Erect and dismantle formwork for footings and slabs on ground

Document Sample
Erect and dismantle formwork for footings and slabs on ground Powered By Docstoc
					Training Package                       General Construction (BCG03)
                                                                                                                                                                 HSC Requirements
Title
                                       Erect and dismantle formwork for footings and                                                                                and Advice
                                       slabs on ground
                                       Unit Descriptor                                                                                                         HSC Indicative Hours
Unit code
                                       This unit specifies the competency required to erect and dismantle formwork to footings and slabs on ground
    BCGCA2003B                         for establishing levels and containment of finished concrete.
                                       The unit includes forming basic slabs, forming rebates to slabs on ground and steps to strip footings
                                                                                                                                                                           25

                                                               Evidence Guide
The Evidence Guide identifies the critical aspects, knowledge and skills to be demonstrated to confirm competency for this unit. This is an integral
part of the assessment of competency and should be read in conjunction with the Performance Criteria, the Range Statement, and the Assessment
Guidelines of the Training Package.


     Specific knowledge required to                                                                          Specific resource requirements                      HSC Requirements
                                                           Relationship to other units
    achieve the performance criteria                                                                                   for this unit                                and Advice
A knowledge of:                                    Pre-requisite units are:                            The following resources should be made             Key Terms and Concepts
• workplace and equipment safety                   • BCGCM1001B Follow OH&S policies and               available:
  requirements                                       procedures.                                       • workplace location or simulated workplace        •   barricade
• quality requirements                                                                                 • materials relevant to erection and dismantling   •   block out
                                                   Competency in this unit may be assessed in
• general construction terminology                                                                       of formwork for footings and slabs on ground     •   calculation of materials
                                                   conjunction with other functional units which
• plant, tools and equipment types,                                                                    • hand and power tools, plant and equipment        •   cast in services
                                                   together form part of the holistic work role.
  characteristics, uses and limitation                                                                   appropriate to erection and dismantling of       •   clean-up
• formwork techniques                                                                                    formwork for footings and slabs on ground        •   clean, maintain and store formwork
• formwork materials                                                                                   • realistic activities covering the mandatory          tools and equipment
• processes for the calculation of material                                                              task requirements                                •   communication
  requirements                                                                                         • specifications and work instruction.             •   edge rebate
• Material Safety Data Sheets                                                                                                                             •   environmental protection
• plans, drawings and specifications                                                                                                                      •   fixing/fasteners
• materials handling, storage and                                                                                                                         •   footing
  environmentally friendly waste management                                                                                                               •   formwork
• processes for setting out and measuring                                                                                                                 •   formwork materials
• line, level and plumb                                                                                                                                   •   formwork techniques
• termite barriers                                                                                                                                        •   framework support
• JSA's/Safe work method statement                                                                                                                        •   general features, purpose and


          Construction Curriculum Framework                   September 2004           BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                            247
                                                            Critical aspects of evidence
           Context of assessment                                                                                                                                    HSC Requirements
                                                             required to demonstrate                               Methods of assessment
                                                              competency in this unit                                                                                  and Advice

