					                                    HSC-2000BD
                  M i c r o c o m p u t e r M e a s ur i n g S y s t e m
                                    Instr ucti on




                No.:

                 Q ing da o Ma nk e B alanc in g Mac hin e Pla nt

                                         (1)




Qingdao Manke Balancing Machine Plant       HSC-2000BD Microcomputer
                                                                           2/13
                                                         Measuring System Instruction




                                                        Catalog

I. Summarization ································· 3

II. Keyboard Instruction ·························· 4

III. Operation ······························ 5

IV. Calibration·································· 6

V. Clamp Compensation Operation·························· 7

VI. Malfunction and Solution···························· 9

VII. Measure Operation Flow Chart························ 10

VIII. Clamp Eccentricity Compensation Flow Chart················ 11

IX. Calibration Operation Flow Chart························ 12

X. Common Question on Operation···················13




                                                      ( 2 )
                                        HSC-2000BD Microcomputer
Qingdao Manke Balancing Machine Plant
                                        Measuring System Instruction
                                                                       3/13
I.       Summarization:
               This electrometric box fits for unbalanced vibration signal measure for single-plane soft and hard
balancing machine.


       Box Input: a、Transducer exports unbalanced vibration signals of support surface of rotor.

                       b、One standard signal exported by switch.

       Box Output: a、Adopt digital displayed unbalanced values and balancing rotate speed of two

correction planes and radiuses.
       Adopt industrial computer (SCM) and international universal digital and analog integrate circuit in
electrometric box. Simple operation, straight display, stable performance efficient.
        2、Box Working Environment:
        、Environmental Temperature
      (1)                                                   0℃<t< 40℃
        、Air Relative Humidity
      (2)                                         ≤85%(25℃)
        、Power Voltage
      (3)                                     AC220±10%
        、Power Frequency
      (4)                                      50Hz±5
      3、Main Technical Index
        、Min. Remaining Unbalance
      (1)                                      emar(Check instruction for details)
        、Unbalance Reduction Rate
      (2)                                             URR    (Check instruction for details.)
        、Measuring Time
      (3)                                      <8s
    4、Box Wire in Rear Plane
      The following chart shows rear plane of the box. Please check whether connection of fittings installed
are good or not:
        、Transducer plug and socket.
      (1)
        、Standard signal plug and socket.
      (2)
        、Power supply plug and socket.
      (3)
        、Examine whether fuse is good or not and connect it with power supply.
      (4)

                                                                            Power Switch

                                                                                 Fuse

                Transducer                                  In-phase    Signal     Interface
             Power Socket


                                                ( 3 )
     Qingdao Manke Balancing Machine                 HSC-2000BD
                 Plant                               Microcomputer               4/13
                                                           Measuring System
                                                             Instruction


II. 1. Front Plate Introduction


      幅值和相位                                              操作键盘
                         锁相指示灯




                          暂停指示灯 不平衡大小范围

                                                                                                      SET
                                                                        1          2         3


                                                                                                      HALT
                                                                        4          5         6
2 Keyboard Instruction
                                                                                                      EXE
                                                                        7          8         9


                                                                                CONTIN               QUIT
                                                                        0
                                                                                  0
                                                                                           +/-

           SET —— Function 1. Calibration { Check the fourth part on operation method }

                     —— Function 2. Set rotate speed (Check the third part, chapter (7) on operation method)
                     ——Function 3. Choose rotor size document. (Check the seventh part on operation method)
           HALT—— Press this key in balancing measure, corresponding indicator light becomes bright. Displayed
value maintains its value. Press this key for continuous measure.
                             ——Press this key in balancing measure, corresponding indicator light
                                       becomes bright. It records all measured results at the moment.
    EXE —— Press this key for approval and execute the next step.
     QUIT ——Press this key to for entering the system again whenever. Operation starts from the beginning.

Increase Weight and De-Weight(+/-)——Press this key in balancing measure, corresponding indicator light changes to
    show increase or decrease of weight.




                                                   ( 4 )
                                                  HSC-2000BD
                                                                            5/13
 Qingdao Manke Balancing Machine                  Microcomputer
             Plant                               Measuring System
                                                   Instruction




              1           2         3


              4           5         6


              7           8         9

                     CONTIN
              0
                          




                            ——These 11 keys are used for setting rotor parameter and rotate speed.
                   Any key pressed, electrometric box will send out ringing voice. After entering
                   rotor parameter, this machine will not maintain these parameters permanently (r,
                   SP, etc.) until entering new parameter.

