Chemaf commissions HMS Plant

Document Sample
Chemaf commissions HMS Plant Powered By Docstoc
					HQ: Shalina Resources Ltd                                                               Operating Office:
Jafza View 19                                                                              Chemaf SPRL
Office 508, Jebel Ali Free Zone                                                        144 Avenue Usoke
PO Box 17938                                                                                 Lubumbashi
Dubai, UAE                                                                   Democratic Republic of Congo

T: +971 4886 5696                           Chemaf SPRL
F: +971 4886 5697                          www.chemaf.com




Chemaf commissions HMS Plant
11 July 2008

CHEMAF commissioned a Heavy Media Separation (HMS) plant for enrichment of copper and
cobalt metal values in the Run-of-mine (ROM) ore. The HMS plant has been set up at the Etoile
mine site with installed capacity for treatment of 100 tonnes/hour ROM ore feed to produce ~18
tonnes/hour of copper and cobalt rich concentrate. The concentrate produced by the HMS plant is
treated in CHEMAF!s processing plant at Usoke (in Lubumbashi town), for conversion into copper
cathodes and cobalt product.

Heavy Media Separation is a mineral beneficiation technique for concentration / enrichment of
desirable metal values in the ore. HMS involves treating the crushed and screened ore in a liquid
media, which is a mixture of fine ferro-silicon powder in a slurry of water. The specific density of the
media slurry is so maintained as to allow the low density gangue material to float and the other
high density useful minerals to sink. The sink product is copper and cobalt rich concentrate.

The plant facilities include crushers, scrubber, screens and standard DMS module. The crushed
and sized ore is mixed with ferro-silicon medium and pumped to DMS cyclones for separation into
sinks(concentrate) and floats (tailings).

The technology and plant was supplied by a specialist engineering and equipment supply company
from South Africa. The plant construction at site was carried out by CHEMAF!s project team and
was completed in scheduled time.

HMS plant was inaugurated on 11th July 2008, and is succssfully operating.




HMS Inauguration




1|                                                                                         Chemaf SPRL

				
DOCUMENT INFO
Shared By:
Categories:
Stats:
views:95
posted:3/7/2010
language:English
pages:1
Description: Chemaf commissions HMS Plant