The application of competency is to be assessed     Location, interpretation and application of          Assessment must satisfy the endorsed                    working knowledge of formwork
in the workplace or realistically simulated         relevant information, standards and                  assessment guidelines of the Building and               tools and equipment
construction site.                                  specifications.                                      Construction industry's General Construction        •   identify and rectify/report faults
                                                                                                         Training Package and relevant NOHSC                 •   levels and falls
Assessment is to occur under standard and           Compliance with site safety plan, OH&S               standards where they apply.
authorised work practices, safety requirements      regulations and State/Territory legislation                                                              •   occupational health and safety
and environmental constraints.                      applicable to workplace operations.                  Assessment methods must confirm consistency             (OHS)
                                                                                                         and accuracy of performance (over time and in       •   plan and prepare
Assessment of essential underpinning                Compliance with organisational policies and          a range of workplace relevant contexts) together    •   quality assurance
knowledge, other than confirmatory questions,       procedures including quality requirements.           with application of underpinning knowledge.         •   release agents
will usually be conducted in an off-site context.                                                                                                            •   safe work practices
                                                    Safe and effective operational use of tools, plant   Assessment must be by direct observation of
Assessment is to comply with relevant               and equipment.                                                                                           •   set out
                                                                                                         tasks, with questioning on underpinning             •   signage
regulatory or Australian Standards                                                                       knowledge and it must also reinforce the
requirements.                                       Communication and working effectively and                                                                •   slab
                                                    safely with others.                                  integration of key competencies.
                                                                                                                                                             •   stripping
                                                    Form up a slab on ground a minimum of 9m²,           Assessment methods must confirm the ability to      •   waste management
                                                    incorporating an edge rebate and internal            access and correctly interpret and apply the        •   work instructions.
                                                    corner to specifications.                            essential underpinning knowledge. Assessment
                                                                                                         may be applied under project related conditions
                                                    Form up a step to a foundation excavation to         (real or simulated) and require evidence of
                                                    specified masonry unit.                              process.
                                                                                                         Assessment must confirm a reasonable
                                                                                                         inference that competency is able not only to be
                                                                                                         satisfied under the particular circumstance, but
                                                                                                         is able to be transferred to other circumstances.
                                                                                                         Assessment may be in conjunction with
                                                                                                         assessment of other units of competency,
                                                                                                         including those listed above.




          Construction Curriculum Framework                   September 2004             BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                               248
Specific key competencies, underpinning and employability skills required to achieve the performance criteria
These include a number of processes that are learned throughout work and life, which are required in most jobs. Some of these are covered by the national key competencies, although others
may be added. The details below highlight how these competencies are to be applied in the attainment of this unit.

Application of the key competencies in this unit are to satisfy the nominated level in which:
Level 1 – relates to working effectively within set conditions and processes;
Level 2 – relates to the management or facilitation of conditions or processes; and
Level 3 – relates to the design, development and evaluation of conditions or process.

How will the candidate apply the following key competency in this unit? The candidate will need to:

                                                                                       Collect, organise, interpret and understand the information required for erection and dismantling of
                                                                                       formwork for footings and slabs on ground, including work instructions, plans/sketches/diagrams, safety
Collect, analyse and organise information                            Level 1
                                                                                       instructions, signage, labels, quality procedures, manufacturer's instructions, material safety data sheets
                                                                                       and equipment instructions

                                                                                       Communicate ideas and information orally and in writing, in simple English to enable confirmation of
Communicate ideas and information                                    Level 1           work requirements, passage of information and requests to other workers during operations and the
                                                                                       reporting and recording of work outcomes

                                                                                       Conduct activities associated with erection and dismantling of formwork for footings and slabs on ground,
Plan and organise activities                                         Level 1
                                                                                       including the co-ordination and use of equipment, materials and tools to avoid backtracking and rework

                                                                                       Work with others and in a team by recognising dependencies and using co-operative approaches to
Work with others and in a team                                       Level 1
                                                                                       optimise satisfaction and productivity

                                                                                       Establish safe and effective work processes which anticipate likely problems and blockages and
Solve problems                                                       Level 1
                                                                                       systematically work around these to avoid or minimise reworking and avoid wastage

                                                                                       Use mathematical ideas and techniques to correctly calculate time to complete tasks, estimate
Use mathematical ideas and techniques                                Level 1
                                                                                       measurements, distances and levels, calculate material requirements and establish quality checks

                                                                                       Use workplace technology related to erection and dismantling of formwork for footings and slabs on
Use technology                                                       Level 1           ground, including the use of calculators, the use of communication devices and the reporting/recording of
                                                                                       results




