					Nb.   Duration From    To      Activity
1     3 Days   28/8    30/8    HMPID on L3-door (Before door full open)
                               Installation Fittings Mc Farlane
2     2 Wks    31/8    15/9    BACK-F. verification, modifications and
                               pressure test to RB24 side (provisory
                               fittings)
3     4 Wks    18/9    13/10   Pipes from inside L3 to L3-door
4     2 Wks    16/10   27/10   Pipes from L3-door to Low beta platform
5     1 Wk     30/10   3/11    Connection flexible to baby ! to order
      Out L3   3/11

6     2 Wks    6/11    17/11   Mini SF: Install multilayer cooling pipe (to
                               be done on the surface)
7     1 Wk     20/11   24/11   Mini SF: Pressure test (to be done on the
                               surface)
                               Inox pipes on Mini SF should follow
8     1 Wk     27/11   1/12    HMPID pipes from L3 to the Plant (under
                               Low Beta platform)
9     1 Wk     4/12    8/12    HMPID connection to the Plant
10    2 Days   11/12   12/12   HMPID pressure test
      15Wks    Total

11    3 Wks    ?               MINI-F. pipes from L3 to the Plant (on fix
                               shielding service support)
12    1 Wk                     MINI-F. pressure test from L3 to the Plant
                               Inox pipes should follow
13    3 Wks                    TPC pipes outside L3 from RB26 to the
                               Plant (under low beta platform)
14    2 Wks                    TPC connection to the Plant
15    1 Wk                     TPC pressure test from RB26 to the Plant
16    2Wks                     Pipes from low beta platform to plant
17    2 Wks                    Pressure test from inside L3 to the Plant(s)
18    2 Wks                    Flexible Connection from Back frame to
                               detectors
19    2 Wks                    Flexible connection from baby frame to
                               detector
20    1 Wk                     Flexible connection from L3 to Mini
21    1 Wk                     Flexible connection from mini to shielding
      20Wks    Total
      35 Wks   Grd
               Total

				