									                                                         The York Group - Sample Time Line for Partner Recruitment Project
  ID    Task Name                                        Duration         Month 1             Month 2                Month 3          Month 4          Month 5
                                                                     W-2 W-1 W1 W2    W3     W4 W5 W6      W7   W8    W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21
  1     Market Diag. & Channel Profile                    10 days
  2          Start market diagnostics                       0 days
  3          Market research                                5 days
  4          Kick-off meeting/partner profile               5 days
  5          Deliverable                                    0 days
  6     Partner Recruitment                              129 days
  7          Start partner recruitment                      0 days
  8          Plan                                            1 day
  9          Materials                                      2 days
  10         Build long-list                                5 days
  11         Identify decision-makers                       5 days
  12         Contact/Initial qualification                39 days
  13                Call decision-maker                    15 days
  14                Send material                          15 days
  15                Qualify candidates                     15 days
  16                Short list                             15 days
  17                Application form                       15 days
  18                Follow-up                              15 days
  19                References                             15 days
  20         Set up conference call                        10 days
  21         Conference call, requalify, follow-up          5 days

  22         Schedule face-to-face meeting                 30 days
  23         Meeting confirmed                              0 days
  24         Meeting follow-up                              2 days
  25         Letter of intent                              10 days
  26         Marketing plan                                10 days
  27         Formal contract                               20 days




                                             Task                                    Rolled Up Task                         External Tasks

                                             Progress                                Rolled Up Milestone                    Project Summary
Project: Recruitment project plan temp
Date: Mon 2/13/06
                                             Milestone                               Rolled Up Progress                     Group By Summary

                                             Summary                                 Split                                  Deadline

                                                                                             Page 1

								