					                                                                        SUMMARY OF CONCRETE POURING & CUBE TEST RESULT

                                                                          EPCC FOR SEGAMAT COMPRESSOR STATION EXPANSION PROJECT
      SE-TMSB CONSORTIUM
                                                                                                                                                                  TEST DATE / AVE. STRENGTH (N/mm2)
                                                                                                                                  3 DAYS                             7 DAYS                         14 DAYS                            28 DAYS
BATCH /    PRE CONC.                                                  SUPPLIER               DESIGN    QTY    SLUMP
                        LOCATION / AREA                 DESCRIPTION              DATE CAST                                                                                                                                                                             REMARKS
DO NO.      RFI NO.                                                     NAME                 (N/mm2)   (M3)    (mm)                AVG.    CUBE TEST                  AVG.   CUBE TEST                 AVG.   CUBE TEST                 AVG.     CUBE TEST
                                                                                                                      DATE TEST                      DATE TEST                         DATE TEST                        DATE TEST
                                                                                                                                  N/mm2     RFI NO.                  N/mm2    RFI NO.                 N/mm2    RFI NO.                 N/mm2      RFI NO.

SG 32378    CIV/104A      GC/PFS/FWT      PILE PLUG                   HANSON      2-Nov-06    G30N     2.0     80.0    5-Nov-06     X          X      9-Nov-06       27.10     CIV/127    16-Nov-06   29.32    CIV/143     30-Nov-06    39.33     CIV/148

SG 32377    CIV/106A       GC & PVS       LEAN CONCRETE               HANSON      2-Nov-06    G20N     5.0     80.0    5-Nov-06     X          X      9-Nov-06       20.22     CIV/126    16-Nov-06   22.88    CIV/135     30-Nov-06    28.44     CIV/149

SG 32498    CIV/116        GC & PVS       PILE CAP                    HANSON      9-Nov-06    G40N     12.0    85.0   12-Nov-06     X          X     16-Nov-06       34.36     CIV/136    23-Nov-06   47.10    CIV/144     7-Dec-06     53.32     CIV/156

SG 32500    CIV/117        GC & PVS       PILE CAP                    HANSON     10-Nov-06    G40N     14.0   100.0   13-Nov-06     X          X     17-Nov-06       34.36     CIV/139    24-Nov-06   45.03    CIV/145     8-Dec-06     53.62     CIV/157

SG 32606    CIV/159    COMP. BLDG TURBINE LEAN CONCRETE               HANSON     18-Nov-06    G20N     5.0     80.0   21-Nov-06     X          X     25-Nov-06       17.17   CIV/171(B)   2-Dec-06    22.90   CIV/175(A)   16-Dec-06    27.10     CIV/186

SG 32694    CIV/169           GC          LEAN CONCRETE               HANSON     23-Nov-06    G20N     3.0     80.0   26-Nov-06     X          X     30-Nov-06       17.32   CIV/171(C)   7-Dec-06    22.66    CIV/189     21-Dec-06    29.32     CIV/190

SG 32642    CIV/170       COMP. BLDG      LEAN CONCRETE               HANSON     24-Nov-06    G20N     5.0     80.0   27-Nov-06     X          X      1-Dec-06       17.99   CIV/171(A)   8-Dec-06    23.33    CIV/184     22-Dec-06    31.10     CIV/185

SG 32647    CIV/171       COMP. BLDG      PILE PLUG                   HANSON     24-Nov-06    G30N     1.0     80.0   27-Nov-06     X          X      1-Dec-06         X         X        8-Dec-06      X         X        22-Dec-06      X          X

SG 32707    CIV/173       COMP. BLDG      LEAN CONCRETE               HANSON     29-Nov-06    G20N     5.0     90.0    2-Dec-06     X          X      6-Dec-06       17.32     CIV/175    13-Dec-06   22.99    CIV/187     27-Dec-06    29.55     CIV/188

SG 32768    CIV/179       COMP. BLDG      PILE PLUG                   HANSON      5-Dec-06   G40SM     0.5     90.0    8-Dec-06     X          X     12-Dec-06         X         X        19-Dec-06     X         X        2-Jan-07       X          X

SG 32768    CIV/180           PVS         PILE CAP                    HASNON      5-Dec-06   G40SM     4.5     90.0    8-Dec-06     X          X     12-Dec-06       39.33     CIV/181    19-Dec-06   49.10    CIV/182     2-Jan-07     55.77     CIV/183

SG 32774    CIV/180           PVS         PILE CAP                    HANSON      5-Dec-06   G40SM     2.5     90.0    8-Dec-06     X          X     12-Dec-06         X         X        19-Dec-06     X         X        2-Jan-07       X          X

SG 32909    CIV/192          FWT          LEAN CONCRETE               HANSON     13-Dec-06   G20SM     6.0     80.0   16-Dec-06     X          X     20-Dec-06       25.99     CIV/198    27-Dec-06   32.88    CIV/199     10-Jan-07    39.99     CIV/200

SG 32914    CIV/193       COMP. BLDG      PILE CAP                    HANSON     13-Dec-06   G40SM     18.0    75.0   16-Dec-06     X          X     20-Dec-06       39.11     CIV/195    27-Dec-06   48.21    CIV/196     10-Jan-07    55.10     CIV/197

SG 32919    CIV/194       COMP. BLDG      PILE CAP                    HANSON     14-Dec-06   G40SM     17.0    90.0   17-Dec-06     X          X     21-Dec-06       33.33     CIV/201    28-Dec-06   44.44    CIV/202     11-Jan-07    50.88     CIV/203

SG 32945    CIV/209       COMP. BLDG      PILE CAP                    HANSON     27-Dec-06   G40SM     6.0    100.0   30-Dec-06     X          X      3-Jan-07       33.32     CIV/212    10-Jan-07   43.77    CIV/213     24-Jan-07    57.22     CIV/214

SG 32950    CIV/211       COMP. BLDG      PILE CAP                    HANSON     28-Dec-06   G40SM     5.0     90.0   31-Dec-06     X          X      4-Jan-07       30.22     CIV/217    11-Jan-07   41.77    CIV/219     25-Jan-07    48.66     CIV/221

SG 32952    CIV/211       COMP. BLDG      PILE CAP                    HANSON     28-Dec-06   G40SM     5.0     80.0   31-Dec-06     X          X      4-Jan-07         X         X        11-Jan-07     X         X        25-Jan-07      X          X

SG 32953    CIV/211       COMP. BLDG      PILE CAP                    HANSON     28-Dec-06   G40SM     5.0     75.0   31-Dec-06     X          X      4-Jan-07         X         X        11-Jan-07     X         X        25-Jan-07      X          X

SG 32954    CIV/211       COMP. BLDG      PILE CAP                    HANSON     28-Dec-06   G40SM     5.0     80.0   31-Dec-06     X          X      4-Jan-07         X         X        11-Jan-07     X         X        25-Jan-07      X          X