  III. Operation Steps:
  (1)   、Measuring system enters into self-detection status when it connects with power supply or
  after pressing “QUIT”. When it runs in normal status, the screen displays:
                         “Manke Balancing Machine”
       、
  (2) Install workpiece
  (3) 、Press “EXE”, it shows: “Please input workpiece parameter.”
                           r=ZZZZ
  Rotor radius r values “ZZZZ”mm. Input r size by keyboard and press “EXE”. Press “EXE” dir
  (4) 、Displays: “Please input measuring rotate speed.”
                          sp = ZZZZ
   Balancing rotate speed is “ZZZZ”r/min, input this parameter by keyboard, otherwise, press
“EXE” directly.
  (5)Displays: “Please start the motor.”
     Start the motor to make rotor in operation.
                                  ( 5 )
                                    HSC-2000BD
                                                      6/13
Qingdao Manke Balancing Machine     Microcomputer
            Plant                  Measuring System
                                     Instruction
    、If
  (6) the operation is normal, “PLL” in the panel will become bright.
       、①
  (7) If the rotor in normal operation, displayed rotate equals to set rotate speed and the screen
  displays the status as:

             Amplitude            Rotate Speed
             Phase(degree)           (r/min)
     Bearing Mode 0, Compensation None, Adjustment Mode Increase Weight




  ②、If rotate speed displayed not equals to set speed, press “SET” to change set rotate speed
    and make it equals to displayed rotate speed.
 (8) 、Make corresponding increase weight or de-weight according to displayed values. Increase or decrease weight unit is
(gram).
   (Note: for same specification size of workpiece, same R and sp, measure directly.)
(9) 、Press “QUIT” after the operation and turn off power supply.
 If you want to change parameter in the operation course, press “QUIT” and back to (1)
  (10)  、Printing Function: If you need to print, press “HALT” +“ 。 。” under measuring status
       when the machine equipped with external printer.
IV. Calibration
             Measuring precision might be reduced because of bump in transportation or
      long-term application, so we have to reset for adjusting the machine to enhance the
      precision. Calibration instruction as follows: (Note: Do not set by voluntariness)

Notice: Before the calibration operation, remember to change adjusting mode into
             weight-increasing status under measuring status, otherwise balanced angle will
             not accurate!
 (1) 、Start power supply or press “QUIT”, the machine shows:
                                         Manke Balancing Machine
   Install proving rotor, press “SET”, the screen displays: “Please input function No.”
                                                                F=0000
   Input “0757”, and press “EXE”, the screen displays:
                         Calibration operation Press “EXE” to start.
      Press “EXE”, it shows: “Please enter measuring rotate speed.”
                                                              sp= ZZZZ




                                                            (6)
  Qingdao Manke Balancing Machine                               HSC-2000BD
              Plant                                             Microcomputer               7/13
                                                             Measuring System
                                                               Instruction


      Balancing rotate speed is “ZZZZ”rpm, input this parameter by keyboard, or press “EXE” directly.
                             Machine shows: pp=ZZZZ
      Unbalanced value owns “Z” decimals (X=1-3), input “Z” by keyboard and press “EXE”. If you don't want to
      change set parameter, press “EXE” directly.
  、The machine displays
(2)
                        “Please start the motor”
   Start the machine. The instrument stop after a few seconds, indictor lights (HOLD) twinkle and give out little
   sound, screen displays “Please halt.” At this moment stop the machine.After that, it shows:
                  “Please input trial weight.”
                                         UP=ZZZZ
  、Rotate the rotor to 0 degree location, increase trial weight and input trial weight, after that press “EXE” key, the
(3)
   machine displays:
                         “Please start the motor.”
   、Here, machine starts. After a few seconds, it shows:
 (4)
                                 “Manke Balancing Machine”
(5)、Brake (Stop) the machine and unload trial weight. Calibration finished. Transfer into normal balancing
   operation course. (Check III. Operation Method)
 Note:
       a、Input format for trial weight in the calibration:
             E.g.1 AP = 2.00【g】
              E.g. 2. AP = 10.0【g】
          After
      b、 the calibration, if the unbalanced values caused by clamp eccentricity are too big. Meanwhile, there exits
      error between clamp and workpiece, so it needs further clamp compensation.

  .
 V Clamp Compensation
 (1) 、Open power supply or after pressing “QUIT”, the machine displays:
                                     “Manke Balancing Machine”
   Install proving rotor, press “SET”, the machine displays:
                              F=0000
   Input “8051”, the screen displays “Press „EXE‟ to start eccentricity compensation.” and then




                                                           (7)
Qingdao Manke Balancing Machine                            HSC-2000BD
            Plant                                          Microcomputer                    8/13
                                                         Measuring System
                                                           Instruction


    Press “EXE”, the screen displays:
                        “Please start the motor.”
      At this time, start the rotor.
      、If
  (2) the rotor under normal operation, displayed rotate speed equals to set rotate speed, screen displays original values
unbalanced.