          Construction Curriculum Framework                   September 2004            BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                              249
       Element                       Performance Criteria                                       Range Statement                             HSC Requirements and Advice
1   Plan and prepare         1.1          Work instructions, including plans,      The Range Statement provides advice to                Learning experiences for the HSC must address:
                                          specifications, quality requirements     interpret the scope and context of this unit of
                                          and operational details are obtained,    competency allowing for differences between           A range of sources for work instructions including:
                                          confirmed and applied                    enterprises and workplaces. It relates to the unit    • work schedules
                                                                                   as a whole and facilitates holistic assessment.       • job sheet/plans/specifications
                                                                                   The following variables relate to this particular     • organisation/company bulletins/memos
                                                                                   unit:                                                 • Material Safety Data Sheets (MSDS)
                                                                                                                                         • diagrams/sketches/maps
                                                                                   Unit scope                                            • job safety analysis (JSA)/safe work method
                                                                                   • Planning and preparation is to include but not        statements
                                                                                     be limited to worksite inspection, equipment        • regulations/legislation
                                                                                     defect identification, assessment of conditions
                                                                                                                                         • manufacturer/organisation/site guidelines,
                                                                                     and hazards and determination of work
                                                                                                                                           policies and procedures
                                                                                     requirements
                                                                                                                                         • Australian Standards.
                                                                                   Quality Requirements
                                                                                   • Quality requirements are to include but not         An awareness of various modes of communication
                                                                                     be limited to relevant regulations including        to receive work instructions including:
                                                                                     Australian Standards, internal company              • verbal
                                                                                     quality policy and standards, workplace                - face-to-face (supervisor to employee)
                                                                                     operations and procedures and manufacturers            - telephone/mobile phone
                                                                                     specifications where specified                         - two-way radio
                                                                                                                                            - on-site meetings
                                                                                   Communications                                        • written communication
                                                                                   • Communications are to include but not                  - work plans
                                                                                     limited to verbal and visual instructions and          - memos/messages
                                                                                     fault reporting and may include mobile phone,          - job descriptions/statements
                                                                                     site specific instructions, written instructions,      - workplace forms
                                                                                     plans or instructions related to job/task, two         - rosters
                                                                                     way radio and hand signals                             - facsimile
                                                                                   • On site meeting processes may include                  - email
                                                                                     notification/scheduling (time, place, purpose),        - intranet
                                                                                     task discussions and local coordination of          • non-verbal
                                                                                     procedural and operational issues                      - gestures
                                                                                   Information                                              - signals
                                                                                   Information sources may include but not be               - signage
                                                                                   limited to                                               - diagrams.
                                                                                   • verbal or written and graphical instructions,
                                                                                      signage, work schedules/plans/specifications,      Planning and preparation for a range of formwork
                                                                                      work bulletins, memos, material safety data        activities.
                                                                                      sheets (MSDS), diagrams or sketches
                                                                                   • safe work procedures related to erection and        A basic overview of the role of employees in
                                                                                      dismantling of formwork for footings and           quality assurance.
                                                                                      slabs on ground

      Construction Curriculum Framework                 September 2004            BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                              250
Element                        Performance Criteria                                    Range Statement                             HSC Requirements and Advice
                                                                           • regulatory/legislative requirements pertaining
                                                                             to erection and dismantling of formwork for
                                                                             footings and slabs on ground
                                                                           • manufacturer’s specifications and instructions
                                                                           • organisation work specifications and
                                                                             requirements
                                                                           • instructions issued by authorised
                                                                             organisational or external personnel
                                                                           • relevant Australian Standards