SG 32955    CIV/211       COMP. BLDG      PILE CAP                    HANSON     28-Dec-06   G40SM     5.0     75.0   31-Dec-06     X          X      4-Jan-07         X         X        11-Jan-07     X         X        25-Jan-07      X          X

SG 32956    CIV/211       COMP. BLDG      PILE CAP                    HANSON     28-Dec-06   G40SM     6.0     80.0   31-Dec-06     X          X      4-Jan-07       30.88     CIV/218    11-Jan-07   42.66    CIV/220     25-Jan-07    46.27     CIV/222

SG 32957    CIV/211       COMP. BLDG      PILE CAP                    HANSON     28-Dec-06   G40SM     6.0     75.0   31-Dec-06     X          X      4-Jan-07         X         X        11-Jan-07     X         X        25-Jan-07      X          X

SG 32958    CIV/211       COMP. BLDG      PILE CAP                    HANSON     28-Dec-06   G40SM     2.0     80.0   31-Dec-06     X          X      4-Jan-07         X         X        11-Jan-07     X         X        25-Jan-07      X          X

SG 33022    CIV/223       GAS COOLER      GROUND BEAM                 HANSON      4-Jan-07   G40SM     5.0     85.0    7-Jan-07     X          X      11-Jan-07      35.10     CIV/224    18-Jan-07   45.10    CIV/225     1-Feb-07     55.10     CIV/226

SG 33023    CIV/223       GAS COOLER      GROUND BEAM                 HANSON      4-Jan-07   G40SM     5.0     80.0    7-Jan-07     X          X      11-Jan-07        X         X        18-Jan-07     X         X        1-Feb-07       X          X

SG 33024    CIV/223       GAS COOLER      GROUND BEAM                 HANSON      4-Jan-07   G40SM     5.0     75.0    7-Jan-07     X          X      11-Jan-07        X         X        18-Jan-07     X         X        1-Feb-07       X          X

SG 33025    CIV/223       GAS COOLER      GROUND BEAM                 HANSON      4-Jan-07   G40SM     4.0     90.0    7-Jan-07     X          X      11-Jan-07        X         X        18-Jan-07     X         X        1-Feb-07       X          X

SG 33026    CIV/227       COMP. BLDG      PILE CAP -A/2, A/3 & E/4    HANSON      5-Jan-07   G40SM     5.0     80.0    8-Jan-07     X          X      12-Jan-07      35.33     CIV/229    19-Jan-07   39.77    CIV/230     2-Feb-07     50.44     CIV/231

SG 33027    CIV/227       COMP. BLDG      PILE CAP -A/2, A/3 & E/4    HANSON      5-Jan-07   G40SM     5.0     80.0    8-Jan-07     X          X      12-Jan-07        X         X        19-Jan-07     X         X        2-Feb-07       X          X

SG 33028    CIV/227       COMP. BLDG      PILE CAP -A/2, A/3 & E/4    HANSON      5-Jan-07   G40SM     5.0    100.0    8-Jan-07     X          X      12-Jan-07        X         X        19-Jan-07     X         X        2-Feb-07       X          X

SG 33029    CIV/227       COMP. BLDG      PILE CAP -A/2, A/3 & E/4    HANSON      5-Jan-07   G40SM     4.0     75.0    8-Jan-07     X          X      12-Jan-07        X         X        19-Jan-07     X         X        2-Feb-07       X          X

SG 33037    CIV/232       COMP. BLDG      LEAN CONCRETE (G BEAM)      HANSON      6-Jan-07   G20SM     2.0     75.0    9-Jan-07     X          X      13-Jan-07      30.66     CIV/233    20-Jan-07   37.77    CIV/234     3-Feb-07     39.33     CIV/235

SG 33041    CIV/236           PVS         STUMP                       HANSON      8-Jan-07   G40SM     4.0     80.0   11-Jan-07     X          X      15-Jan-07      33.32     CIV/239    22-Jan-07   38.66    CIV/240     5-Feb-07     49.11     CIV/241

SG 33042    CIV/236           PVS         STUMP                       HANSON      8-Jan-07   G40SM     3.0     80.0   11-Jan-07     X          X      15-Jan-07        X         X        22-Jan-07     X         X        5-Feb-07       X          X




 CONTRACTOR:SETMSB                                                                                                                                                                                                                      13bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                                                                                  SUMMARY OF CONCRETE POURING & CUBE TEST RESULT

                                                                                    EPCC FOR SEGAMAT COMPRESSOR STATION EXPANSION PROJECT
      SE-TMSB CONSORTIUM
                                                                                                                                                                            TEST DATE / AVE. STRENGTH (N/mm2)
                                                                                                                                            3 DAYS                             7 DAYS                         14 DAYS                          28 DAYS
BATCH /    PRE CONC.                                                            SUPPLIER               DESIGN    QTY    SLUMP
                        LOCATION / AREA                  DESCRIPTION                       DATE CAST                                                                                                                                                                           REMARKS
DO NO.      RFI NO.                                                               NAME                 (N/mm2)   (M3)    (mm)                AVG.    CUBE TEST                  AVG.   CUBE TEST                AVG.    CUBE TEST               AVG.     CUBE TEST
                                                                                                                                DATE TEST                      DATE TEST                         DATE TEST                        DATE TEST
                                                                                                                                            N/mm2     RFI NO.                  N/mm2    RFI NO.                N/mm2     RFI NO.               N/mm2      RFI NO.

SG 33093    CIV/242       COMP. BLDG       TURBINE FOUNDATION                   HANSON     12-Jan-07    G40P     6.0    120.0   15-Jan-07     X          X      19-Jan-07      29.77     CIV/247   26-Jan-07   46.44     CIV/248   9-Feb-07     49.55     CIV/249

SG 33101    CIV/242       COMP. BLDG       TURBINE FOUNDATION                   HANSON     12-Jan-07    G40P     6.0    120.0   15-Jan-07     X          X      19-Jan-07      30.66     CIV/247   26-Jan-07   46.99     CIV/248   9-Feb-07     54.21     CIV/249

SG 33107    CIV/242       COMP. BLDG       TURBINE FOUNDATION                   HANSON     12-Jan-07    G40P     6.0    120.0   15-Jan-07     X          X      19-Jan-07      31.77     CIV/247   26-Jan-07   47.10     CIV/248   9-Feb-07     52.88     CIV/249

SG 33112    CIV/242       COMP. BLDG       TURBINE FOUNDATION                   HANSON     12-Jan-07    G40P     6.0    100.0   15-Jan-07     X          X      19-Jan-07      31.33     CIV/247   26-Jan-07   45.55     CIV/248   9-Feb-07     52.44     CIV/249

SG 33118    CIV/242       COMP. BLDG       TURBINE FOUNDATION                   HANSON     12-Jan-07    G40P     6.0    120.0   15-Jan-07     X          X      19-Jan-07      32.22     CIV/247   26-Jan-07   45.22     CIV/248   9-Feb-07     52.88     CIV/249

SG 33125    CIV/243            PVS         STUMP                                HANSON     12-Jan-07    G40P     2.0    110.0   15-Jan-07     X          X      19-Jan-07      31.33     CIV/244   26-Jan-07   46.66     CIV/245   9-Feb-07     53.99     CIV/246

