                                 Project Contract

       The following document outlines the terms and conditions under which the
       project will be carried out. The aim of the project is to understand and further
       develop a hybrid rocket engine and test cell.


Deliverables

       Semester 1     Week 6 – Analysis of previous years work completed
                      Week 9 – Submission of interim report

       Semester 2     Week 4 – Launch of group website
                      Week 6 – Submission of final report
                      Week 8 – Group presentation

       Testing will commence between Week 11 of Semester 1 and Week 3 of
       Semester 2. This extended estimation is to compensate for any unexpected
       delays or failures during testing.

       A peer review will be undertaken during the course of the project and
       submitted in conjunction with the final report.

       The group will not accept any liability for the overrun of the project due to
       manufacturing deadlines taking longer than initially agreed between the group
       and the university technicians.

Production Duration

       The project will officially run for 18 academic weeks however our initial plan
       has project completion within this timescale.


Signed:-                                                    Date:-



………………………                     ………………………                     ………………………
Marc Cargill                  Ross Hamilton                 William Wright


       ………………………                                     ………………………
       Prof. Colin McInnes                           Dr. David Nash

				
DOCUMENT INFO
Shared By:
Categories:
Stats:
views:13
posted:3/17/2010
language:English
pages:1