                       1.2          Safety requirements are followed in    Safety (OH&S)                                       Learning experiences for the HSC must address:
                                    accordance with safety plans and       • OH&S requirements are to be in accordance
                                    policies                                                                                   A basic awareness of occupational health and safety
                                                                             with State or Territory legislation and
                                                                                                                               (OHS) regulations and legislation relevant to the
                                                                             regulations, organisational safety policies and
                                                                                                                               construction industry.
                                                                             procedures, and project safety plan. This may
                                                                             include protective clothing and equipment, use
                                                                                                                               An awareness of project/site safety plan.
                                                                             of tools and equipment, workplace
                                                                             environment and safety, handling of materials,
                                                                                                                               An awareness of safe work practices including:
                                                                             use of fire fighting equipment, organisational
                                                                             first aid, hazard control, hazardous materials    • OHS induction training (general, work activity
                                                                             and substances                                      and site-specific)
                                                                           • Personal protective equipment is to include       • selection, use and maintenance of personal
                                                                             that prescribed under legislation, regulation       protective equipment (PPE)
                                                                             and workplace policies and practices              • access to appropriate communication devices
                                                                           • Safe operating procedures are to include but      • selection of appropriate tools for the task
                                                                             not be limited to the conduct of operational      • correct use, maintenance and storage of tools,
                                                                             risk assessment and treatments associated with      equipment and machinery
                                                                             power cables (including overhead service          • correct handling, application, transport and
                                                                             trays, cables and conduits), lighting, earth        storage of hazardous and non-hazardous
                                                                             leakage boxes, trip hazards, working with           materials
                                                                             dangerous materials, working in confined          • safe posture (sitting, standing, bending, twisting
                                                                             spaces, surrounding structures, restricted          and lifting)
                                                                             access barriers, traffic control, working at      • correct manual handling (lifting and transferring)
                                                                             heights, working in proximity to others,          • correct selection and use of fire fighting
                                                                             worksite visitors and the public                    equipment
                                                                           • Emergency procedures related to this unit are       - fire blanket
                                                                             to include but may not be limited to                - fire extinguishers
                                                                             extinguishing fires, organisational first aid       - fire hydrant and hose
                                                                             requirements and evacuation                       • hazard identification and risk control
                                                                                                                               • basic first aid training and access to first aid kits
                                                                           Statutory/Regulatory Authorities
                                                                                                                               • access to sufficient drinking water
                                                                           • Statutory/regulatory authorities may include
                                                                                                                               • procedures to follow in the event of an
                                                                             Federal, State and Local Authorities
                                                                                                                                 emergency
                                                                             administering the applicable acts, regulations
                                                                             and codes of practice                             • effective communication and teamwork

Construction Curriculum Framework                September 2004           BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                             251
Element                        Performance Criteria                                         Range Statement                             HSC Requirements and Advice
                                                                                                                                     • adherence to work instructions, organisation/
                                                                                                                                       company policies and standard operating
                                                                                                                                       procedures.

                       1.3          Signage/barricade requirements are         Communications                                        Learning experiences for the HSC must address:
                                    identified and implemented                 • Communications are to include but not
                                                                                                                                     Selection and use of standard signage and
                                                                                 limited to verbal and visual instructions and
                                                                                                                                     barricades common to the general construction
                                                                                 fault reporting and may include mobile phone,
                                                                                                                                     industry as well as specific to formwork activities:
                                                                                 site specific instructions, written instructions,
                                                                                 plans or instructions related to job/task, two      • legislative requirements
                                                                                 way radio and hand signals                          • meaning of colour and shape
                                                                                                                                     • appropriate placement and positioning.

                       1.4          Plant, tools and equipment selected to     Tools and Equipment                                   Learning experiences for the HSC must address:
                                    carry out tasks are consistent with the    • Tools and equipment are to include but not be
                                    requirements of the job, checked for                                                             General features, purpose, maintenance and
                                                                                 limited to measuring tapes/rules, hammers,
                                    serviceability and any faults are                                                                working knowledge of a range of formwork tools
                                                                                 spirit levels, squares (combination/tri), nail
                                    rectified or reported prior to                                                                   and equipment.
                                                                                 bags, chisels, hand saws, saw stools, string
                                    commencement                                 lines, shovels, marking equipment, pinch bars,
                                                                                                                                     Procedures and documentation for identifying
                                                                                 automatic levels, laser levels and may include
                                                                                                                                     faulty tools and equipment including:
                                                                                 but not be limited to power saws, power drills,
                                                                                 nail guns, air compressors and hoses, power         • malfunctions
                                                                                 leads, spanners, steel squares and bevels           • worn, broken or missing components
                                                                                                                                     • broken or missing safety guards.
                                                                               Communications
                                                                               • Communications are to include but not               An awareness of the signs of poor performance and
                                                                                 limited to verbal and visual instructions and       inefficiency including:
                                                                                 fault reporting and may include mobile phone,       • noise
                                                                                 site specific instructions, written instructions,   • quality of end product
                                                                                 plans or instructions related to job/task, two      • appearance
                                                                                 way radio and hand signals                          • vibration
                                                                                                                                     • rough running
                                                                                                                                     • failure to start
                                                                                                                                     • presence of smoke and odours
                                                                                                                                     • consumption of fuel and other consumables
                                                                                                                                     • blockages
                                                                                                                                     • amount of maintenance required
                                                                                                                                     • time taken to complete the job.

