					                              COST COMPARISON                                                                                                         7/22/2005
                              Azar Block v. Standard Block (cmu)
                              Commercial Building 40' x 75' x 10' High

                                   Width                    Length                 Height            Total Linear ft.        Sq. Ft. of Wall
 Building Size                       40                         75                   10                    230                   2,300


Standard Block Wall (8"x8"x16")

  Cost per Square Foot                    $25.00

                 Total Cost         $57,500.00

                                    Time Required to Build With Standard Block (cmu) Man Days                                             13.22


Azar Block Wall (8"x8"x16")

                                       Quantity         Material (each)         Total Material         Labor (each)              Total Labor                Total

 Azar 8" x 8" x 16"                        2,584                     $2.85                $7,365                 $3.00                  $7,753           $15,118

 Azar Corners - Right                          30                    $2.85                   $86                 $3.00                      $90              $176

 Azar Corners - Left                            30                   $2.85                   $86                 $3.00                      $90        $176
                                -------------------                                                                                           ----------------
            Total Blocks                    2,644                                                                              Total Material      $15,469

 Re-bar                             Lump Sum                                                                                                              $2,000

 Ready-Mix Concrete                        29.37                       110                 3,230                                                          $3,230

 Miscellaneous                      Lump Sum                              1              $1,000                                                            $1,000
                                -------------------         ----------------      ----------------     ------------------      ------------------- -----------------

   60,000.00
                                                                                                                                   Total Cost            $21,699
                                               Standard CMU
   50,000.00                                                                                                                                             $35,801
                                               Azar Block                                                                       Saving/Profit
   40,000.00
   30,000.00                                   Saving                                                                       Percentage Profit             62.26%
   20,000.00                                   Saving per FT.                                                  ========================================
   10,000.00
                                                                                                                    Cost per Square Foot                        $9
          0.00
                         1
                                                                                                                 Saving per Square Foot                        $16


                                                                               Time Required to Build With Azar Block Man Days                                4.41

                                                                Time Saving Azar v. Standard Block Construction Man Days                                      8.81


                                              Cost per Square Foot                        $25.00               $22.00                   $19.00            $16.00
                                           Saving per Square Foot                         $15.57               $12.57                     $9.57             $6.57
                           COST COMPARISON                                                                                               7/22/2005
                           Azar Block v. Standard Block (cmu)
                           98' long x 6' High - 7' Column & 14' Panel

                                                     Length               Height            Linear Feet          Sq. Ft. of Wall
 Fence Size                                            98                   6                   98                    588


Standard Block Wall (8"x8"x16")
   Cost per Square Foot               $12.00

              Total Cost           $7,056.00

                        Time Required to Build With Standard Block - CMU (Man Days)                                            4.23


Azar Block Wall (8"x8"x16")

                                    Quantity            Material       Total Material                 Labor         Total Labor                Total
 Azar 8" x 8" x 16"                        486              $2.85               $1,385                $3.00                $1,458            $2,843
 Azar Corners - Right                      140              $2.85                  $399               $3.00                   $420              $819
 Azar Corners - Left                       112              $2.85                  $319               $3.00                   $336              $655
 Azar Full Sash                             54              $2.85                  $154               $3.00                   $162              $316
 Azar Half Sash                              54              $2.85                 $154                $3.00                  $162              $316
                             ------------------- -------------------   ------------------- -------------------    -------------------------------------
              Total Azar                   846                                   $2,411                                     $2,538            $4,949

 Std. Caps 2"x10"x16"                       63              $3.00               189.00                $3.00                189.00                 378
 Std. Caps 26"x26"                            7             $2.85                 19.95               $3.00                  21.00            41
                                                                                                                                 ----------------
                                                                                                                  Total Material          5,368

