Project Initiation Stage Plan by dfhrf555fcg

VIEWS: 1,224 PAGES: 5

More Info
									orcestershire ealth                                     rogramme


                            (W061) Worcestershire Telephone Replacement
                                                         (Covering PCT / Mental Health)




                                Project Initiation Stage Plan

Purpose of this document
This document is an initiation stage plan which contains details of the process to produce
two management products; the Project Initiation Document (PID) and the Stage Plan for the
stage immediately following initiation. This product is produced as part of (SU6) which
relates to Prince 2, Start Up 6 (Planning an Initiation Stage).

Version History
 Version                 Issue & Circulation Date                       Brief Summary of Change
 01        22nd Jul 08



           Chris Greening, ICT Programme Manager (chris.greening@nhs.net) (01905 760105)
 Contact   Worcestershire Health ICT Services
           Worcester Royal Hospital, Charles Hastings Way, Worcester, WR5 1DD




                                                    i
Contents
1.    Plan Description ............................................................................................................ 1

2.    Pre-requisites ................................................................................................................ 1

3.    External Dependencies / Responsibilities ...................................................................... 1

4.    Tolerances .................................................................................................................... 1

5.    Reporting ...................................................................................................................... 1

6.    Initiation Stage Plan ...................................................................................................... 2

6.1      Initiation Stage Product Breakdown Structure............................................................ 2

6.2      Initiation Stage Product Flow Diagrams ..................................................................... 3

6.3      Initiation Stage Financial Budget ............................................................................... 3

6.4      Initiation Stage Resource Requirements.................................................................... 3

6.5      Risk Assessment ....................................................................................................... 3




                                                             ii
1. Plan Description
The main objectives of this process are to produce two management products:
     the Project Initiation Document (PID) and..
     the Stage Plan for the stage immediately following initiation.
At the end of initiation the project board will expect to see not only the PID but also a
detailed plan for the next stage, because the extent of their actual commitment will only be
for the next stage.

2. Pre-requisites
Before creating an initiation stage plan the following components should be completed.
   Established project management team
   Completed project brief
   Defined project approach

3. External Dependencies / Responsibilities
The project manager is responsible for planning the initiation stage, however, if applicable
the appointed project assurance and project support roles can also assist / guide.

4. Tolerances
A tolerance or constraint which would normally be of cost, quality or time will be unlikely in
the production of the initiation stage plan. However it should be noted that if the project is
part of a programme that the end date for the initiation stage should be checked against that
held in the programme plan.

5. Reporting
Communication with the Project Board is likely to be so frequent in the initiation stage that
very formal reporting arrangements are not necessary. Normal reporting frequencies may be
too long for such a short stage.




                                           1
6. Initiation Stage Plan
  6.1   Initiation Stage Product Breakdown Structure

     Specialist Products
           1. Project Initiation Document, which includes the information below:
              Background (refined from project brief)
              Project Controls
              Project Organisation Structure (refined from project mandate / brief)
              Project Definition (refined from mandate / brief)
              Outline Business Case (refined from project brief)
              Initial Project Plan
              Communications / Stakeholder Engagement Plan
              Customers Quality Expectations (refined from mandate / brief)
              Exception Plan
              Acceptance Criteria
              Project Contingency Plan
              Project File Structure
              Initial Risk Log (refined from project brief)

           2. Next Stage Plan, which includes the information below:
              Plan Description
              Quality Plan
              Plan Pre-requisites
              External Dependencies
              Tolerances
              Stage Monitoring/Control
              Reporting
              Planning Assumptions
              Stage Plan
                  Stage level Gantt (or bar) chart
                  Stage level Product Breakdown Structure
                  Stage level Product Flow Diagrams
                  Stage level activity network
                  Stage financial budget
                  Stage level work packages
                  Stage level Table of Resource Requirements
              Risk Assessment (refined from project brief)




                                       2
6.2       Initiation Stage Product Flow Diagrams
         Planning quality (IP1)
          o Tolerances
          o Acceptance Criteria
          o Customers Quality Expectations
         Planning a project (IP2)
          o Plan Description
          o Plan Pre-requisites
          o Initial Project Plan
          o Communications / Stakeholder Engagement Plan
          o Exception Plan
          o Project Contingency Plan
         Refine business case and risk log (IP3)
          o Initial Risk Log
          o Outline Business Case
         Set up controls (IP4)
          o Project Controls
          o Reporting
          o Stage Monitoring/Control
          o Tolerance
         Set up files (IP5)
          o Project File Structure
         Assemble into a project initiation document (PID) (IP6)
          o Background
          o Project Organisational Structure
          o Project Definition
          o External Dependencies

6.3       Initiation Stage Financial Budget
          It is unlikely that the initiation stage will have a financial implication, but one
          example is that you may require the resources of a third party to generate some
          specialist area / element of the PID.

6.4       Initiation Stage Resource Requirements
          This section is to ensure that sufficient resources are available to help the project
          manager develop each of the elements of the PID and the subsequent stage
          plan. To be included during this evaluation process are:
                    Management team time
                    Project Assurance
                    Project Support
                    Other (third party consultation etc.)

6.5       Risk Assessment
          Management of Risk is done so by exception. The initial risk log will have been
          created.




                                          3

								