                                                                                                                                     The importance of acting within their level of
                                                                                                                                     authority in terms of:
                                                                                                                                     • taking initiative
                                                                                                                                     • problem-solving
                                                                                                                                     • decision-making.

Construction Curriculum Framework                 September 2004              BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                                252
Element                        Performance Criteria                                    Range Statement                            HSC Requirements and Advice
                                                                                                                              Personnel to whom problems should be reported:
                                                                                                                              • supervisor/manager
                                                                                                                              • supplier/manufacturer.

                                                                                                                              Reporting of serious faults including:
                                                                                                                              • verbal notification to appropriate personnel
                                                                                                                              • recording on job card/maintenance log
                                                                                                                              • safety/lockout tagging where appropriate.

                                                                                                                              Reasons for safety/lockout tagging including:
                                                                                                                              • ease of identification
                                                                                                                              • evidence of serviceability
                                                                                                                              • preventing use until repaired.

                                                                                                                              Solutions to a range of potential faults.


                       1.5          Material quantity requirements are     Environmental Requirements                         Learning experiences for the HSC must address:
                                    calculated in accordance with plans    • Environmental requirements are to include
                                    and/or specifications                                                                     A working knowledge of the following to enable
                                                                             but are not limited to waste management,
                                                                                                                              the calculation of quantities for formwork activities:
                                                                             noise, dust, vibration and clean-up
                                                                             management                                       • measuring tools
                                                                                                                              • appropriate units of measurement
                                                                           Materials                                          • scale drawings
                                                                           • Materials are to include but not be limited to   • stock sizes
                                                                             boxing (either timber, metal, masonry, fibre     • materials lists
                                                                             cement sheeting, reconstituted timber            • mathematical concepts and formulae
                                                                             products) and may include but not be limited     • waste minimisation
                                                                             to nails/spikes, bolts and nuts, coach screws,   • working with geometric and irregular shapes.
                                                                             steel tie rods, metal brackets and patented
                                                                             metal fasteners                                  Measurements, calculations and determination of
                                                                                                                              material quantities for a range of projects of varying
                                                                                                                              complexity.

                                                                                                                              An awareness of the consequences of incorrect
                                                                                                                              measurements and calculations for:
                                                                                                                              • the client
                                                                                                                              • the organisation/company
                                                                                                                              • the environment.

                                                                                                                              Recording calculations.




Construction Curriculum Framework                 September 2004          BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                             253
Element                        Performance Criteria                                      Range Statement                            HSC Requirements and Advice
                       1.6          Materials appropriate to the work        Safety (OH&S)                                       Learning experiences for the HSC must address:
                                    application are identified, obtained,    • OH&S requirements are to be in accordance
                                    prepared, safely handled and located                                                         Correct handling, application, transport and storage
                                                                               with State or Territory legislation and
                                    ready for use                                                                                of hazardous and non-hazardous materials used in
                                                                               regulations, organisational safety policies and
                                                                                                                                 formwork activities.
                                                                               procedures, and project safety plan. This may
                                                                               include protective clothing and equipment, use
                                                                                                                                 An awareness of information provided in Material
                                                                               of tools and equipment, workplace
                                                                                                                                 Safety Data Sheets (MSDS):
                                                                               environment and safety, handling of materials,
                                                                               use of fire fighting equipment, organisational    • manufacturer’s/supplier’s details
                                                                               first aid, hazard control, hazardous materials    • physical description and properties
                                                                               and substances                                    • identification of substance
                                                                                                                                 • use
                                                                             Materials                                           • ingredients
                                                                             • Materials are to include but not be limited to    • health hazard information
                                                                               boxing (either timber, metal, masonry, fibre      • first aid
                                                                               cement sheeting, reconstituted timber             • precautions for use
                                                                               products) and may include but not be limited
                                                                                                                                 • safe handling information
                                                                               to nails/spikes, bolts and nuts, coach screws,
                                                                                                                                 • control point.
                                                                               steel tie rods, metal brackets and patented
                                                                               metal fasteners
                                                                                                                                 How and where to obtain required MSDS.


