					 South LRT Construction Update
                                 Construction                                                  September 23, 2008




                                   Update                                                     SouthLRT
September 23, 2008

 114 Street from 83 Avenue to University Avenue
        The trackway contractor has started setting the track to final alignment and grade. Over the next couple
        of weeks, the equipment will be seen working north of University Avenue.
        A closure of the Aberhart pedestrian walkway is scheduled from September 26 1600 hrs to September 29
        0600 hrs. During this time pedestrians traveling north from the Belgravia area are requested to take
        University Avenue east to 114 Street and continue north along 114 Street.
        ETS and the trackwork contractor will also be working across 83 Avenue on September 27 and 28 from
        0100 hrs to 0500 hrs. This will require intermittent crossings of 83 Avenue. Traffic along 114 Street
        should not be affected.

 114 Street from University Avenue to 74 Avenue
        Landscaping continues along 114 Street and along the multi-use trail. Intermittent off-peak lane
        closures are required for landscaping installation.
        Most of the multi-use trail is paved except for the sections from 77 Avenue to the pedestrian tunnel and
        the connection from 74 Avenue to 73 Avenue.
        In the area from 74 Avenue to 73 Avenue the contractor is installing a catch basin and a section of
        retaining wall before the multi-use trail can be completed. This is scheduled to be complete in the next
        few weeks. Temporary pedestrian access will not be available in this area because of limited working
        space. Pedestrians should use 115 Street and 74 Avenue or 76 Avenue to access 114 street.
        The contractor is setting the track to final grade and alignment from University Avenue to Belgravia
        Road LRT Underpass. Intermittent removals of the pedestrian bridges at 78 and 74 Avenues continue to
        allow installation of tracks. This work is now expected to be completed by November. Use 76 Avenue
        as an alternate crossing point for bus stop or to cross 114 Street.

 McKernan / Belgravia LRT Station and Pedestrian Underpass
        Work continues on the pedestrian underpass to install handrails.
        Additional signage has been added to the 76 Avenue intersection to alert cars not to park on the
        crosswalk on the west side of 114 Street, leading to the pedestrian underpass.
        Work on station and platform continues including installation of handrails and tile.

 Belgravia Road LRT Underpass
        The City drainage project to construct a shaft for a storm relief tunnel for the neighbourhood east of 114
        Street and south of 72 Avenue continues. This tunnel will also connect to the Belgravia Road LRT
        Underpass for flood prevention.
        Concrete plinth construction is complete. Track is being installed.




  Page 1 of 5
South LRT Construction Update                                                                 September 23, 2008

Belgravia Bridge and Road Modifications
       NEW!! Concrete work on bridge deck is complete. Pre-cast panels are being installed on the trestle
       structure.
       NEW!! Ramps along Fox Drive are complete.
       Landscaping continues on the north side of Belgravia Road hilltop with tree installations. The
       construction area has been fenced off. For your safety, please respect this fencing.
       Roadwork along Fox Drive continues. Anticipate off-peak lane closures in this area.
       Work continues on the south and north sides of Belgravia Road. Traffic disruptions, including lane
       closures, should be anticipated in this area. Some cable and light pole relocations continue.
       Phase I road construction north of University Farms continues; curb and asphalt is complete and road is
       open. Phase II construction on 116 Street continues and it is closed south of the Alberta Infrastructure
       access. Two-way traffic from Belgravia Road will continue. Temporary local access to area buildings is
       in place.

South Campus Station and Area (Foote Field / Saville Centre)
       Landscaping nears completion in this area.
       Final clean up of transit centre building interior and exterior continues.
       Glass installation at the LRT station continues. Work on station lighting continues.
       Track installation continues north to Belgravia Road LRT Underpass.
       Construction south of University Farms continues. Installation of multi-use trail and lighting continues.

