Installation and Conversion Template, Rev. 0 (53000)

Shared by: gigi12
-
Stats
views:
17
posted:
11/16/2008
language:
pages:
25
Document Sample
scope of work template
							QUALITY
ASSURANCE
PLAN

Project or System Name


U.S. Small Business Administration


Month, Year
                                                                          Revision Sheet

Revision Sheet
 Release No.   Date       Revision Description
 Rev. 1        11/14/01   Quality Assurance Plan Template and Checklist




Quality Assurance Plan                                                            Page i
                   Quality Assurance Plan Authorization
                              Memorandum




I have carefully assessed the Quality Assurance Plan for the (System Name). This document has been
completed in accordance with the requirements of the SBA System Development Methodology.

MANAGEMENT CERTIFICATION - Please check the appropriate statement.


______ The document is accepted.


______ The document is accepted pending the changes noted.


______ The document is not accepted.


We fully accept the changes as needed improvements and authorize initiation of work to proceed. Based
on our authority and judgment, the continued operation of this system is authorized.

_______________________________                                       _____________________
NAME                                                                  DATE
Project Leader

_______________________________                                       _____________________
NAME                                                                  DATE
Program Area/Sponsor Representative

_______________________________                                       _____________________
NAME                                                                  DATE
Program Area/Sponsor Director




Quality Assurance Plan                                                                         Page ii
                                       QUALITY ASSURANCE PLAN

                                                     TABLE OF CONTENTS
                                                                                                                                                               Page #

1.0   GENERAL INFORMATION .......................................................................................................... 1-1
      1.1      Purpose ................................................................................................................................... 1-1
      1.2      Scope ...................................................................................................................................... 1-1
      1.3      System Overview ................................................................................................................... 1-1
      1.4      Project References .................................................................................................................. 1-1
      1.5      Terms and Abbreviations ....................................................................................................... 1-2
      1.6      Points of Contact .................................................................................................................... 1-2
               1.6.1       Information .............................................................................................................................1-2
               1.6.2       Coordination ...........................................................................................................................1-2
2.0   SCHEDULE OF TASKS AND RESPONSIBILITIES .................................................................... 2-1
3.0   SYSTEM DOCUMENTATION ...................................................................................................... 3-1
      3.1      Documents by Phase .............................................................................................................. 3-1
               3.1.1       Initiate Phase ...........................................................................................................................3-1
               3.1.2       Define Phase ...........................................................................................................................3-1
               3.1.3       Design Phase ...........................................................................................................................3-1
               3.1.4       Build Phase .............................................................................................................................3-2
               3.1.5       Evaluate Phase ........................................................................................................................3-2
               3.1.6       Operate Phase .........................................................................................................................3-2
      3.2      Discipline for Documentation Standard Practices ................................................................. 3-2
4.0   REVIEWS AND AUDITS ............................................................................................................... 4-1
      4.1      Review Process ...................................................................................................................... 4-1
      4.2      Formal Reviews and Audits ................................................................................................... 4-1
               4.2.1       Lifecycle Reviews ...................................................................................................................4-1
               4.2.2       Audits ......................................................................................................................................4-1
      4.3      Informal Reviews ................................................................................................................... 4-2
      4.4      Review Reports ...................................................................................................................... 4-2
      4.5      Review and Audit Metrics ..................................................................................................... 4-2
5.0   TESTING ......................................................................................................................................... 5-1
6.0   PROBLEM REPORTING AND CORRECTIVE ACTION ............................................................ 6-1
      6.1      Problem/Issue Documentation ............................................................................................... 6-1
      6.2      Report Metrics ........................................................................................................................ 6-1
7.0   TOOLS ............................................................................................................................................. 7-1
8.0   PROJECT CONTROLS ................................................................................................................... 8-1
      8.1      Product Control ...................................................................................................................... 8-1
      8.2      Supplier Control ..................................................................................................................... 8-1
9.0   TRAINING....................................................................................................................................... 9-1


Quality Assurance Plan                                                                                                                                         Page iii
                                                     1.0 General Information




                         1.0   GENERAL INFORMATION




Quality Assurance Plan
                                                                                  1.0 General Information

NOTE TO AUTHOR: Highlighted, italicized text throughout this template is provided solely as
background information to assist you in creating this document. Please delete all such text, as well as
the instructions in each section, prior to submitting this document. ONLY YOUR PROJECT-
SPECIFIC INFORMATION SHOULD APPEAR IN THE FINAL VERSION OF THIS
DOCUMENT.

This Quality Assurance Plan (QAP) presents a framework for activities, which when followed, will
ensure delivery of quality products and services. The SDM provides the project standards and
procedures to be used as the basis for the QA group's reviews and audits Please see Appendix B of the
SDM for further information of the use of this document and it alignment with the SBA Enterprise
Quality Assurance Plan.


1.0     GENERAL INFORMATION


1.1     Purpose

Describe the purpose of the Quality Assurance Plan.

1.2     Scope

Describe the scope of the Quality Assurance Plan as it relates to the project.