                       1.7          Environmental protection                 Environmental Requirements                          Learning experiences for the HSC must address:
                                    requirements are identified for the      • Environmental requirements are to include
                                    project in accordance with                                                                   Environmental hazards/threats including:
                                                                               but are not limited to waste management,
                                    environmental plans and regulatory         noise, dust, vibration and clean-up               • chemical/gas spillage/leakage
                                    obligations and applied                    management                                        • faulty tools, equipment and machinery
                                                                                                                                 • flood
                                                                             Statutory/Regulatory Authorities                    • fire
                                                                             • Statutory/regulatory authorities may include      • wildlife habitat destruction
                                                                               Federal, State and Local Authorities              • discharge into waterways
                                                                               administering the applicable acts, regulations    • pollution
                                                                               and codes of practice                             • soil erosion.

                                                                                                                                 Consequences of poor environmental planning for
                                                                                                                                 the following:
                                                                                                                                 • waterways
                                                                                                                                 • wildlife habitats
                                                                                                                                 • neighbouring properties
                                                                                                                                 • roads and amenities.

                                                                                                                                 An awareness of project environment management
                                                                                                                                 plan.



Construction Curriculum Framework                 September 2004            BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                           254
      Element                        Performance Criteria                                      Range Statement                          HSC Requirements and Advice
                                                                                                                                     Strategies for minimisation of potential negative
                                                                                                                                     environmental impacts including:
                                                                                                                                     • environmental hazard identification and risk
                                                                                                                                        minimisation and reporting
                                                                                                                                     • minimisation strategies
                                                                                                                                       - regular maintenance of machinery and
                                                                                                                                           equipment
                                                                                                                                       - use of biodegradable/non-toxic materials
                                                                                                                                       - silt control
                                                                                                                                       - habitat protection
                                                                                                                                     • re-vegetation and stabilisation
                                                                                                                                     • waste minimisation
                                                                                                                                       - accurate measurements and calculations
                                                                                                                                       - recycling
                                                                                                                                       - using recyclable products
                                                                                                                                       - resource efficiency
                                                                                                                                     • improvement strategies
                                                                                                                                     • environmental monitoring
                                                                                                                                     • emergency procedures.
                                                                                                                                     A basic awareness of the roles and responsibilities
                                                                                                                                     ofn:
                                                                                                                                     • the NSW Department of Environment and
                                                                                                                                       Conservation [incorporating Environment
                                                                                                                                       Protection Authority (EPA)]
                                                                                                                                     • local government.

2   Erect formwork           2.1          Design of footing and/or slab on         Unit scope                                        Learning experiences for the HSC must address:
                                          ground is identified from job            • Formwork shutters and/or edge boxing is to
                                          drawings, specifications and checked                                                       Requirements for formwork including:
                                                                                     include an edge rebate
                                          to be in accordance with legislation/                                                      • accuracy
                                                                                   • Types of formwork are to include but not be
                                          regulations/codes of practice              limited to prefabricated or in-situ             • strength
                                                                                   • Formwork is to be rigid to withstand the mass   • rigidity
                                                                                     of wet concrete and actions imposed during      • water tightness
                                                                                     placement                                       • durability
                                                                                   • Formwork is critical to comply with             • termite barriers.
                                                                                     specifications to height and level              Symbols/abbreviations/terminology relating to slab
                                                                                   • Constructed formwork may include but not be     on ground as indicated on plans/drawings.
                                                                                     limited to timber, metal or prefabricated for
                                                                                     both footings and slabs on ground
                             2.2          Formwork is set out to requirements                                                        Learning experiences for the HSC must address:
                                          of drawings and specifications           Statutory/Regulatory Authorities
                                                                                                                                     Processes for:
                                                                                   • Statutory/regulatory authorities may include
                                                                                     Federal, State and Local Authorities            • measuring
                                                                                                                                     • setting out.