SG 33126    CIV/243            PVS         STUMP                                HANSON     12-Jan-07    G 40P    6.0    110.0   15-Jan-07     X          X      19-Jan-07        X         X       26-Jan-07     X          X      9-Feb-07       X          X

SG 33148    CIV/251            PVS         STUMP                                HANSON     17-Jan-07   G40SM     5.0     80.0   20-Jan-07     X          X      24-Jan-07      31.10     CIV/253   31-Jan-07   37.33     CIV/254   14-Feb-07    45.10     CIV/255

SG 33150    CIV/251            PVS         STUMP                                HANSON     17-Jan-07   G40SM     5.0     80.0   20-Jan-07     X          X      24-Jan-07        X         X       31-Jan-07     X          X      14-Feb-07      X          X

SG 33192    CIV/252       COMP. BLDG       GROUND BEAM                          HANSON     23-Jan-07   G40SM     6.0     90.0   26-Jan-07     X          X      30-Jan-07      30.44     CIV/256   6-Feb-07    39.10     CIV/257   20-Feb-07    51.10     CIV/258

SG 33196    CIV/252       COMP. BLDG       GROUND BEAM                          HANSON     23-Jan-07   G40SM     5.0     80.0   26-Jan-07     X          X      30-Jan-07        X         X       6-Feb-07      X          X      20-Feb-07      X          X

SG 33202    CIV/252       COMP. BLDG       GROUND BEAM                          HANSON     23-Jan-07   G40SM     5.0     80.0   26-Jan-07     X          X      30-Jan-07        X         X       6-Feb-07      X          X      20-Feb-07      X          X

SG 33222    CIV/260     PVS&COMP BLDG      GROUND BEAM                          HANSON     24-Jan-07   G40SM     5.0     80.0   27-Jan-07     X          X      31-Jan-07      31.33     CIV/261   7-Feb-07    35.10     CIV/262   21-Feb-07    49.99     CIV/263

SG 33224    CIV/260     PVS&COMP BLDG      PILE CAP                             HANSON     24-Jan-07   G40SM     3.0    100.0   27-Jan-07     X          X      31-Jan-07        X         X       7-Feb-07      X          X      21-Feb-07      X          X
                                           GRND. BEAM AT AIR INTAKE & EXHAUST
SG 33243    CIV/264       COMP. BLDG                                            HANSON     26-Jan-07   G40SM     6.0     80.0   29-Jan-07     X          X      2-Feb-07       30.44     CIV/265   9-Feb-07    38.66     CIV/266   23-Feb-07    51.99     CIV/267
                                           DUCK
                        PIPE RACK & COM.
SG 33339    CIV/269                        LEAN CONC. FOR FOOTING & TRENCH      HANSON      2-Feb-07   G20SM     6.0     80.0    5-Feb-07     X          X      9-Feb-07       21.99     CIV/275   16-Feb-07   26.20     CIV/276   2-Mar-07     35.55     CIV/277
                          BUILD. UNIT 3

SG 33343    CIV/269          CIV/269       LEAN CONC. FOR FOOTING & TRENCH      HANSON      2-Feb-07   G20SM     3.0     80.0    5-Feb-07     X          X      9-Feb-07         X         X       16-Feb-07     X          X      2-Mar-07       X          X

SG 33536    CIV/278       SOC substation   Trenches & plinth                    HANSON     12-Feb-07    G40N     4.5     70.0   15-Feb-07    22.33    CIV/282   19-Feb-07      31.55     CIV/283   26-Feb-07   37.32     CIV/284   12-Mar-07    51.33     CIV/285

SG33621     CIV/286         PIPERACK       FOOTING (15 NOS)                     HANSON     21-Feb-07   G40SM     6.0     80.0   24-Feb-07     X          X      28-Feb-07        X         X       7-Mar-07      X          X      21-Mar-07      X          X
                                           AIR INTAKE STUMP & EXHAUST STACK
SG33619     CIV/287       COMP. BLDG                                            HANSON     21-Feb-07   G40SM     6.0     75.0   24-Feb-07     X          X      28-Feb-07      34.44     CIV/299   7-Mar-07    38.21     CIV/300   21-Mar-07    60.88     CIV/301
                                           GRD BEAM
SG 33620    CIV/288            PVS         UPPER BEAM                           HANSON     21-Feb-07   G40SM     6.0     90.0   24-Feb-07     X          X      28-Feb-07        X         X       7-Mar-07      X          X      21-Mar-07      X          X
                       FILTER SEPARATOR @
SG 33630    CIV/289                       FOUNDATION                            HANSON     22-Feb-07   G40SM     6.0     80.0   25-Feb-07     X          X      1-Mar-07       35.10     CIV/298   8-Mar-07    38.21     CIV/313   22-Mar-07    52.22     CIV/314
                                RO
                       FILTER SEPARATOR @
SG 33635    CIV/289                       FOUNDATION                            HANSON     22-Feb-07   G40SM     6.0    100.0   25-Feb-07     X          X      1-Mar-07         X         X       8-Mar-07      X          X      22-Mar-07      X          X
                                RO
SG 33641    CIV/289        PVS @ RO        FOUNDATION                           HANSON     22-Feb-07   G40SM     3.0     90.0   25-Feb-07     X          X      1-Mar-07         X         X       8-Mar-07      X          X      22-Mar-07      X          X

SG 33667    CIV/293       COMP. BLDG       TRENCH SLAB A, B, C & D              HANSON     26-Feb-07   G40SM     6.0     90.0    1-Mar-07     X          X      5-Mar-07       32.88     CIV/305   12-Mar-07   39.33     CIV/315   26-Mar-07    52.66     CIV/316

SG 33669    CIV/293       COMP. BLDG       TRENCH SLAB A, B, C & D              HANSON     26-Feb-07   G40SM     6.0     80.0    1-Mar-07     X          X      5-Mar-07         X         X       12-Mar-07     X          X      26-Mar-07      X          X

SG 33672    CIV/293       COMP. BLDG       TRENCH SLAB A, B, C & D              HANSON     26-Feb-07   G40SM     6.0     90.0    1-Mar-07     X          X      5-Mar-07         X         X       12-Mar-07     X          X      26-Mar-07      X          X

SG 33674    CIV/293       COMP. BLDG       TRENCH SLAB A, B, C & D              HANSON     26-Feb-07   G40SM     6.0     90.0    1-Mar-07     X          X      5-Mar-07         X         X       12-Mar-07     X          X      26-Mar-07      X          X

SG 33676    CIV/293       COMP. BLDG       TRENCH SLAB A, B, C & D              HANSON     26-Feb-07   G40SM     6.0     90.0    1-Mar-07     X          X      5-Mar-07         X         X       12-Mar-07     X          X      26-Mar-07      X          X

