MI RF – CR Items Schedule

Document Sample
MI RF – CR Items Schedule Powered By Docstoc
					                                                 MI RF – CR Items Schedule
WBS             Description                                              Duration         Start       Finish        M&S                   Personnel
1.3.4.7         MI RF APS Rectifier Transformer Upgrade                                                             $110,000
                                                                                                                               Reid, Jach, Wolff, Berenc, Meyer, RF
1.3.4.7.1       Acquire New Spare Transformer                                             8/28/2006    11/21/2007
                                                                                                                                              Techs
1.3.4.7.2       Center APS Transformer Replacement                                       10/16/2006   Shutdown



WBS             Description                                              Duration         Start       Finish        M&S                   Personnel
1.3.4.8         MI RF SSD Power Supply Upgrade                                            9/11/2006     6/18/2007   $206,000 Berenc, Zifko, MI RF Techs
1.3.4.8.1       Purchase Supply for Evaluation                           0 days           9/11/2006     9/11/2006    $10,000
                                                                                                                             AD RF Tech 50%
1.3.4.8.2       Test Evaluation Supply                                   1 week           11/6/2006    11/13/2006            AD RF EE 50%
1.3.4.8.3       Fermi SSD PS Control Card Production
1.3.4.8.4       Purchase SSD Power Supplies                                          0   11/14/2006    11/14/2006   $190,000
1.3.4.8.5       Receive SSD Power Supplies                                                 3/6/2006      3/6/2006
1.3.4.8.6       Install/Test Fermi Control Cards                         2 weeks          3/12/2006     3/26/2006              AD RF Tech 75%
1.3.4.8.7       Install SSD Power Supplies                               2 weeks         Shutdown       6/18/2007              AD RF Tech 100%



WBS             Description                                              Duration         Start       Finish        M&S                   Personnel
                                                                                                                             Tim Berenc, Steve Kotz, Rick Zifko,
1.3.4.6.2       MI RF Cavity Tuning Controller Upgrade                                                              $261,000 LLRF Personnel
1.3.4.6.2.1     Design and Develop Prototype                             8 months         8/28/2006     2/26/2007     $5,000
1.3.4.6.2.1.1   Characterize/model existing controller at Test Station   1.5 month        8/28/2006     10/9/2006            AD RF EE 175%
1.3.4.6.2.1.2   Design/model new control algorithm                       1 month          10/9/2006     11/6/2006            AD RF EE 175%
1.3.4.6.2.1.3   Hardware Selection/Decision Process                      2 weeks          11/7/2006    11/21/2006            AD RF EE 100%
1.3.4.6.2.1.4   Develop/Test Prototype at Test Station                   2 months        11/22/2006     1/17/2006            AD RF EE 300%, AD RF Tech 100%
1.3.4.6.2.1.5   Test Protoype in Operational Station                     2 weeks          2/12/2007     2/26/2007            AD RF EE 200%, AD RF Tech 100%
                                                                                                                             AD RF EE 200%, AD RF Tech 100%,
1.3.4.6.2.1.6   Finalize Design                                          2 months         2/27/2007     4/24/2007            AD Comp. Prof. 100%
                                                                                                                             AD RF EE 75%, AD RF Tech 200%
1.3.4.6.2.2     Mass Produce Final Design                                3 months         4/25/2007     7/25/2007   $256,000 AD Comp. Prof. 50%
                                                                                                                             AD RF EE 100%, AD RF Tech 100%,
1.3.4.6.2.3     Install/Test                                             2 months         7/26/2007     9/19/2007            AD Comp Prof. 50%
1.3.4.6.2.4     Commission with Beam                                     1 month          9/20/2007    10/25/2007            AD RF EE 100%




   Proton Plan PMG 9/28/06                                                                                                     T.Berenc                      1
                                      Concerns
•    Beam Loading Compensation Strategy for Proton Plan
       Limit Cavity De-Tuning
          • New Controller = new design = risk
       Use Mode 1 Longitudinal Damper as necessary
          • Not currently operational on present Slip-Stacking cycles

•    RF Resource Competition for Proton Plan
       Operations
       Booster SSD Upgrade
       ILC/SCRF: Meson, A0, etc.
       SNuMI: Phase I and Phase II

•    Aggressive Schedule
       Ideally - Need experienced personnel
       Practically – also training new personnel



    Proton Plan PMG 9/28/06                                T.Berenc     2

				