1.3     System Overview

Provide a brief system overview description as a point of reference for the remainder of the document. In
addition, include the following:

       Responsible organization
       System name or title
       System code
       System environment and special conditions

1.4     Project References

Provide a list of the references that were used in preparation of this document. Examples of references
are:

       Previously developed documents relating to the project
       Documentation concerning related projects
       SBA standard procedures documents
       Quality Assurance Guidelines


Quality Assurance Plan                                                                           Page 1-1
                                                                                      1.0 General Information

1.5     Terms and Abbreviations

Provide a list of the terms and abbreviations used in this document and the meaning of each.

1.6     Points of Contact


1.6.1 Information

Provide a list of the points of organizational contact (POCs) that may be needed by the document user for
informational and troubleshooting purposes. Include type of contact, contact name, department,
telephone number, and e-mail address (if applicable). Points of contact may include, but are not limited
to, helpdesk POC, development/maintenance POC, and operations POC.

1.6.2 Coordination

Provide a list of organizations that require coordination between the project and its specific support
function (e.g., installation coordination, security, etc.). Include a schedule for coordination activities.




Quality Assurance Plan                                                                                Page 1-2
                                           2.0 Schedule of Tasks and Responsibilities




            2.0     SCHEDULE OF TASKS AND RESPONSIBILITIES




Quality Assurance Plan
                                                              2.0 Schedule of Tasks and Responsibilities



2.0    SCHEDULE OF TASKS AND RESPONSIBILITIES

Based on the tasks described in your Project Plan, provide a schedule of the QA activities for the
duration of the project. Tasks may include, but are not limited to, those listed below. (Refer to the
Quality Assurance Guidelines in the SDM for a complete description of these tasks.) A waiver exempting
the project from any of these tasks is required.

      Identify Standards and Guidelines
      Evaluate Software Tools
      Evaluate Facilities
      Evaluate Software Products Review Process
      Evaluate Project Planning, Tracking, and Oversight Processes
      Evaluate Requirements Analysis Process
      Evaluate Design Process
      Evaluate Code and Unit Testing Process
      Evaluate Integration Testing Process
      Evaluate Acceptance Testing Process
      Evaluate Release Process
      Evaluate the Corrective Action Process
      Evaluate Media Certification Process
      Certify Non-deliverable Software
      Evaluate Storage and Handling Process
      Evaluate Deviations and Waivers Process
      Evaluate Configuration Management Process
      Evaluate Software Development Library Control Process
      Evaluate Non-developmental Software
      Perform Configuration Audits
      Evaluate Risk Management Process




Quality Assurance Plan                                                                         Page 2-1
                                                      3.0 System Documentation




                         3.0   SYSTEM DOCUMENTATION




Quality Assurance Plan
                                                                                3.0 System Documentation



3.0     SYSTEM DOCUMENTATION

This section describes all documentation that will be generated, by lifecycle phase, for the project. The
identified documentation listed will be that which control the development, verification and validation,
use and maintenance of the software.

3.1     Documents by Phase

List and briefly describe the documentation expected to be produced during this project. Depending on
the size of your project, this may include, but is not limited to, the documents in the following
subsections. (Note that some of the documents listed below are updated in subsequent phases.) The SBA
SDM Documentation Standards lists the objectives for producing standardized system documentation.
The QAP may include any other deliverables cited in the project Work Breakdown Structure (WBS).

3.1.1 Initiate Phase

       Needs Statement
       Project Plan (including WBS)
       Configuration Management Plan
       Quality Assurance Plan
       Feasibility Study
       Cost/Benefit Analysis
       Risk Analysis

3.1.2 Define Phase

       System Support and Acquisition Plan (initial)
       Functional Requirements Document
       Data Requirements Document
       System Security and Privacy Plan
       Internal Audit Plan
       Project Plan (updated)

3.1.3 Design Phase

       System/Subsystem Specifications
       Database Specifications
       Program Specifications


Quality Assurance Plan                                                                            Page 3-1
                                                                                3.0 System Documentation

       System Support and Acquisition Plan (final)
       Validation, Verification, and Testing Plan (initial)
       Training Plan (initial)
       Project Plan (updated)

3.1.4 Build Phase

       Installation and Conversion Plan (initial)
       Test Plan
       User’s Manual
       Operations Manual
       Maintenance Manual
       Validation, Verification, and Testing Plan (final)
       Training Plan (final)
       Project Plan (updated)

3.1.5 Evaluate Phase

       Test Results and Evaluation Reports
       Installation and Conversion Plan (final)
       Project Plan (updated)

3.1.6 Operate Phase

       Pilot Test Results
       Training Material

3.2     Discipline for Documentation Standard Practices

Describe the criteria that will be applied during review and evaluation of all lifecycle documents. If SBA
documentation standard templates are not used in the creation of project documents, describe the
alternative. A waiver exempting the project from standard template usage is required.




Quality Assurance Plan                                                                            Page 3-2
                                                    4.0 Reviews and Audits




                         4.0   REVIEWS AND AUDITS




Quality Assurance Plan
                                                                                   4.0 Reviews and Audits



4.0     REVIEWS AND AUDITS

This section discusses quality assurance’s role in the reviews and audits that will be conducted during
the lifecycle of the project to ensure the quality, consistency, comprehension, and completeness of the
project documentation and activities.