                       FILTER SEPARATOR &
SG 33718    CIV/296                       STUMP                                 HANSON      1-Mar-07   G40SM     4.0     75.0    4-Mar-07    27.33    CIV/306   8-Mar-07       35.99     CIV/310   15-Mar-07   46.44     CIV/311   29-Mar-07    54.22     CIV/312
                          PVS NO 1 @ RO

                       FILTER SEPARATOR &
SG 33719    CIV/296                       STUMP                                 HANSON      1-Mar-07   G40SM     4.0     75.0    4-Mar-07     X          X      8-Mar-07         X         X       15-Mar-07     X          X      29-Mar-07      X          X
                          PVS NO 1 @ RO

SG 33750    CIV/304        COMP.BLDG       WALL TRENCH A, B, C & D              HANSON      6-Mar-07   G40SM     6.0     75.0    9-Mar-07     X          X      13-Mar-07      32.21     CIV/322   20-Mar-07   43.77     CIV/323   3-Apr-07     50.44     CIV/324

SG 33756    CIV/304        COMP.BLDG       WALL TRENCH A, B, C & D              HANSON      6-Mar-07   G40SM     5.0     75.0    9-Mar-07     X          X      13-Mar-07        X         X       20-Mar-07     X          X      3-Apr-07       X          X

SG 33759    CIV/304        COMP.BLDG       WALL TRENCH A, B, C & D              HANSON      6-Mar-07   G40SM     5.0     90.0    9-Mar-07     X          X      13-Mar-07        X         X       20-Mar-07     X          X      3-Apr-07       X          X

SG 33762    CIV/304        COMP.BLDG       WALL TRENCH A, B, C & D              HANSON      6-Mar-07   G40SM     4.0     80.0    9-Mar-07     X          X      13-Mar-07        X         X       20-Mar-07     X          X      3-Apr-07       X          X




 CONTRACTOR:SETMSB                                                                                                                                                                                                                              23bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                                                                           SUMMARY OF CONCRETE POURING & CUBE TEST RESULT

                                                                             EPCC FOR SEGAMAT COMPRESSOR STATION EXPANSION PROJECT
      SE-TMSB CONSORTIUM
                                                                                                                                                                    TEST DATE / AVE. STRENGTH (N/mm2)
                                                                                                                                     3 DAYS                            7 DAYS                         14 DAYS                          28 DAYS
BATCH /    PRE CONC.                                                     SUPPLIER               DESIGN    QTY    SLUMP
                         LOCATION / AREA                 DESCRIPTION                DATE CAST                                                                                                                                                                          REMARKS
DO NO.      RFI NO.                                                        NAME                 (N/mm2)   (M3)    (mm)                AVG.    CUBE TEST                 AVG.   CUBE TEST                AVG.    CUBE TEST               AVG.     CUBE TEST
                                                                                                                         DATE TEST                      DATE TEST                        DATE TEST                        DATE TEST
                                                                                                                                     N/mm2     RFI NO.                 N/mm2    RFI NO.                N/mm2     RFI NO.               N/mm2      RFI NO.

SG 33787    CIV/308         PIPERACK       STUMP (15 NOS)                HANSON     10-Mar-07   G40SM     1.5     90.0   13-Mar-07     X          X     17-Mar-07      30.44     CIV/331   24-Mar-07   38.66     CIV/332   7-Apr-07     44.71     CIV/333

SG 33783    CIV/318       GAS COOLER       STUMP (21 NOS)                HANSON     10-Mar-07   G40SM     4.0     80.0   13-Mar-07     X          X     17-Mar-07      32.10     CIV/328   24-Mar-07   39.33     CIV/329   7-Apr-07     50.66     CIV/330

SG 33787    CIV/318        PVS PS-617      STUMP (1 NOS)                 HANSON     10-Mar-07   G40SM     0.5     90.0   13-Mar-07     X          X     17-Mar-07      30.44     CIV/331   24-Mar-07   38.66     CIV/332   7-Apr-07     44.71     CIV/333
                       BUFFER AIR & PVS NO.
SG 33778    CIV/319                         FOUNDATION                   HANSON      9-Mar-07   G40SM     6.0     80.0   12-Mar-07     X          X     16-Mar-07      31.33     CIV/325   23-Mar-07   38.66     CIV/326   6-Apr-07     50.88     CIV/327
                                2
                       BUFFER AIR & PVS NO.
SG 33780    CIV/319                         FOUNDATION                   HANSON      9-Mar-07   G40SM     6.0     75.0   12-Mar-07     X          X     16-Mar-07        X         X       23-Mar-07     X          X      6-Apr-07       X          X
                                2
                       BUFFER AIR & PVS NO.
SG 33781    CIV/319                         FOUNDATION                   HANSON      9-Mar-07   G40SM     3.0     80.0   12-Mar-07     X          X     16-Mar-07        X         X       23-Mar-07     X          X      6-Apr-07       X          X
                                2
SG 33783    CIV/320      EXHAUST STACK     STUMP (4 NOS)                 HANSON     10-Mar-07   G40SM     1.5     80.0   13-Mar-07     X          X     17-Mar-07      32.10     CIV/328   24-Mar-07   39.33     CIV/329   7-Apr-07     50.66     CIV/330    RFI FROM MECHANICAL -MEC/015

SG 33786    CIV/321        BUFFER AIR      STUMP ( 2 NOS)                HANSON     10-Mar-07   G40SM     3.5    100.0   13-Mar-07     X          X     17-Mar-07      30.44     CIV/331   24-Mar-07   38.66     CIV/332   7-Apr-07     44.71     CIV/333

SG 33851    CIV/335        COMP.BLDG       LEAN CONCRETE GROUND SLAB     HANSON     16-Mar-07   G20SM     6.0     90.0   19-Mar-07     X          X     23-Mar-07      23.55     CIV/343   30-Mar-07   29.55     CIV/350   13-Apr-07    35.99     CIV/361

SG 33852    CIV/335        COMP.BLDG       LEAN CONCRETE GROUND SLAB     HANSON     16-Mar-07   G20SM     6.0     90.0   19-Mar-07     X          X     23-Mar-07        X         X       30-Mar-07     X          X      13-Apr-07      X          X

SG 33853    CIV/335        COMP.BLDG       LEAN CONCRETE GROUND SLAB     HANSON     16-Mar-07   G20SM     6.0    100.0   19-Mar-07     X          X     23-Mar-07        X         X       30-Mar-07     X          X      13-Apr-07      X          X

SG 33869    CIV/337         PIPERACK       FOOTING-3nos, TIE BEAM-6nos   HANSON     17-Mar-07   G40SM     3.8     80.0   20-Mar-07     X          X     24-Mar-07      31.66     CIV/344   31-Mar-07   36.44     CIV/351   14-Apr-07    48.44     CIV/363

SG 33869    CIV/338    FUEL GAS SEPARATOR FOOTING                        HANSON     17-Mar-07   G40SM     1.2     80.0   20-Mar-07     X          X     24-Mar-07      31.66     CIV/344   31-Mar-07   36.44     CIV/351   14-Apr-07    48.44     CIV/363