                Amplitude          Rotate Speed
                Phase(degree)            (r p m)
         Bearing Mode 0,  Compensation None, Adjustment Mode Increase Weight




             (3)  、The instrument stop indicator light (HOLD) twinkles and gives out sound after running for a few seconds,
the screen displays:
           “Please stop.”. Press HALT. After a while, it displays:
                             “Turn the axis 180° relative to workpiece”
    、Loose clamp, rotate rotor 180° relative to clamp, lock the clamp tight. Press “EXE”, the instrument displays:
  (4)
                         “Please start the motor.”
    、Start the motor and make rotor in operation, screen displays unbalancing status after original compensation:
  (5)

           Amplitude           Rotate Speed
          Phase(degree)             (r p m)
   Bearing Mode 0,   Compensation Has, Adjustment Mode Increase Weight




 (6) 、The stop indicator light (HOLD) of instrument twinkles and gives out sound after
   running for a few second. The instrument displays:
                          “Manke Balancing Machine”
 (7)、Clamp compensation finished. Enter into normal operation. (Check III. Operation Method)
  Note:
        a、Clamp compensation requires little error between clamp and workpiece, otherwise, compensating effect is not
good.
     b、Compensation for clamp again when replacing clamp.
        C、Methods for exiting clamp compensation:
          After startup, press “SET”, the screen displays “Please enter function No.”, “F=0000”
        Input “8052”, and then press “EXE”, the screen displays:




                                                            (8)
                                                           HSC-2000BD

                                                                                        9/13
  Qingdao Manke Balancing Machine                          Microcomputer
              Plant                                       Measuring System
                                                            Instruction


                                “Please input compensation status.”
                                “AC=X”
    Thereinto “X” is “0” or “2”。
         AC = 0 signs non-compensation status(status after calibration)
      AC = 2 signs clamp compensation status(clamp working status after compensation)
Change its value into 0 and then press “EXE”.

VI. Malfunction and Solution


    、LED displays Err… and constantly twinkle for wrong entered parameter or internal
  (1)

    circuit malfunctions.

    、Replace wires for sensor or finding abnormal sensor signal, find the sensor which has
  (2)

    malfunctions or check the wire, and whether the plug loose or not.

    、For those malfunctions about external wire of electrometric box and others, customers
  (3)

    can fix them out. For internal malfunctions, customers can connect with manufacturer. Do
    not open electrometric box by yourself; otherwise, you take responsibility for the damage.




                                                        (9)
                                         HSC-2000BD Microcomputer
                                                                        10/13
    Qingdao Manke Balancing
         Machine Plant                   Measuring System Instruction


 VII. Measure Operation Flow Chart·


                Self-detection   after   startup,   display
                开机自检, 显 Machine
                Manke Balancing
                示曼科平衡机

                     按"执行"
     Display:    Please   input
                显示请输入工
     workpiece number r=XXXX                 输入校正半径
                件数r =XXXX                          m
                                            ( 单位: m )
                     按"执行"
Display: Please input measuring             输入平衡转速( 不知或不明确时可不输
                显示请输入测
rotate speed SP=XXXX
                                            入, 直接按"执行"键跳过此处, 在不面
                量转速SP=XXXX
                                            显示测量画面时按"SET" 键调节)
                     按"执行"
            Display: Please start
                      显示
            the motor.                      提示启动电机
                 请启动电机

                     启动电机
                                             进入测量画面, 进入测量状态.
            Display measured
                  显示测量值                     ( 数字不跳动, 可直接按一下
            value
                                            "执行"键则可)




                                                (10)
                                                  HSC-2000BD Microcomputer
                                                                                               11/13
    Qingdao Manke Balancing
         Machine Plant                            Measuring System Instruction
  VIII. Clamp Eccentricity Compensation Flow Chart




                       Press “SET”

      Display:    Please      enter
      function No. F=0000

                        Input“8051”, press “EXE”


     Display press “EXE” to             start
     eccentricity compensation.


                        Press “EXE”

      Please start the motor.
                                            Hint to start the motor.
                        Start the motor.

     Enter into measuring status, after a
     few seconds, acousto-optic alarm,
     displays: Please halt.               When numbers not twinkles, press “SET” directly.

                       Stop the motor.

     Turns the axial for 180degree relative to workpiece

                       1. Turns the workpiece for 180 degree relative to clamp
                      2.Press “EXE”

     Please start the motor
                                                Hint to start the motor.
                      Start the motor

    Back to main interface after a
    few seconds and displays                     “Clamp Compensation Operation” finished, start real measure
    Manke Balancing Machine


Notice:
      Note: 1、All of different types of workpiece, clamp and rotate speed need “Clamp Eccentricity
      Compensation” for once.

