professional documents
home
Profile
docsters
request
Blogs
Upload
about me
contact me
user photo
Bryant Haines
Program & Project Mana...
Chief Executive Office...
Kinetic IT Systems, In...
Bryant Haines is the Chief Executive and Chairman of the Board at Kinetic IT Systems, Inc. He has over 13 years professional experience in government and private sector work. Bryant is a professional IT project manager and systems...
submit clear
Excel Spreadsheet

Launch PAD (Project Assessment Dashboard) center doc

Summary Status Funding Scope Staffing Schedule Stakeholders Requirements Architecture & Design Development Work Environments Testing Transition to Support Training Successes & Issues Potential Impact Planned Action – – – – – – – – – – – – – • • • – – – – – – – – – – – – – • • • – – – – – – – – – – – – – • • • – – – – – – – – – – – – – • • • – – – – – – – – – – – – – • • • Status Color Criteria: Submitted By: Indicates a critical threat to the execution/deployment capability of the project Indicates a potential threat to the execution/deployment capability of the project Indicates a healthy status in support of the execution/deployment capability of the project Indicates a status of complete toward the execution/deployment capability of the project No status is available to determine the status of the execution/deployment capability of the project Task/Project 5 -Description Task/Project 4 -Description Task/Project 3 -Description Task/Project 2 -Description • • • [Date] • [Project Name] Launch PAD Project Assessment Dashboard • • Task/Project 1 -Description • • • • • Red • • Yellow Green Blue No Status ••Summary Status Funding Scope Staffing Schedule Stakeholders Requirements Architecture & Design Development Work Environments Testing Transition to Support Training Critical Issues Potential Impact Planned Action G G Y G G G G G – – – – – R G R R Y G Y G – G – – – • Staffing: FTE staffing is not sufficient for the baseline schedule, and one of the two SMEs has left the project. • Collaboration and development may be hindered without additional resources. • Additional resources must be assigned for project continuation, perhaps from other projects or project partners. • Schedule: The baseline schedule still reflects a stand-alone project and cannot be updated without Project Mgmt. Team approval. • The current schedule does not reflect an executable plan if collaboration with the AR project is required. • The schedule should be updated to reflect the impact and work-arounds considered. • Requirements: The requirements gathering process is progressing slower than expected and will not complete on schedule. Requirements are a critical path item impacting RFP. Collaboration may negate the impact of this delay. Additional Requirements staffing and a collaboration plan (or plan to remain stand-alone) must be initiated. G G Y G G G – – – – – – – – R – – – – – – – – – – – Status Color Criteria: Indicates a critical threat to the execution/deployment capability of the project Indicates a potential threat to the execution/deployment capability of the project Indicates a healthy status in support of the execution/deployment capability of the project Indicates a status of complete toward the execution/deployment capability of the project No status is available to determine the status of the execution/deployment capability of the project Task 3 -Execution & Control Task 2 -Requirements Definition Sample Project • Task 1 -Planning & Initiation Sample Launch PAD Project Assessment Dashboard Scope is in question, and recent delays create risk to the project's viability as a stand-alone. • Scope: The scope of the project has grown to the broader scope of work management and accounting. Many of the project requirements and schedule are delayed to facilitate collaboration. November 26, 2004 • Non-critical staff may be reduced in Task 3 and 4 to free-up the needed funds. • Task 3 cannot begin until the scope of the project is finalized and Task 2 requirements are defined. •• Task two requirements cannot be fully defined until the full scope of the project is clarified. •• PMT review is in progress and opportunities for collaboration are being explored. The Feasibility document is Red The PMT pending decision will determine the scope and direction of the VMS Project. Task 4 -Close-Out • Scope: Task 3 scope is undefined. May range from stand-alone to Enterprisewiid integration. • • Funding: Task 2 Delays have create an expected budget overrun in Task 4. Yellow Green Blue No Status Task 4 efforts will not be complete with currently-allocated funding. Sponsor approval and funding is required. •• Scope: The project definition is in flux due to collaboration questions. • Changing the category color automatically changes the higherleeve Summary Status. Click to select a different category status color. Type a description of the reason for any category labeled red or yellow. The Launch PAD encourages the definition of a possible solution to every problem identified Change the categories to your area of interest or expertise. Use the Task/Project Groups to manage stages in a project or multiple projects, and add more sets as needed. Re-define the Status Color Criteria to fit your needs and audience. Make additional copies of the Page 2 of 4Summary Status Funding Scope Staffing Schedule Stakeholders Requirements Architecture & Design Development Work Environments Testing Transition to Support Training Critical Issues Potential Impact Planned Action area of interest or expertise. This report presents the Project Manager's assessment of project readiness for release, including deployment and transition to support. Make additional copies of the tab each week/month to keep a running record of the project in one file. Page 3 of 4Modify the gray cells below to change the way each Project or Task calculates a Green, Yellow, or Red status. Overall Red if a row has 2 or more Reds Overall Yellow if a row has 2 or more Yellows, or at least 1 Yellow AND at least 1 Red Overall Green if row has 1 or more Greens, or more than 0 Blues and no Yellow or Red overall status. Copyright 2004, Bryant I Haines. Do Not Delete This Tab. We recommend hiding this tab once the tool is configured to your needs. Printing of this tab is not required. For more information contact: Bryant Haines Sr. Project Manager bhaines@rrsolutions.com Form Logic Assessment Logic (704) 340-7660 Permission is hereby granted to any person, entity or corporation to use and/or modify this assessment tool and report provided this copyright tab is left intact. This open-source approach is intended to promote better project management, project assessment, and project communication across the industry. No notification or mention is required for the use of this tool or its printed output provided this tab remains intact. It is acceptable to hide this tab, and printing of this tab for printed reports is not required. Check with the organization whose data/project is being assessed to ensure you have a copy of this tool that does not contain proprietary information. For a blank template, please contact Bryant Haines. This file contains a hidden Assessment Template tab. Un-hide the tab to begin developing your own project assessment.
rate this doc
email this doc
embed this doc
add to folder
digg reddit stumble delicious
flag this doc
763
235
8(2)
0
1/17/2008
English
search termpage on Googletimes searched
Preview