 SRW Adhesive                              846              $0.15                   127                                                           127
                             -------------------   ----------------      ---------------- ------------------      ------------------- -----------------
                                                                             Standard CMU                             Total Cost               5,495
     $8,000                                                                                                                Saving              1,561
                                                                             Azar Block
     $6,000                                                                                                  Percentage Profit               28.41%
     $4,000                                                                                       ========================================
                                                                             Saving

     $2,000                                                                                            Cost per Square Foot                      9.35

         $-                                                                                         Saving per Square Foot                       2.65
                               1



                                                              Time Required to Build With Azar Block (Man Days)                                  1.41

                                               Time Saving Azar v. Standard Block Construction (Man Days)                                        2.82

                                     Cost per Square Foot                       $10.00               $12.00                $14.00            $16.00
                                   Saving per Square Foot                         $0.65               $2.65                  $4.65             $6.65
                           COST COMPARISON                                                                                      28-Feb-06
                           Azar Block v. CMU'S


                                                                                                         Total Sq. Ft. of
                                  Width             Length            Height         Total Linear ft.         Wall
  Building Size (ft)                40                75                10                 230                2,300

CMU'S Wall (8"x8"x16")

 Cost per Square Foot                    $25.00

              Total Cost           $57,500.00

                                 Time Required to Build With Standard Block (cmu) Man Days                          13.22


Azar Block Wall (8"x8"x16")

                                     Quantity Material (each) Total Material           Labor (each)          Total Labor             Total

  Azar 8" x 8" x 16"                       2,584           2.85         7,365.17                  3.00          7,752.81          $15,118

  Azar Corners - Right                       30            2.85              85.50                3.00              90.00            $176

  Azar Corners - Left                      30              2.85              85.50                3.00              90.00         $176
                           -------------------                                                                           ----------------
          Total Blocks                 2,644                                                     Total Material & Labor       $15,469
  Re-bar                        Lump Sum                                                                                        $4,000
  Ready-Mix Concrete                  30.05              120.00         3,605.82                 88.00          2,644.27        $6,250
  Shipping from Sacramento to Phoenix                                                             1.16          3,067.35        $3,067
                                                                                                                              ============

                        Commercial Building 40' x 75' x 10' High
                                 Phoenix, Arizona                                                                     Total       $28,786


                           CMU
                             Saving,                  57,500.00
                                                       Saving Foot,                                        Saving/Profit          $28,714
                                 $28,714                   $12
                           Azar Block                 28,786.42                                       Percentage Profit            49.94%

                          Saving                      28,713.58                                                                ===========
                          Saving Foot
                   Azar Block,                            12.48 CMU,                                     Cost per Sq. Ft.          $12.52
                       $28,786                                    $57,500
                                                                                                     Saving per Sq. Ft.            $12.48




                                                              Time Required to Build With Azar Block Man Days                         4.41

                                                    Time Saving Azar v. Standard Block Construction Man Days                          8.81


                                           Cost per Square Foot       $25.00             $22.00              $19.00              $16.00

                                      Saving per Square Foot          $12.48              $9.48               $6.48              $3.48


                                                                 1
                                COST COMPARISON                                                                                                 2/28/2006
                                Azar Block Smooth v. Standard Block (cmu)
                                98' long x 6' High - 7 Column & 6, 14' Panel

                                                            Length              Height            Linear Feet          Sq. Ft. of Wall
                                   Fence Size                 98                  6                   98                    588

Standard Block Wall (8"x8"x16")
    Cost per Square Foot                     $18.00

               Total Cost             $10,584.00

                            Time Required to Build With Standard Block - CMU (Man Days)                                              4.37



Azar Block Wall (8"x8"x16")

                                          Quantity            Material       Total Material                 Labor          Total Labor                  Total