      2、Before this operation, press “EXE” to enter rotor parameter after “self-detection”, press “QUIT” when
             it shows “Please start the motor.” and back to main interface, execute this operation.
  3、It needs the same operation after executing “SET”.
                                                            (11)
                                              HSC-2000BD Microcomputer
                                                                                              12/13
Qingdao Manke Balancing Machine
            Plant                             Measuring System Instruction



 IX. Calibration Operation Flow Chart

            Self-Detection after startup and displays:
                开机自检显                                                 Please input trail
            Manke Balancing Machine                                   显示请输入所加试                        Input trail weight
                示曼科平衡机                                                weight UP=XXXX
                                                                      重重量UP= XXXX                    输入试重质量
                      按"SET"键                                            1. Increase trial weight for workpiece
                                                                                 proving   radius,    and    0      degree
             Display: Please input function
               显示请输入                                                             在工件校正半径、 0° 方向
                                                                              1、 direction.
             No. F=0000 0000
               功能号F=                                                             加上定标试重。
                                                                              2. Press “EXE”.
                                                                              2、 按“ 执行” 。
                      输入"0757"按" 确认"键
                                                                 Please start the motor.        Hint to start the motor.
                Press “EXE” to start calibration                      显示请启动电机                   提示启动电机
                定标操作按
                                                                         Start the motor.
                " 确定"键开始                                                启动电机
                      按"执行"                                           进入测量状态等
                                                                      Enter       into
                                                                      待几秒, 自动回                    “SET Operation”
                                                                                                 定标操作"完
               Please input measuring rotate                          measuring status
                显示请输入测                                                                          成, 可执行“
                                                                                                  finished, execute
               speed SP=XXXX                                          到主画面 for a
                                                                      and waiting
                量转速SP=XXXX                                                                        “Measuring
                                                                                                测量操作” 和
                                                                       few      seconds,
                      按"执行"                                            back   to main           “ Operation” and
                                                                                                   夹具偏心补
                                                                                                  “Clamp
                                                                                                偿操作” 。
           Please start the motor.
                显示请启动电机                     提示启动电机
                                            Please start the motor.    interface
                                                                                                     Eccentricity
                                                                       automatically.
                       启动电机                                                                          Compensation
    Enter into measuring status, after              When numbers                                     Operation”.
                 进入测量状态,
    a few seconds, acousto-optic                   not   twinkle,
                 数秒后, 声光报                     数字不跳动
    alarm, displays “Please stop.”             press     “SET”
                 警, 显示"请停车"                   时, 可直接按
                                               directly.
                                              一下"定标"
                      停止电机
                      Stop the motor.
                                              键则可.




      Notice: 1. Before this operation, press “EXE” to enter rotor parameter after
                    “self-detection”, start the motor when it shows “Please start the motor.”.
                    Change the status into increasing weight and press “QUIT” and back to the
                    main interface, execute “SET” operation according to the above flow.
                  2. Do not free to change this item after the calibration set by debugging
                  personnel!




                                                         (12)
                                                 HSC-2000BD
                                                                                    13/13
Qingdao Manke Balancing Machine                  Microcomputer
            Plant                               Measuring System
                                                  Instruction


X. Common Questions about The System


   1、    Start the motor after showing “Please start the motor.”. After entering measuring

         interface, only the rotate speed vibrates; other numbers no twinkling; red light

         becomes bright. This is caused by difference between real balancing rotate and

         required SP values. Only need to press “SET” key during measuring status.

   2、    The key of “SET” and calibration operation are two different things. Do not confuse
         between them. Do not free to use SET operation. Conduct this operation under our
         debugging personnel‟s guidance if necessary.

   3、    After startup, it displays “Manke Balancing Machine”. It‟s a main interface under
         self-detection status. When it shows this interface, it shows the electrometric box is
         normal. No realistic meaning for measure.

   4、    Start the motor when it shows “Please start the motor.” It enters measuring

         interface, without number appearance, PLL not bright. This is caused by

         photoelectric head inaccurate location. It only needs to set the photoelectric head

         into vertical place or set it in a certain angle and keep it in a certain distance from

         Reflective sheeting. Meanwhile, enter to measuring interface when the PLL is

         bright. If it displays rotate speed but other numbers not twinkling, see the solution 1

   5、    Please    notice,    whether     the    balancing     operation     correspond       with
         “increase/de-weight” (Set “increase weight light” bright when increasing balance
         and set “de-weight light” bright during reducing balance)

   6、    When speed-testing components close to switch and after a period of application,

         clean switch surface in time or adjust sensing distance to ensure its sensibility.

   7、    Stick Reflective sheeting on the workpiece. Common boundary between reflective

         and non-reflective is 0, angle increase in anticlockwise direction (view from right

         side.)
(13)

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:13
posted:3/3/2010
language:
pages:16