      Construction Curriculum Framework                 September 2004            BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                         255
Element                        Performance Criteria                                      Range Statement                           HSC Requirements and Advice
                                                                               administering the applicable acts, regulations   An understanding of:
                                                                               and codes of practice                            • line
                                                                                                                                • level
                                                                                                                                • plumb.
                                                                                                                                Appropriate levels and falls as identified from
                                                                                                                                instructions.
                                                                                                                                Formwork techniques.


                       2.3          Fixing/fasteners are selected                                                               Learning experiences for the HSC must address:
                                    consistent with construction
                                    requirements of the job                                                                     A range of fixing/fasteners appropriate to
                                                                                                                                concreting applications including:
                                                                                                                                • nails
                                                                                                                                • screws
                                                                                                                                • clamps
                                                                                                                                • bolts.


                       2.4          Formwork shutters and/or edge                                                               Learning experiences for the HSC must address:
                                    boxing are constructed and erected to
                                    site requirements and specifications                                                        An awareness of the purpose of rebates on slab
                                                                                                                                edges.


                       2.5          Formwork support is braced to job
                                    requirements and specifications


                       2.6          Block outs and cast in services are
                                    installed to specified locations


                       2.7          Release agents are applied to                                                               Learning experiences for the HSC must address:
                                    formwork face, where specified, to
                                    manufacturers specifications                                                                Purpose of release agents including:
                                                                                                                                • parting compound to facilitate easy release of
                                                                                                                                  formwork from concrete
                                                                                                                                • sealant to prevent formwork absorbing water
                                                                                                                                • avoid stains or disfigure of concrete surface.
                                                                                                                                Release agents including:
                                                                                                                                • oil
                                                                                                                                • mould cream
                                                                                                                                • water soluble emulsion
                                                                                                                                • chemical reactive agents
                                                                                                                                • barrier paints and coatings.

Construction Curriculum Framework                 September 2004            BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                          256
      Element                        Performance Criteria                                      Range Statement                            HSC Requirements and Advice
3   Strip formwork           3.1          Edge boxing and bracing/strutting        Safety (OH&S)                                       Learning experiences for the HSC must address:
                                          support is removed sequentially and      • OH&S requirements are to be in accordance
                                          safely                                                                                       Removal techniques and sequence to avoid damage
                                                                                     with State or Territory legislation and
                                                                                                                                       to corners and edges of slab.
                                                                                     regulations, organisational safety policies and
                                                                                     procedures, and project safety plan. This may
                                                                                     include protective clothing and equipment, use
                             3.2          Timber components are de-nailed,           of tools and equipment, workplace                 Learning experiences for the HSC must address:
                                          cleaned and stored/stacked safely for      environment and safety, handling of materials,
                                          reuse or removal from site                                                                   The importance of:
                                                                                     use of fire fighting equipment, organisational    • storing materials for ease of retrieval considering
                                                                                     first aid, hazard control, hazardous materials      - where they will be used on site
                                                                                     and substances                                      - when they will be used
                                                                                                                                       • stacking method appropriate to material
                             3.3          Steel components are cleaned, oiled
                                                                                                                                       • good housekeeping
                                          and stored/stacked to manufacturer's
                                          maintenance recommendations                                                                  • waste minimisation.