SG 33924    CIV/341         PIPERACK       STUMP-3NOS, TIE BEAM-3NOS     HANSON     22-Mar-07   G40SM     1.2     80.0   25-Mar-07     X          X     29-Mar-07      30.88     CIV/348   5-Apr-07    39.33     CIV/355   19-Apr-07    46.88     CIV/366

SG 33924    CIV/342    FUEL GAS SEPARATOR STUMP                          HANSON     22-Mar-07   G40SM     0.8     80.0   25-Mar-07     X          X     29-Mar-07      30.88     CIV/348   5-Apr-07    39.33     CIV/355   19-Apr-07    46.88     CIV/367

SG 33939    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     75.0   29-Mar-07     X          X      2-Apr-07      30.22     CIV/352   9-Apr-07    43.55     CIV/358   23-Apr-07    50.44     CIV/368        CONC SUPPLY BY SIME

SG 33940    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     80.0   29-Mar-07     X          X      2-Apr-07        X         X       9-Apr-07      X          X      23-Apr-07      X          X       TOTAL: 75 m3 4 GROUND SLAB A

SG 33941    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     80.0   29-Mar-07     X          X      2-Apr-07        X         X       9-Apr-07      X          X      23-Apr-07      X          X

SG 33942    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     80.0   29-Mar-07     X          X      2-Apr-07        X         X       9-Apr-07      X          X      23-Apr-07      X          X

SG 33943    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     80.0   29-Mar-07     X          X      2-Apr-07        X         X       9-Apr-07      X          X      23-Apr-07      X          X

SG 33944    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     90.0   29-Mar-07     X          X      2-Apr-07      29.99     CIV/352   9-Apr-07    47.10     CIV/358   23-Apr-07    52.66     CIV/370

SG 33945    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     80.0   29-Mar-07     X          X      2-Apr-07        X         X       9-Apr-07      X          X      23-Apr-07      X          X

SG 33946    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     80.0   29-Mar-07     X          X      2-Apr-07        X         X       9-Apr-07      X          X      23-Apr-07      X          X

SG 33947    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     75.0   29-Mar-07     X          X      2-Apr-07        X         X       9-Apr-07      X          X      23-Apr-07      X          X

SG 33948    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     80.0   29-Mar-07     X          X      2-Apr-07        X         X       9-Apr-07      X          X      23-Apr-07      X          X

SG 33949    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     80.0   29-Mar-07     X          X      2-Apr-07      29.99     CIV/352   9-Apr-07    45.77     CIV/358   23-Apr-07    49.55     CIV/371

SG 33950    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     6.0     85.0   29-Mar-07     X          X      2-Apr-07        X         X       9-Apr-07      X          X      23-Apr-07      X          X

SG 33951    CIV/346        COMP.BLDG       GROUND SLAB A                 HANSON     26-Mar-07   G40SM     3.0     75.0   29-Mar-07     X          X      2-Apr-07        X         X       9-Apr-07      X          X      23-Apr-07      X          X

SG 33955    CIV/347        COMP.BLDG       GROUND SLAB B & C             HANSON     27-Mar-07   G40SM     6.0     75.0   30-Mar-07     X          X      3-Apr-07      30.44     CIV/354   10-Apr-07   44.88     CIV/359   24-Apr-07    48.44     CIV/372        CONC SUPPLY BY SIME
                                                                                                                                                                                                                                                             TOTAL: 37 m3 4 GROUND SLAB B
SG 33958    CIV/347        COMP.BLDG       GROUND SLAB B & C             HANSON     27-Mar-07   G40SM     6.0     80.0   30-Mar-07     X          X      3-Apr-07        X         X       10-Apr-07     X          X      24-Apr-07      X          X
                                                                                                                                                                                                                                                                          &C
SG 33959    CIV/347        COMP.BLDG       GROUND SLAB B & C             HANSON     27-Mar-07   G40SM     6.0     80.0   30-Mar-07     X          X      3-Apr-07        X         X       10-Apr-07     X          X      24-Apr-07      X          X

SG 33963    CIV/347        COMP.BLDG       GROUND SLAB B & C             HANSON     27-Mar-07   G40SM     6.0     75.0   30-Mar-07     X          X      3-Apr-07        X         X       10-Apr-07     X          X      24-Apr-07      X          X

SG 33965    CIV/347        COMP.BLDG       GROUND SLAB B & C             HANSON     27-Mar-07   G40SM     6.0     80.0   30-Mar-07     X          X      3-Apr-07        X         X       10-Apr-07     X          X      24-Apr-07      X          X

SG 33968    CIV/347        COMP.BLDG       GROUND SLAB B & C             HANSON     27-Mar-07   G40SM     6.0     80.0   30-Mar-07     X          X      3-Apr-07      30.21     CIV/354   10-Apr-07   45.44     CIV/359   24-Apr-07    49.99     CIV/374

SG 33971    CIV/347        COMP.BLDG       GROUND SLAB B & C             HANSON     27-Mar-07   G40SM     1.0     80.0   30-Mar-07     X          X      3-Apr-07        X         X       10-Apr-07     X          X      24-Apr-07      X          X




 CONTRACTOR:SETMSB                                                                                                                                                                                                                      33bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                                                                                         SUMMARY OF CONCRETE POURING & CUBE TEST RESULT

                                                                                           EPCC FOR SEGAMAT COMPRESSOR STATION EXPANSION PROJECT
      SE-TMSB CONSORTIUM
                                                                                                                                                                                       TEST DATE / AVE. STRENGTH (N/mm2)
                                                                                                                                                       3 DAYS                             7 DAYS                         14 DAYS                          28 DAYS
BATCH /    PRE CONC.                                                                   SUPPLIER                 DESIGN      QTY    SLUMP
                        LOCATION / AREA                 DESCRIPTION                               DATE CAST                                                                                                                                                                               REMARKS
DO NO.      RFI NO.                                                                      NAME                   (N/mm2)     (M3)    (mm)                AVG.    CUBE TEST                  AVG.   CUBE TEST                AVG.    CUBE TEST               AVG.     CUBE TEST
                                                                                                                                           DATE TEST                      DATE TEST                         DATE TEST                        DATE TEST
                                                                                                                                                       N/mm2     RFI NO.                  N/mm2    RFI NO.                N/mm2     RFI NO.               N/mm2      RFI NO.

