Project Monthly Status Report Template

Reviews
Shared by: gigi12
Stats
views:
1396
rating:
6(1)
reviews:
0
posted:
11/16/2008
language:
GALICIAN
pages:
0
PROJECT MONTHLY STATUS REPORT Project Title: Owner: Date (MM/DD/YYYY): Reporting Period: OMBA-123 implementation Mike Costello 9/25/2006 July 1, 2006 through September 15, 2006 Project Description: To comply with the 9/15/2006 deadline of Secretary of Energy signing of The assurance letter on the effectiveness and efficiency of the internal controls over financial reporting. 1. Executive Summary Overall Status: Green 1 Yellow 2 Red 3 Reason for Deviation (Controlled) Deliverable: Schedule: Scope: Budget: 1 2 3 (Caution) (Critical) [X] [X] [X] [X] [ ] [ ] [ ] [ ] [ ] [ ] [ ] [ ] Project is within established milestones, scope and on schedule. Project has deviated slightly from the plan. Project has fallen significantly behind schedule, is not tracking to established milestones, or has taken on tasks that are out of scope. Comments: Testing for all Entity control subcategories and process cycles was completed on 9/1/2006. The Remediation work was completed by 8/15/2006. All corrective action plans were finalized, approved, and signed off. Implementation project met the overall timelines, milestones, as well as any interim reporting to the Chicago site office. 2. Controls Issue Status (Significant issues impacting milestones, schedule or scope) 1. DOE guidelines on the detail steps required continued to be less than clear, this means that future review by any oversight agency may reveal additional required information. 2. Constantly evolving requirements from DOE Chicago prevent planning with a reasonable time horizon. Change Status (Changes raised for consideration that change the approved project baselines. Future review by oversight agency of the implementation process Page 1 of 4 1. Executive Summary Overall Status: Green 1 Yellow 2 Red 3 Reason for Deviation (Controlled) Deliverable: Schedule: Scope: Budget: 1 2 3 (Caution) (Critical) [X] [X] [X] [X] [ ] [ ] [ ] [ ] [ ] [ ] [ ] [ ] Project is within established milestones, scope and on schedule. Project has deviated slightly from the plan. Project has fallen significantly behind schedule, is not tracking to established milestones, or has taken on tasks that are out of scope. Comments: Testing for all Entity control subcategories and process cycles was completed on 9/1/2006. The Remediation work was completed by 8/15/2006. All corrective action plans were finalized, approved, and signed off. Implementation project met the overall timelines, milestones, as well as any interim reporting to the Chicago site office. Risk Status (Report on any major project risks) 1. The extensiveness and the depth of the project implementation may be impacted by the overall aggressive timelines. 2. The effort continues to concentrate within the office of the Controller (natural result of the aggressive timelines), therefore the scope of the OMBA-123 implementation, while sufficient, is likely to be less extensive. 3. Budget Report Expense Original Budget Spent to Date Variance Current Budget Current Forecast Estimate to Complete Labor    Hardware Software Other (Training) N/A N/A 9,000 160,987 4,000 156,987 External OCFO OCFO, Controller’s office 70,000 81,987 70,000 81,987 N/A N/A N/A Total Link: Comments: Page 2 of 4 4. Scheduled Milestones / Deliverables List all Major Project Milestones. Dates should tie to established baseline schedules in the Eroom. Milestone (last revised 7/17/2006) Final DOE Guidance Software Demo scheduled Project plan finalized and review with sr. mgmt Phase I Documentation Phase II Evaluation Test Plan to DOE Chicago 3 quarter report to DOE Chicago Phase III Testing Phase IV Remediation Finalize all OMBA-123 reporting and submission To DOE Chicago Monthly status report – assessment team Monthly status report to CFO Ad Hoc status report to the Steering Committee Ongoing Ongoing Ongoing Open Open Open rd Approved Schedule 11/15/2005 12/22/2005 Actual 1/17/2006 12/22/2005 1/20/2006 Current Forecast Status Complete Complete Complete Complete Complete Complete Complete Complete Complete Complete 2/17/2006 3/29/2006 3/30/2006 July 2006 8/1/2006 8/15/2006 9/15/2006 2/17/2006 3/29/2006 3/30/2006 7/7/2006 9/1/2006 8/15/2006 9/6/2006 5. Accomplishments / Plans Accomplishments during this Reporting Period (Should relate to milestones): 1. 2. 3. 4. Positive feedback from HQs and Chicago site office on LBNL submission of implementation data, Statement of material weaknesses to DOE Chicago in August 2006 (none reported). Successfully met the implementation Remediation, Testing, and Reporting milestones and timelines. Finalized, approved, and signed off on seven Corrective Action Plans and its CATS reporting. Plans during the next Reporting Period (Should relate to milestones): Lessons Learned and 2007 Implementation activities planning. Page 3 of 4 6. Project Monthly Status Report / Signatures Project participants: John Chernowski, Michele Mock, Ira Nishibayashi, Kimberly Martens, Grace Huang, Lauretta Corsair, Rosalyn Height, Sallie Frainier, Harry Lorsbach, and Jim Yoshihara, Rich Nosek, and Rose Katsu. Project Owner: Controller, Mike Costello I have reviewed the information contained in this Project Monthly Status Report and agree: Name Title Signature Date (MM/DD/YYYY) The signatures above indicate an understanding of the purpose and content of this document by those signing it. By signing this document, they agree to this as the formal Project Monthly Status Report document. Page 4 of 4

Related docs
Project Monthly Status Report Template
Views: 1197  |  Downloads: 158
Monthly Status Report Template
Views: 80  |  Downloads: 9
Monthly Status Report Template
Views: 174  |  Downloads: 13
Monthly Status Report Template
Views: 143  |  Downloads: 16
Monthly Status Report Template
Views: 56  |  Downloads: 11
Monthly Status Report Template II
Views: 1441  |  Downloads: 79
Project Monthly Status Report Template
Views: 1  |  Downloads: 1
Project Monthly Status Report Template
Views: 8  |  Downloads: 5
Project Management Monthly Status Report
Views: 20  |  Downloads: 2
Monthly Status Report Template
Views: 4  |  Downloads: 2
Monthly Status Report Template
Views: 5  |  Downloads: 2
Monthly Status Report Template
Views: 3  |  Downloads: 0
Monthly Status Report Template
Views: 0  |  Downloads: 0
Monthly Status Report Template
Views: 16  |  Downloads: 3
premium docs
Other docs by gigi12
H and R Block Inc Ammendments and Bylaws
Views: 140  |  Downloads: 1
You can t please everyone
Views: 235  |  Downloads: 3
Avon Products Inc Ammendments and By laws
Views: 201  |  Downloads: 1
Employee Discipline Form
Views: 5593  |  Downloads: 196
Driving record check
Views: 211  |  Downloads: 0
Minutes of Special Meeting of Shareholders
Views: 302  |  Downloads: 9
Business selection checklist
Views: 479  |  Downloads: 16
3dfx Interactive Ammendments and By laws
Views: 164  |  Downloads: 1
My first "Celebrity Blog"
Views: 348  |  Downloads: 0
A Series ofLessons in Raja
Views: 248  |  Downloads: 8
The Development Psychology of Psychopathology
Views: 562  |  Downloads: 19