					Community and Technical Colleges
 Center for Information Services
  Re-Hosting Project Update


                      Presentation to the




                      January 12, 2006
             Community and Technical Colleges
              Center for Information Services
               Re-Hosting Project Update


                     Introductions

       Jack Oharah – Edmonds Community College
       Corey Knutsen – CIS
       Jim Popa – Hewlett-Packard Company




2
                  Community and Technical Colleges
                   Center for Information Services
                    Re-Hosting Project Update

                                 Project Status
       Original project scope still in place
         – Substantial accomplishments since project inception
         – More mandated changes to the old code have to be made
            because of the delays

       The revised project schedule will be available after a key technical
        uncertainty is resolved
         – HP has determined that it cannot rely on the database input/output
           portion of the Transoft technology and is seeking a new solution
       Project costs
         – Estimates for additional CIS Staff and QA expense will be provided
            when the new project schedule is available

3
                   Community and Technical Colleges
                    Center for Information Services
                     Re-Hosting Project Update


                      Progress Since Last Report

       Project management processes improved
       Infrastructure and security reviewed – work in progress
       Steps taken for early access to reporting and test data
       Project plan revised
         –   Short-term tasks identified and being tracked
         –   Ready when database input/output solution selected
       Began process to select and test alternative database
        input/output solutions

4
                Community and Technical Colleges
                 Center for Information Services
                  Re-Hosting Project Update


    Transoft Role and Database Input/output Concerns
       Translate business logic
             Migrating with few problems
       Convert screens
             Some migration issues, but none of serious concern
       Convert database calls
             Serious functionality and performance issues with many

               of the database input/output routines




5
                   Community and Technical Colleges
                    Center for Information Services
                     Re-Hosting Project Update


          Schedule for Developing Revised Project Plan
       Database input/output testing        30 Jan 06
       Investigate alternative approaches   13 Feb 06
       Test alternative approaches          13 Mar 06
       Select new approach                  20 Mar 06
       Finalize overall schedule            31 Mar 06




6
                 Community and Technical Colleges
                  Center for Information Services
                   Re-Hosting Project Update


       HP has taken actions to address the identified issues on the
        CIS Re-Hosting Project. The assessment has uncovered a
        serious technical issue.
       HP is working collaboratively with CIS with the common goal of
        resolving all people, process and technical issues and getting
        the project on track.
       HP’s project team will be successful with the joint support of HP
        and CIS management.
       HP remains committed to achieving tangible progress on the
        project, providing a total project schedule and successfully
        delivering the project.
7
              Community and Technical Colleges
               Center for Information Services
                Re-Hosting Project Update


                        Lessons Learned
       A more extensive proof-of-concept evaluation might
        have exposed the database input/output deficiency
        earlier in the project
       Establish governance meetings with HP executives
        early in the project to enable more effective
        escalation of project issues
       Establish early independent quality assurance
        presence

8
    Community and Technical Colleges
     Center for Information Services
      Re-Hosting Project Update



             Questions?