4.1     Review Process

Define the steps of the review process and the procedures that will be used to conduct reviews. Address
management and attendee responsibilities with respect to the review process.

4.2     Formal Reviews and Audits

This subsection addresses the formal, scheduled reviews and audits that will be conducted on the project.
Reviews are a monitoring mechanism to assess the progress and well being of the project.

4.2.1 Lifecycle Reviews

Identify the types of SDM associated lifecycle or non-lifecycle reviews that will be conducted within
each project lifecycle phase. Include a schedule of review and include how the results of each review
will be used on the project. Typically, the lifecycle reviews include:

       Requirements Review
       Design Review
       Specification Review
       Preliminary Design Review
       Critical Design Review
       Test Readiness Review
       Formal Qualification Review
       Production Readiness Review
       Acceptance Test Review
       Post-Implementation Review

4.2.2 Audits

Describe the audits that will be conducted on the project and when they will be scheduled. Audits are
independent examinations of a deliverable or a set of deliverables. Audits are accomplished by
comparing the actual characteristics of a deliverable with those required or specified.




Quality Assurance Plan                                                                           Page 4-1
                                                                                   4.0 Reviews and Audits

4.3     Informal Reviews

Outline the types of informal reviews that will be conducted. Types of reviews may include
walkthroughs, desk check codes, peer reviews, and quality control reviews.

4.4     Review Reports

Identify QA reports that will be produced throughout the project lifecycle and their uses. These reports
may include:

       Review issues list
       Review summary report
       Action tracking report

4.5     Review and Audit Metrics

Describe the metrics that will be used to capture management information, and how they will be analyzed
and reported.




Quality Assurance Plan                                                                           Page 4-2
                                         5.0 Testing




                         5.0   TESTING




Quality Assurance Plan
                                                                                                 5.0 Testing



5.0     TESTING

Identify the roles and responsibilities of the QA function in relation to testing throughout the various
stages of the project. These include but are not limited to:

       Unit testing
       System testing
       Integration testing
       Regression testing
       Acceptance testing




Quality Assurance Plan                                                                              Page 5-1
                                      6.0 Problem Reporting and Corrective Action




         6.0     PROBLEM REPORTING AND CORRECTIVE ACTION




Quality Assurance Plan
                                                             6.0 Problem Reporting and Corrective Action



6.0     PROBLEM REPORTING AND CORRECTIVE ACTION

Discuss QA responsibilities and activities concerned with the reporting and tracking of project-related
problems and resolutions.

6.1     Problem/Issue Documentation

Explain how problems and issues will be documented.

6.2     Report Metrics

Describe how metrics from the above reports will be collected and analyzed to determine and coordinate
corrective actions.




Quality Assurance Plan                                                                            Page 6-1
                                       7.0 Tools




                         7.0   TOOLS




Quality Assurance Plan
                                                                                                7.0 Tools



7.0     TOOLS

This section discusses QA responsibilities and activities concerned with the reporting and tracking of
project related problems and resolutions.

Describe the tools that will be used for QA and the methodology employed to implement usage of the
mentioned tools. The tools may include, but are not limited to:

       Operating system utilities
       Debugging aids
       Documentation tools
       Code and structure analyzers
       Monitors
       Statistical analysis packages
       Static or dynamic test tools




Quality Assurance Plan                                                                           Page 7-1
                                                  8.0 Project Controls




                         8.0   PROJECT CONTROLS




Quality Assurance Plan
                                                                                     8.0 Project Controls



8.0     PROJECT CONTROLS


8.1     Product Control

Identify how QA will monitor the methods and tools used to maintain and store controlled versions of
system products.

8.2     Supplier Control

Describe the provisions for assuring that products provided by suppliers meets established requirements.
In some cases, projects do not foresee purchasing certain products. If that is the case, the following
paragraph may be used:

All supplier products have been operationally tested in the target system. No future product acquisition
is planned.




Quality Assurance Plan                                                                           Page 8-1
                                          9.0 Training




                         9.0   TRAINING




Quality Assurance Plan
                                                                                                9.0 Training



9.0     TRAINING

Identify the training activities that will be provided to meet the needs of QA on this project. Suggested
training may include:

       Project orientation on roles, responsibilities, and quality assurance staff authority
       Software engineering skills and practices
       Project standards, procedures, and methods
       Understanding and using automated tools
       Interpersonal communications




Quality Assurance Plan                                                                              Page 9-1

						
Related docs
Other docs by gigi12
Email Template
Views: 11  |  Downloads: 0
Template Five-Year CIWMP Review Report
Views: 12  |  Downloads: 0
Instructions for use Template Research Protocol
Views: 32  |  Downloads: 0
Template Functions (pages 911-918)
Views: 0  |  Downloads: 0
PART IV. ADOPTION (Sample Template)
Views: 12  |  Downloads: 0
Qwest Service Order Template
Views: 26  |  Downloads: 0
SC Template Standards INJ
Views: 20  |  Downloads: 0
Working Bibliography Template
Views: 67  |  Downloads: 2