                                                                        capacity of 6500KVA.

                                                                                                                                                                        Working in association with Multiplex the ‘design and construct’ builder,
                                                                                                                                                                        Apps Electrics were responsible for the lighting and power, switchboards,


     S     pecializing in the supply and installation of network cabling, eight year
           old company Lanec Services is capable of handling a variety of electri-
     cal and mechanical-electrical tasks. An established reputation in tenancy
                                                                                       supply telephony to the tenanted floors via extensive backbone cabling to
                                                                                       each communication room. “Lanec Services was instrumental in the design
                                                                                       on these communication rooms”, as Craig Wallace Lanec Services Southern
                                                                                       Cross Project Manager states, “with the installation of Panduit lab racks for
                                                                                                                                                                        and generators, from temporary electrics to final connections. As Mr. Terry
                                                                                                                                                                        Apps states, “working with Multiplex, proved to be a rewarding and memo-
                                                                                                                                                                        rable experience”.
     fitouts, UPS and energy conservation systems, switchboard replacement/
                                                                                       easy patching management and cablofil basket tray.”                              Apps experience within the industry is undisputed and continues to shine
     modification, has allowed this innovative outfit to utilize its multiple design
                                                                                                                                                                        amongst the current plethora of developments. Other substantial construc-
     and engineering certificates. As one of Victoria’s leading installers of Cat-
                                                                                        Twelve of its sixty talented employees, accounting for a workforce with an      tion projects, over the last two years, that feature this dynamic company
     egory 6 cable, Lanec Services maintains its consistent achievements by being
                                                                                       average of 10 years each experience in the field, worked for eighteen months     include Tribeca Apartments, Casey Community Hospital, Yarra’s Edge Tow-
     well rehearsed in the latest technologies.
                                                                                       to provide Melbourne’s youngest tall tale with a voice and data cabling in-      ers 2, 3 & 5, 11 Exhibition Street, and the Herald and Weekly Times. In-
                                                                                       frastructure. In conjunction with Multiplex Constructions, Lanec Services        terestingly, the Herald and Weekly Times Redevelopment was a very similar
     Molex Low Smoke Zero Halogen, Category 6 Unshielded Twisted Pair, or
                                                                                       adhered to a stern Occupational Health and Safety plan, and delivered a          installation to the Southern Cross building, and involved comparable mate-
     LSZH UTP cable is another fresh example of this company’s product in-
                                                                                       remarkable effort at 121 Exhibition Street.                                      rials and manpower to complete. With routine practice and such a flexible
     ventory, and it was recently supplied to 22 levels of the new 40 storey East-
                                                                                                                                                                        approach to their work, it’s no wonder the Apps family name is synonymous
     ern Tower of the Southern Cross Building. Due to its particular sheathing,
                                                                                                                                                                        with quality and customer appreciation.
     LSZH is more fire retardant than normal data cable, and doesn’t give off
     dangerous gases in the event of a fire. Additionally, Lanec Services designed                                                         Lanec Services Pty Ltd                                                                 Apps Electrics P/L
     and made mobile cable stands and rollers specifically for this project, which                                                               21 Thorton Cres                                                                  44 Levanswell Rd
     enabled them to handle the various materials in a much quicker, easier, and                                                                        VIC 3132                                                                         Moorabbin
     safer manner. A scissor lift was also purchased by the company to accommo-                                                                                                                                                           VIC 3189
     date for the height and unconventional access of the site. In order to meet                                                                  p. 03 9873 1611
     the requirements of the tenants, among them the Department of Justice                                                                                                                                                         p. 03 9555 2711
                                                                                                                                                   f. 03 9873 1711
     Department of Innovation,Industry & Regional Development,Department
                                                                                                                                                 m. 0425 753 838                                                                   f. 03 9553 2679
     of State Revenue, Lanec built a 13 vertical Test Point Frame on Level 28 to
                                                                                                                                           e. brett@lanec.com.au                                                         e. terry@appselec.com.au
56                                                                                                                                                                                                                                                     57
         VIC Special Feature - Southern Cross Building                                                                                                                                                VIC Special Feature - Southern Cross Building

				