  Azar 8" x 8" x 16"                            486               $2.85               $1,385                $3.00                $1,458             $2,843
  Azar Corners - Right                          140               $2.85                 $399                $3.00                   $420                $819
  Azar Corners - Left                           140               $2.85                 $399                $3.00                   $420                $819
  Azar Full Sash                                  54              $2.85                 $154                $3.00                   $162                $316
  Azar Half Sash                                   54             $2.85                  $154               $3.00                   $162               $316
                                   ------------------- -------------------   ------------------- -------------------    ------------------- ------------------
               Total Azar                        874                                   $2,491                                     $2,622             $5,113

  Std. Caps 2"x10"x16"                            63              $2.85               179.55                $3.00                189.00                  369
  Std. Caps 26"x26"                     7                       $30.00                210.00               $30.00                210.00                 420
  SRW Adhesive                        874                        $0.15                   131                 0.00                     0                 131
  Shipping from Sacramento to Phoenix                                                                        1.16                 1,012              1,012
                                                                                                                                              ---------------
                                  100' X 6' High Fence                                                                     Total Other               1,931
                                   Phoenix, Arizona                                                                                           ---------------
                                Standard CMU       $   10,584                                                               Total Cost                  7,044
                                Azar Block              $        7,044                                                           Saving                 3,540
                    Saving $3,540
                                Saving                  $        3,540                                             Percentage Profit               33.45%
                                                                                                                                              ===========
                                                                      Standard
                                                                     CMU $10,584                              Cost per Square Foot                      11.98
                   Azar Block                                                                              Saving per Square Foot                        6.02
                    $7,044




                                                                     Time Required to Build With Azar Block (Man Days)                              2
                                                       Time Saving Azar v. Standard Block Construction (Man Days)                                        2.62

                                           Cost per Square Foot                       $18.00               $20.00                $25.00             $30.00
                                         Saving per Square Foot                         $6.02               $8.02                $13.02             $18.02



                                                                       1
   IT PAYS TO COMPARE!

   Here is an example that shows how economical AZAR Mortarless Building Systems™ really are!


   EXAMPLE #1
   6Ft. x 100 Linear Ft. Privacy Fence
   (600 Square Feet of Wall Surface)


   National Average                                      Material     Labor         Total

   8” Thick Poured Concrete Wall
          Skilled Labor to Form, Pour & Strip
           (4 Men – 2 Days) @ $400.00
           Per man per day)                                           $3,200.00     $ 3,200.00

          Ready-mix concrete 15 yards @ $65.00           $975.00                    $   975.00

                                                                Total Cost          $4,175.00
                                                         Cost per Square Foot       $    6.96


   8” Thick Standard Block Wall
          Skilled Labor (3 Men – 2 days)
          @ $400.00 per man per day                                   $2,400.00     $ 2,400.00

          Standard 8” Block w/reinforcing
          675 @ $1.20                                    $810.00                    $   810.00

          A bed of mortar joint 675 @ $0.30              $202.50                    $   202.50

                                                                Total Cost          $3,412.50
                                                         Cost per Square Foot       $    5.69


   8” Thick AZAR Systems™ Wall
          Labor (You and two friends – 4 hours)                                     0
          AZAR Systems™ – 675 units @ $2.50              $1,687.50                  $ 1,687.50
          SRW Adhesive 675 @ $0.15                       $ 101.25                   $ 101.25

                                                                Total Cost          $1,788.75
                                                         Cost per Square Foot       $    2.98




10 Azar Mortarless Building Systems Inc.                                          www.azarblock.com
PRICE COMPARISON WORKSHEET

Use this sheet to compare pricing in your area:


EXAMPLE #1
6Ft. x 100 Linear Ft. Privacy Fence
(600 Square Feet of Wall Surface)


National Average                                  Material     Labor      Total

8” Thick Poured Concrete Wall
       Skilled Labor to Form, Pour & Strip
        (4 Men – 2 Days) @ $_____
        Per man per day)                                       $______    $______

       Ready-mix concrete 15 yards @ $_____       $_____                  $______

                                                         Total Cost       $______
                                                  Cost per Square Foot    $______