SG 33999    CIV/349     GEN. ROOM FDTN    SLAB                                         HANSON     30-Mar-07     G40SM       5.0     75.0    2-Apr-07    21.77    CIV/353   6-Apr-07       29.33     CIV/357   13-Apr-07     X          X      27-Apr-07      X          X

SG 33400    CIV/349     GEN. ROOM FDTN    SLAB                                         HANSON     30-Mar-07     G40SM       5.0     75.0    2-Apr-07     X          X      6-Apr-07         X         X       13-Apr-07   47.55     CIV/362   27-Apr-07      X          X

SG 33401    CIV/349     GEN. ROOM FDTN    SLAB                                         HANSON     30-Mar-07     G40SM       4.0     80.0    2-Apr-07     X          X      6-Apr-07         X         X       13-Apr-07     X          X      27-Apr-07    48.89     CIV/376

SG 34087    CIV/356    COMPRESSOR BLDG    SMALL FOUNDATION                             HANSON      7-Apr-07     G40SM       4.0     80.0   10-Apr-07     X          X      14-Apr-07      31.55     CIV/364   21-Apr-07   46.44     CIV/375   5-May-07       X          X

SG 34090    CIV/356    COMPRESSOR BLDG    SMALL FOUNDATION                             HANSON      7-Apr-07     G40SM       1.5     80.0   10-Apr-07     X          X      14-Apr-07        X         X       21-Apr-07     X          X      5-May-07     47.21     CIV/379
                                          COLUMN: A1, B1, C1, D1, E1 & F1 @ 3.60M
SG 34126    CIV/360    COMPRESSOR BLDG                                                 HANSON      13-Apr-07    G30SM       6.0     85.0   16-Apr-07     X          X      20-Apr-07      29.77     CIV/369   27-Apr-07     X          X      11-May-07      X          X
                                          HIGH
                                          COLUMN: A1, B1, C1, D1, E1 & F1 @ 3.60M
SG 34128    CIV/360    COMPRESSOR BLDG                                                 HANSON      13-Apr-07    G30SM       5.0     90.0   16-Apr-07     X          X      20-Apr-07        X         X       27-Apr-07   37.55     CIV/377   11-May-07      X          X
                                          HIGH
                                          COLUMN: A1, B1, C1, D1, E1 & F1 @ 3.60M
SG 34129    CIV/360    COMPRESSOR BLDG                                                 HANSON      13-Apr-07    G30SM       6.0     85.0   16-Apr-07     X          X      20-Apr-07        X         X       27-Apr-07     X          X      11-May-07    43.99     CIV/380
                                          HIGH
SG 34164    CIV/365    COMPRESSOR BLDG    COLUMN: F2, F3,F4 @ 3.60M HIGH               HANSON      17-Apr-07    G30SM       4.5     80.0   20-Apr-07     X          X      24-Apr-07      33.11     CIV/373   3-May-07    38.21     CIV/378   15-May-07    43.33     CIV/381

SG 34165    CIV/365    COMPRESSOR BLDG    COLUMN: F2, F3,F4 @ 3.60M HIGH               HANSON      17-Apr-07    G30SM       4.0     85.0   20-Apr-07     X          X      24-Apr-07        X         X       3-May-07      X          X      15-May-07      X          X

SG 34172    CIV/382    COMPRESSOR BLDG    COLUMN:A2, A3, A4 @ 3.60M HIGH               HANSON      19-Apr-07    G30SM       4.5    100.0   22-Apr-07     X          X      26-Apr-07      29.85     CIV/384   3-May-07    37.10     CIV/385   17-May-07    43.10     CIV/386

SG 34173    CIV/382    COMPRESSOR BLDG    COLUMN:A2, A3, A4 @ 3.60M HIGH               HANSON      19-Apr-07    G30SM       4.0    100.0   22-Apr-07     X          X      26-Apr-07        X         X       3-May-07      X          X      17-May-07      X          X
                                          WALL GL (D/1-E/1) & ( C/1-D/1) @ 3.6M
SG 34182    CIV/383    COMPRESSOR BLDG                                                 HANSON      20-Apr-07    G30PSM      5.0    120.0   23-Apr-07     X          X      27-Apr-07      31.77     CIV/387   4-May-07    38.44     CIV/388   18-May-07    44.21     CIV/389
                                          HIGH
                                          WALL GL (A/1-B/1), (B/1-C/1) & (E/1-F/1) @
SG 34191    CIV/390    COMPRESSOR BLDG                                                 HANSON      21-Apr-07    G30PSM      6.0    100.0   24-Apr-07     X          X      28-Apr-07      35.78     CIV/391   5-May-07    37.99     CIV/392   19-May-07    44.66     CIV/393
                                          3.6M HIGH
                                          WALL GL (F/1-F/2), (F/2-F/3) & (F/3-F/4) @
SG 34209    CIV/394    COMPRESSOR BLDG                                                 HANSON      24-Apr-07    G30PSM      6.0    100.0   27-Apr-07     X          X      3-May-07       30.66     CIV/398   8-May-07    44.44     CIV/399   22-May-07    50.88     CIV/400
                                          3.6M HIGH
                                          WALL GL (F/1-F/2), (F/2-F/3) & (F/3-F/4) @
SG 34213    CIV/394    COMPRESSOR BLDG                                                 HANSON      24-Apr-07    G30PSM      6.0    110.0   27-Apr-07     X          X      3-May-07         X         X       8-May-07      X          X      22-May-07      X          X
                                          3.6M HIGH
SG 34214    CIV/395    COMPRESSOR BLDG    COLUMN: B4, C4 @ 3.60M HIGH                  HANSON      24-Apr-07    G30PSM      6.0    100.0   27-Apr-07     X          X      3-May-07         X         X       8-May-07      X          X      22-May-07      X          X

SG 34249    CIV/395    COMPRESSOR BLDG    COLUMN: D4 & E4 @ 3.60M HIGH                 HANSON      24-Apr-07    G30PSM      5.0    110.0   27-Apr-07     X          X      1-May-07       31.55     CIV/404   8-May-07    37.55     CIV/405   22-May-07    44.66     CIV/406

SG 34251    CIV/396    COMPRESSOR BLDG    WALL GL (A2-A3) & (A3-A4) @ 3.6M HIGH        HANSON      24-Apr-07    G30PSM      5.0    120.0   27-Apr-07     X          X      1-May-07         X         X       8-May-07      X          X      22-May-07      X          X


SG 34252    CIV/396    COMPRESSOR BLDG    WALL GL (A2-A3) & (A3-A4) @ 3.6M HIGH        HANSON      24-Apr-07    G30PSM      4.0    100.0   27-Apr-07     X          X      1-May-07         X         X       8-May-07      X          X      22-May-07      X          X