111 Street Underpass
       Excavation of south approach to underpass continues. Concrete slab construction will begin.
       Shoring of walls for Stage II construction in the median continues. Final alignment of 111 Street
       continues. Northbound lanes have been moved eastward onto new road and construction has begun to
       finalize alignment. Southbound lanes have been returned to their ultimate configuration.
       Work continues to construct the concrete walls at the north end of the underpass. Rebar installation and
       concrete slab pours continue. Single lane closures southbound will continue during off-peak hours until
       project completion.
       Excavation, drainage work and electrical duct installation continue.
       The City drainage project to construct a shaft for storm water storage tunnel north of 60 Avenue and
       west of 114 Street continues. This storm tunnel will provide storage capacity to prevent flooding in the
       LRT underpass.

111 Street from 61 Avenue to Whitemud Drive
NEW!! 57 Avenue Intersection Closure
Anticipated effective dates from September 30 at 0600 to October 21
       No left turns in any direction will be allowed. North and southbound traffic will not be affected.
       Pedestrian access will be maintained.
       Visit www.takeETS.com for information about changes to bus service.
       This intersection closure was delayed due to left lane turning issues at 51 Avenue, which have an affect
       on all intersections along 111 Street.



 Page 2 of 5
South LRT Construction Update                                                                September 23, 2008

NEW!! 54 Avenue Intersection Closure
Anticipated effective dates from September 30 at 0600 to October 21
       No left turns in any direction will be allowed. North and southbound traffic will not be affected.
       Pedestrian access cannot be maintained at 54 Avenue as there will be no east/west lights. Pedestrian can
       cross at 51 Avenue or 57 Avenue.
       Visit www.takeETS.com for information about changes to bus service.
       This intersection closure was delayed due to left lane turning issues at 51 Avenue, which have an affect
       on all intersections along 111 Street.
General 57 Avenue to Whitemud Drive Information:
      Milling and filling of northbound lanes in front of Southgate Mall is now scheduled to begin in October.
      NEW!! Final north and south sidewalks on 51 Avenue from 111 Street to 110 Street are being installed.
      Medians, pork chops, pedestrian crossing are being installed at 51 Avenue.
      The 51 Avenue westbound curb lane closure allowing for a pedestrian walkway, continues.
      Roadwork construction northbound from 51 to 54 Avenues is expected to be completed by September
      29. Road construction on the southbound lane between 54 and 51 Avenues is complete. Traffic will
      continue to be reduced to one lane southbound between 54 and 51 Avenues until the curb is installed in
      the median.
      Roadwork in the southbound lanes between 51 Avenue and Whitemud Drive continues. Curb pouring
      continues. Construction of northbound turn lanes continues south of 51 Avenue. Anticipated completion
      September 29.
      Multi-use trail construction north of Whitemud Drive continues.
      Installation of duct banks and track drainage continues from 51 Avenue to Whitemud Drive.
      City of Edmonton Drainage Branch continues construction of an outlet control structure at the south end
      of the dry pond north of Whitemud Drive.

Southgate LRT Station
West Entrance
       Roofing and structural steel are complete. Masonry work is ongoing. Concrete curb work is ongoing.
East Entrance
       Structural steel construction nears completion. Masonry work to begin.
LRT Station
       Track slabs completed on south end of station. Track drainage north of station is complete. Structural
       steel construction complete.
54 Avenue Traction Power Sub-station
       Roofing continues. Insulation and vapour barrier installation is underway. Decking for roof to begin.

Whitemud LRT Bridge
       NEW!! Whitemud Drive will be restored to normal configuration and speed limit by early October.
       Bridge construction is ongoing. Remaining work includes abutments, bridge rails, slope protection and
       concrete finishing.
       Topsoil placement will be complete in October.




 Page 3 of 5
South LRT Construction Update                                                                  September 23, 2008

       Miscellaneous site work is ongoing. Motorists are advised to pay attention to signage and barricades as
       crews move around the site to complete this work.