8” Thick Standard Block Wall
       Skilled Labor (3 Men – 2 days)
       @ $_____ per man per day                                $______    $______

       Standard 8” Block w/reinforcing
       675 @ $_____                               $_____                  $______

       A bed of mortar joint 675 @ $_____         $_____                  $______

                                                         Total Cost       $______
                                                  Cost per Square Foot    $______


8” Thick AZAR Systems™ Wall
       Labor (You and two friends – 4 hours)                              0
       AZAR Systems™ – 675 units @ $_____         $_____                  $______
       SRW Adhesive 675 @ $_____                  $_____                  $______

                                                         Total Cost       $______
                                                  Cost per Square Foot    $______




Azar Mortarless Building Systems Inc.                                    www.azarblock.com 11
   IT PAYS TO COMPARE!

   Here is another example that shows how economical AZAR Mortarless Building Systems™ really are!


   EXAMPLE #2
   Foundation of typical raised ranch side entrance and one car attached garage
   (200 Linear ft. of foundation wall, 4 ft. high, 800 sq. ft. of wall surface area)


   National Average                                           Material       Labor        Total

   8” Thick Poured Concrete Wall
          Skilled Labor to Form, Pour & Strip
          (4 Men – 2 Days) @ $400.00
          Per man per day)                                                   $3,200.00    $ 3,200.00

          Ready-mix concrete 20 yards @ $65.00                $1,300.00                   $ 1,300.00

                                                                        Total Cost        $4,500.00
                                                                      Cost per Sq. Ft.    $    5.63


   8” Thick Standard Block Wall
          Skilled Labor (4 Men – 2 Days)
          @ $400.00 per day per man                                          $3,200.00    $ 3,200.00

          Standard 8” Block w/reinforcing
          900 @ $1.20                                         $1, 080.00                  $ 1,080.00

          A bed of mortar joint 900 @ $0.30                   $ 270.00                    $ 270.00

                                                                        Total Cost        $4,550.00
                                                                      Cost per Sq. Ft.    $    5.69


   8” Thick AZAR Systems™ Wall
          Labor (you and two friends – 5 hours)                                           $0

          AZAR Systems™ 900 units @ $2.50                     $2,250.00                   $ 2,250.00

          Ready-mix Concrete 9 yards @ $65.00                 $ 585.00                    $    585.00

                                                                        Total Cost        $2,835.00
                                                                      Cost per Sq. Ft.    $    3.54




12 Azar Mortarless Building Systems Inc.                                                 www.azarblock.com
PRICE COMPARISON WORKSHEET

Here is another sheet to compare pricing in your area:


EXAMPLE #2
Foundation of typical raised ranch side entrance and one car attached garage
(200 Linear ft. of foundation wall, 4 ft. high, 800 sq. ft. of wall surface area)


National Average                                           Material       Labor        Total

8” Thick Poured Concrete Wall
       Skilled Labor to Form, Pour & Strip
       (4 Men – 2 Days) @ $_____
       Per man per day)                                                   $______      $______

       Ready-mix concrete 20 yards @ $_____                $_____                      $______

                                                                     Total Cost        $______
                                                                   Cost per Sq. Ft.    $______


8” Thick Standard Block Wall
       Skilled Labor (4 Men – 2 Days)
       @ $_____ per day per man                                           $______      $______

       Standard 8” Block w/reinforcing
       900 @ $_____                                        $______                     $______

       A bed of mortar joint 900 @ $_____                  $______                     $______

                                                                     Total Cost        $______
                                                                   Cost per Sq. Ft.    $______


8” Thick AZAR Systems™ Wall
       Labor (you and two friends – 5 hours)                                           $0

       AZAR Systems™ 900 units @ $_____                    $______                     $______

       Ready-mix Concrete 9 yards @ $_____                 $______                     $______

                                                                     Total Cost        $______
                                                                   Cost per Sq. Ft.    $______