Project performance tracking and reporting

anonymous 4/8/2008 | 408 | 88 | 1 | business
Preview

Project Tracking Excel Template

ronviers36 1/18/2008 | 1765 | 327 | 0 | business
Preview

project performance tracking and reporting[2]

olive529 5/25/2008 | 135 | 48 | 0 |
Preview

OAKS Project Dashboard April

Ohio 6/18/2008 | 24 | 2 | 0 | legal
Preview

OAKS Project Dashboard February

Ohio 6/18/2008 | 21 | 0 | 0 | legal
Preview

OAKS Project Dashboard January

Ohio 6/18/2008 | 25 | 5 | 0 | legal
Preview

OAKS Project Dashboard December

Ohio 6/18/2008 | 15 | 0 | 0 | legal
Preview

OAKS Project Dashboard November

Ohio 6/18/2008 | 15 | 2 | 0 | legal
Preview

OAKS Project Dashboard October

Ohio 6/18/2008 | 21 | 0 | 0 | legal
Preview

Project Safe Childhood PSA Launch

DOJ 6/4/2008 | 9 | 0 | 0 | legal
Preview

Project assessment

StarBoy 11/14/2007 | 224 | 8 | 0 | educational
Preview

Performance Assessment Project Statement

ocak 1/10/2008 | 222 | 30 | 0 | business
Preview

Project Risk Assessment

ocak 1/28/2008 | 408 | 125 | 0 | business
Preview

Performance Assessment Project Statement template

banter 1/8/2008 | 414 | 65 | 0 | business
project scope of work documenting tool521
assessment dashboard11
dashboard scope of work11
launch pad project assessment dashboard11
 
review this doc