                             3.4          Damaged formwork components are
                                          safely discarded after stripping


4   Clean up                 4.1          Work area is cleared and materials       Materials                                           Learning experiences for the HSC must address:
                                          disposed of, reused or recycled in       • Materials are to include but not be limited to
                                          accordance with legislation/                                                                 An awareness of procedures for minimisation of
                                                                                     boxing (either timber, metal, masonry, fibre
                                          regulations/codes of practice and job                                                        impact on the environment including:
                                                                                     cement sheeting, reconstituted timber
                                          specification                              products) and may include but not be limited      • replacing disturbed or removed soil
                                                                                     to nails/spikes, bolts and nuts, coach screws,    • removal and disposal of non-reusable materials in
                                                                                     steel tie rods, metal brackets and patented         a responsible manner
                                                                                     metal fasteners                                   • work materials
                                                                                                                                       • plant debris and other organic matter
                                                                                   Environmental Requirements                          • chemicals
                                                                                   • Environmental requirements are to include         • safe storage of reusable materials in accordance
                                                                                     but are not limited to waste management,            with company policy
                                                                                     noise, dust, vibration and clean-up               • containment of loose materials on site (such as
                                                                                     management                                          mud, dust, litter and waste material)
                                                                                   Statutory/Regulatory Authorities                    • control of run-off.
                                                                                   • Statutory/regulatory authorities may include
                                                                                     Federal, State and Local Authorities              Environmental requirements for dealing with waste
                                                                                     administering the applicable acts, regulations    including:
                                                                                     and codes of practice                             • recycling
                                                                                                                                         - paper-based products
                                                                                   Tools and Equipment                                   - plastic
                                                                                   • Tools and equipment are to include but not be       - worn components
                                                                                     limited to measuring tapes/rules, hammers,          - metal components
                                                                                     spirit levels, squares (combination/tri), nail      - construction materials
                                                                                     bags, chisels, hand saws, saw stools, string        - building components

      Construction Curriculum Framework                 September 2004            BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                            257
Element                        Performance Criteria                                   Range Statement                            HSC Requirements and Advice
                                                                            lines, shovels, marking equipment, pinch bars,    • approved disposal of
                                                                            automatic levels, laser levels and may include      - hazardous material
                                                                            but not be limited to power saws, power drills,     - non-hazardous material.
                                                                            nail guns, air compressors and hoses, power
                                                                            leads, spanners, steel squares and bevels
                       4.2          Plant, tools and equipment are                                                            Learning experiences for the HSC must address:
                                    cleaned, checked, maintained and
                                    stored in accordance with                                                                 Clean-up procedures with due consideration to the
                                    manufacturers' recommendations and                                                        environment and OHS.
                                    standard work practices
                                                                                                                              A range of cleaning techniques including:
                                                                                                                              • wiping
                                                                                                                              • washing
                                                                                                                              • brushing
                                                                                                                              • sweeping
                                                                                                                              • scraping
                                                                                                                              • use of cleaning agents (chemicals, solvents and
                                                                                                                                detergents).

                                                                                                                              Cleaning equipment including:
                                                                                                                              • high pressure water cleaner
                                                                                                                              • wet/dry vacuum
                                                                                                                              • brooms and brushes
                                                                                                                              • scrapers.

                                                                                                                              Tools and equipment cleaning/maintenance
                                                                                                                              requirements as necessary including:
                                                                                                                              • removal of dirt, dust, grease and oil
                                                                                                                              • sharpening
                                                                                                                              • anti-rust treatments
                                                                                                                              • repair/replacement of missing/damaged parts
                                                                                                                              • scheduled servicing
                                                                                                                              • refuel and top-up consumables.

                                                                                                                              An awareness of issues relating to storage of tools
                                                                                                                              and equipment including:
                                                                                                                              • climatic effects
                                                                                                                              • OHS considerations
                                                                                                                              • stability
                                                                                                                              • security
                                                                                                                              • ease of access.




Construction Curriculum Framework                September 2004          BCGCA2003B Erect and dismantle formwork for footings and slabs on ground                           258

				