                                                                                                               G35 TREMIE
SG 34217    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                6.0    120.0   28-Apr-07     X          X      2-May-07         X         X       9-May-07      X          X      23-May-07      X          X
                                                                                                                  1 MIX
                                                                                                               G35 TREMIE
SG 34218    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                6.0    110.0   28-Apr-07     X          X      2-May-07         X         X       9-May-07      X          X      23-May-07      X          X
                                                                                                                  1 MIX
                                                                                                               G35 TREMIE
SG 34220    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                6.0    120.0   28-Apr-07     X          X      2-May-07         X         X       9-May-07      X          X      23-May-07      X          X
                                                                                                                  1 MIX
                                                                                                               G35 TREMIE
SG 34222    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                6.0    120.0   28-Apr-07     X          X      2-May-07       33.21     CIV/401   9-May-07    37.99     CIV/402   23-May-07    45.55     CIV/403
                                                                                                                  1 MIX
                                                                                                               G35 TREMIE
SG 34223    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                6.0    130.0   28-Apr-07     X          X      2-May-07         X         X       9-May-07      X          X      23-May-07      X          X
                                                                                                                  1 MIX
                                                                                                               G35 TREMIE
SG 34224    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                6.0    130.0   28-Apr-07     X          X      2-May-07         X         X       9-May-07      X          X      23-May-07      X          X
                                                                                                                  1 MIX
                                                                                                               G35 TREMIE
SG 34227    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                6.0    120.0   28-Apr-07     X          X      2-May-07         X         X       9-May-07      X          X      23-May-07      X          X
                                                                                                                  1 MIX
                                                                                                               G35 TREMIE
SG 34230    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                6.0    130.0   28-Apr-07     X          X      2-May-07         X         X       9-May-07      X          X      23-May-07      X          X
                                                                                                                  1 MIX
                                                                                                               G35 TREMIE
SG 34231    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                6.0    120.0   28-Apr-07     X          X      2-May-07       31.11     CIV/401   9-May-07    39.33     CIV/402   23-May-07    47.99     CIV/403
                                                                                                                  1 MIX
                                                                                                               G35 TREMIE
SG 34236    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                6.0    140.0   28-Apr-07     X          X      2-May-07         X         X       9-May-07      X          X      23-May-07      X          X
                                                                                                                  1 MIX
                                                                                                               G35 TREMIE
SG 34238    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                6.0    140.0   28-Apr-07     X          X      2-May-07         X         X       9-May-07      X          X      23-May-07      X          X
                                                                                                                  1 MIX
                                                                                                               G35 TREMIE
SG 34240    CIV/397    FIREWATER TANK     SLAB & WALL UP TO 0.65 M HIGH                HANSON      25-Apr-07                5.0    130.0   28-Apr-07     X          X      2-May-07         X         X       9-May-07      X          X      23-May-07      X          X
                                                                                                                  1 MIX

SG 34279    CIV/407    COMPRESSOR BLDG    COLUMN: A1, B1 & C1 @ 7.20M HIGH             HANSON      3-May-07     G30PSM      6.0    110.0    6-May-07     X          X      10-May-07      34.45     CIV/415   17-May-07   40.44     CIV/416   31-May-07    44.21     CIV/417
                                          WALL GL (A4-B4), (B4-C4) , (C4-D4), (D4-
SG 34276    CIV/408    COMPRESSOR BLDG    E4), (E4-F4) & (A1-A2) @ 3.6M HIGH           HANSON      30-Apr-07    G30PSM      5.0    110.0    3-May-07     X          X      7-May-07       34.67     CIV/412   14-May-07   40.88     CIV/413   28-May-07    45.99     CIV/414

                                          WALL GL (A4-B4), (B4-C4) , (C4-D4), (D4-
SG 34277    CIV/408    COMPRESSOR BLDG    E4), (E4-F4) & (A1-A2) @ 3.6M HIGH           HANSON      30-Apr-07    G30PSM      5.0    100.0    3-May-07     X          X      7-May-07         X         X       14-May-07     X          X      28-May-07      X          X

                                          WALL GL (A4-B4), (B4-C4) , (C4-D4), (D4-
SG 34278    CIV/408    COMPRESSOR BLDG    E4), (E4-F4) & (A1-A2) @ 3.6M HIGH           HANSON      30-Apr-07    G30PSM      6.0    110.0    3-May-07     X          X      7-May-07         X         X       14-May-07     X          X      28-May-07      X          X




 CONTRACTOR:SETMSB                                                                                                                                                                                                                                         43bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                                                                                       SUMMARY OF CONCRETE POURING & CUBE TEST RESULT

                                                                                         EPCC FOR SEGAMAT COMPRESSOR STATION EXPANSION PROJECT
      SE-TMSB CONSORTIUM
                                                                                                                                                                                  TEST DATE / AVE. STRENGTH (N/mm2)
                                                                                                                                                   3 DAYS                            7 DAYS                         14 DAYS                           28 DAYS
BATCH /    PRE CONC.                                                                 SUPPLIER                DESIGN     QTY    SLUMP
                        LOCATION / AREA                DESCRIPTION                              DATE CAST                                                                                                                                                                                 REMARKS
DO NO.      RFI NO.                                                                    NAME                  (N/mm2)    (M3)    (mm)                AVG.    CUBE TEST                 AVG.   CUBE TEST                AVG.    CUBE TEST                AVG.     CUBE TEST
                                                                                                                                       DATE TEST                      DATE TEST                        DATE TEST                        DATE TEST
                                                                                                                                                   N/mm2     RFI NO.                 N/mm2    RFI NO.                N/mm2     RFI NO.                N/mm2      RFI NO.

                                          PRECAST SMALL FOUNDATION FOR LIFE
SG 34280    CIV/408A    HOARDING AREA                                                HANSON      30-Apr-07   G40N(SM)   4.5     80.0    3-May-07     X          X      7-May-07      31.33    CIV/408B   14-May-07   38.22     CIV/408C   28-May-07    47.32     CIV/408D
                                          PLANT INCLUDE. E&I SUP. TYPE S

SG 34280    CIV/409    COMPRESSOR BLDG    COLUMN: D1, E1 & F1 @ 7.20M HIGH           HANSON      4-May-07    G30PSM     4.5    100.0    7-May-07     X          X     11-May-07      31.99     CIV/418   18-May-07   38.88     CIV/419    1-Jun-07     44.66     CIV/420

SG 34281    CIV/409    COMPRESSOR BLDG    COLUMN: D1, E1 & F1 @ 7.20M HIGH           HANSON      4-May-07    G30PSM     4.0    110.0    7-May-07     X          X     11-May-07        X         X       18-May-07     X          X       1-Jun-07       X          X

SG 34301    CIV/411    COMPRESSOR BLDG    COLUMN: F2, F3 & F4 @ 7.20M HIGH           HANSON      7-May-07    G30PSM     5.0     100    10-May-07     X          X     14-May-07      31.11     CIV/424   21-May-07   38.88     CIV/425    4-Jun-07     48.66     CIV/426    1.0M3 USED FOR LEAN CONC AT
                                                                                                                                                                                                                                                                            PUMP HOUSE TO LOCAL ENG.
SG 34302    CIV/411    COMPRESSOR BLDG    COLUMN: F2, F3 & F4 @ 7.20M HIGH           HANSON      7-May-07    G30PSM     4.5     100    10-May-07     X          X     14-May-07        X         X       21-May-07     X          X       4-Jun-07       X          X       REFER TO RFI/CIV/410

SG 34337    CIV/421    COMPRESSOR BLDG    WALL: A1-B1, B1-C1 @ 7.2M HIGH             HANSON     10-May-07    G30PSM     6.0    110.0   13-May-07     X          X     17-May-07      32.88     CIV/427   24-May-07   39.33     CIV/428    7-Jun-07     46.21     CIV/429