111 Street from Whitemud Drive to 23 Avenue
Whitemud Drive to 43 Avenue
       Two-lane travel northbound from 43 Avenue to Whitemud Drive is expected to be reinstated in the next
       couple of weeks.
       Grading in the median for trackway continues.
43 Ave to 40 Avenues
       Subgrade preparation for the trackway and installation of electrical ductbanks continues.
40 to 37 Avenues
       The intersection at 40 Avenue was closed on September 15 and is now expected to open on October 2.
       Pedestrians can cross 111 Street on temporary crosswalks.
       Asphalt removal is complete. Installing electrical ductbanks and ballast wall for trackway is underway.
37 to 34 Avenues
       NEW!! Intersection at 37 Avenue is scheduled to be closed from October 6 to 18. Only right turns will
       be allowed during this time. Two-way traffic operating on the existing southbound lanes. Single lanes in
       each direction.
       Curb and asphalt has been constructed for the new northbound lanes. Concrete barrier adjacent to the
       trackway in the northbound lanes is being installed.
       NEW!! The eastbound lanes of 34 Avenue have been re-opened. However, a one day closure is
       scheduled for Sunday September 28 to apply the final lift of asphalt. (This could not be confirmed by
       printing time.)
34 Avenue to Saddleback Road
       Intersection at 34 Avenue is now scheduled to be closed from October 2 to 16. Only right turns will be
       allowed during this time. East/west travel will be prohibited. North/south travel will not be affected.
       NEW!! A partial day closure is planned for Saturday afternoon September 27 to complete final lift
       paving on the new northbound lanes of 111 Street from Saddleback Road to 34 Avenue. (This could not
       be confirmed by printing time.)
       Subgrade preparation for the trackway and installation of trackway drainage is ongoing.
       Drainage work for the drop structure on the northwest corner of 29A Avenue is ongoing.
Saddleback Road to 23 Avenue
       NEW!! Intersection at Saddleback Road is scheduled to be closed from October 14 to 26. Only right
       turns will be allowed during this time. East/west travel will be prohibited. North/south travel will not be
       affected.
       Work continues on the section of retaining wall south of the transit station.
       Granular is installed for new northbound lanes north of Century Park access.
       Ballast wall construction for trackway continues.

Century Park LRT Station
LRT Station
       Mechanical and electrical (M&E) rough-in continues. Structural steel installation continues. Brick
       veneer installation is ongoing.



 Page 4 of 5
South LRT Construction Update                                                                        September 23, 2008

       The pedway girders in the northbound lanes were installed on September 23. Southbound girders were
       installed September 24.
Transit Centre
       Curtain wall installation continues. M&E rough-in continues. Steel stud framing continues.
West Entrance
       Coping on MSE (retaining) wall complete. Allan Block wall construction is complete on one side. Work
       on the other side continues.
40 Avenue Traction Power Sub-Station
       Parking lot paving underway. M&E rough-in continues.
23 Avenue Traction Power Sub-Station
       M&E rough-in continues. Sub-station parking lot construction has begun. Site trailers have been moved
       off site.

D.L. MacDonald Maintenance Facility Expansion
These buildings will house vehicles and crews for the South LRT. They are located between Belvedere and
Clareview Stations.
Building ‘A’ Extension:
       Contractors are working on deficiency list. Overhead catenary wire installation inside and outside
       building continues. Track installation south of building complete.
Right-of-Way Building
       Parking lot paving complete. Drywall installation continues. M&E ongoing. Cladding work complete.
       Painting of the steel structure is ongoing. Installation of overhead crane has begun.
Blow-down Area:
A specialized cleaning facility for LRT vehicles.
       Concrete floor structure will be completed by end of September. Construction of block wall to begin.




 Information in this bulletin is current to September 23, 2008. Weather and other unanticipated events may change
 these schedules. Special bulletins are issued as required. Regular updates are issued every two weeks.

 If you’d like more information, or to receive updates and notifications, please email lrtprojects@edmonton.ca or leave
 your address at 780.496.4874 to receive updates by regular mail.

 The City of Edmonton is changing its website to better serve our citizens. However, this means that new
 information cannot be uploaded until early October. Visit www.edmonton.ca/LRTprojects for general
 information about the South LRT Extension, or call the LRT Projects information line at 780.496.4874 and
 leave a message.

 Information on traffic lane closures is also posted on the web at www.edmonton.ca/transportation (Click on "Current
 Road Closures and Detours").
 Do your part to keep workers safe – slow down and be patient. Speed fines double in construction zones
 when workers present.