                                          COLUMN: A2,A3,A4,B4,C4,D4,E4 & F4@                                                                                                                                                                                                  0.4 M3 USED FOR WALL @ A1
SG 34333    CIV/422    COMPRESSOR BLDG                                               HANSON     10-May-07    G30PSM     6.0    100.0   13-May-07     X          X     17-May-07      32.88     CIV/427   24-May-07   39.33     CIV/428    7-Jun-07     46.21     CIV/429
                                          7.2M HIGH                                                                                                                                                                                                                                (ROLLER SHUTER)
                                          COLUMN: A2,A3,A4,B4,C4,D4,E4 & F4@
SG 34334    CIV/422    COMPRESSOR BLDG                                               HANSON     10-May-07    G30PSM     6.0    110.0   13-May-07     X          X     17-May-07        X         X       24-May-07     X          X       7-Jun-07       X          X
                                          7.2M HIGH
                                          COLUMN: A2,A3,A4,B4,C4,D4,E4 & F4@
SG 34335    CIV/422    COMPRESSOR BLDG                                               HANSON     10-May-07    G30PSM     4.0    110.0   13-May-07     X          X     17-May-07        X         X       24-May-07     X          X       7-Jun-07       X          X
                                          7.2M HIGH
                                          COLUMN: A2,A3,A4,B4,C4,D4,E4 & F4@
SG 34336    CIV/422    COMPRESSOR BLDG                                               HANSON     10-May-07    G30PSM     3.0    120.0   13-May-07     X          X     17-May-07        X         X       24-May-07     X          X       7-Jun-07       X          X
                                          7.2M HIGH

SG 34351    CIV/423    COMPRESSOR BLDG    WALL: 1/C-D,1/D-E,1/E-F @ 7.2M HIGH        HANSON     12-May-07    G30PSM     4.0     120    15-May-07     X          X     19-May-07      29.77     CIV/430   26-May-07   36.89     CIV/431    9-Jun-07     48.67     CIV/432

SG 34354    CIV/423    COMPRESSOR BLDG    WALL: 1/C-D,1/D-E,1/E-F @ 7.2M HIGH        HANSON     12-May-07    G30PSM     4.0     110    15-May-07     X          X     19-May-07        X         X       26-May-07     X          X       9-Jun-07       X          X

SG 34403    CIV/433    COMPRESSOR BLDG    WALL: F/1-2, F/2-3 & F/3-4 @ 7.2M HIGH     HANSON     16-May-07    G30PSM     5.0     120    19-May-07     X          X     23-May-07      31.99     CIV/440   30-May-07   38.21     CIV/441    13-Jun-07    42.22     CIV/442

SG 34407    CIV/433    COMPRESSOR BLDG    WALL: F/1-2, F/2-3 & F/3-4 @ 7.2M HIGH     HANSON     16-May-07    G30PSM     5.0     120    19-May-07     X          X     23-May-07        X         X       30-May-07     X          X       13-Jun-07      X          X

SG 34408    CIV/433    COMPRESSOR BLDG    WALL: F/1-2, F/2-3 & F/3-4 @ 7.2M HIGH     HANSON     16-May-07    G30PSM     3.5     120    19-May-07     X          X     23-May-07        X         X       30-May-07     X          X       13-Jun-07      X          X

                                          WALL: 4/A-B, 4/B-C, 4/D-E & 4/E-F @ 7.2M
SG 34397    CIV/434    COMPRESSOR BLDG                                               HANSON     15-May-07    G30PSM     5.0     110    18-May-07     X          X     22-May-07      33.11     CIV/435   29-May-07   37.99     CIV/436    12-Jun-07    42.21     CIV/437
                                          HIGH
                                          WALL: 4/A-B, 4/B-C, 4/D-E & 4/E-F @ 7.2M
SG 34398    CIV/434    COMPRESSOR BLDG                                               HANSON     15-May-07    G30PSM     5.5     120    18-May-07     X          X     22-May-07        X         X       29-May-07     X          X       12-Jun-07      X          X
                                          HIGH

SG 34445    CIV/438    COMPRESSOR BLDG    WALL: A/1-2, A/2-3 & A/3-4 @ 7.2M HIGH     HANSON     18-May-07    G30PSM     3.5    120.0   21-May-07     X          X     25-May-07        X         X       1-Jun-07      X          X       15-Jun-07      X          X

SG 34447    CIV/438    COMPRESSOR BLDG    WALL: A/1-2, A/2-3 & A/3-4 @ 7.2M HIGH     HANSON     18-May-07    G30PSM     3.0    110.0   21-May-07     X          X     25-May-07        X         X       1-Jun-07      X          X       15-Jun-07      X          X

SG 34458    CIV/444    COMPRESSOR BLDG    COLUMN: B1, C1, D1 & E1 @ 10.8M HIGH       HANSON     19-May-07    G30PSM     5.0     120    22-May-07     X          X     26-May-07      32.55     CIV/449   2-Jun-07    37.32     CIV/450    16-Jun-07    46.66     CIV/451

SG 34459    CIV/444    COMPRESSOR BLDG    COLUMN: B1, C1, D1 & E1 @ 10.8M HIGH       HANSON     19-May-07    G30PSM     5.0     110    22-May-07     X          X     26-May-07        X         X       2-Jun-07      X          X       16-Jun-07      X          X

SG 34496    CIV/445    SOC - PUMP HOUSE   NEW FOUNDATION                             HANSON     23-May-07    G40 SM     4.0     90     26-May-07     X          X     30-May-07      31.55    CIV/456A   6-Jun-07    40.66     CIV/457A   20-Jun-07    54.99     CIV/458A

SG 34498    CIV/445    SOC - PUMP HOUSE   NEW FOUNDATION                             HANSON     23-May-07    G40 SM     3.6     80     26-May-07     X          X     30-May-07        X         X       6-Jun-07      X          X       20-Jun-07      X          X

                                          COLUMN:F1, A1, F2, F3, & F4 @ 10.8M
SG 34492    CIV/452    COMPRESSOR BLDG                                               HANSON     23-May-07    G30PSM     5.0     110    26-May-07     X          X     30-May-07        X         X       6-Jun-07      X          X       20-Jun-07      X          X
                                          HIGH
                                          COLUMN:F1, A1, F2, F3, & F4 @ 10.8M
SG 34495    CIV/452    COMPRESSOR BLDG                                               HANSON     23-May-07    G30PSM     4.5     100    26-May-07     X          X     30-May-07        X         X       6-Jun-07      X          X       20-Jun-07      X          X
                                          HIGH
                                          WALL: 1/A-B, 1/B-C, 1C-D, 1D-E, & 1E-F @
SG 34609    CIV/453    COMPRESSOR BLDG                                               HANSON     28-May-07    G30PSM     5.0     110    31-May-07     X          X      4-Jun-07      31.33     CIV/467   11-Jun-07   36.44     CIV/468    25-Jun-07    43.99     CIV/469
                                          10.8M HIGH
                                          WALL: 1/A-B, 1/B-C, 1C-D, 1D-E, & 1E-F @
SG 34610    CIV/453    COMPRESSOR BLDG                                               HANSON     28-May-07    G30PSM     5.0     110    31-May-07     X          X      4-Jun-07        X         X       11-Jun-07     X          X       25-Jun-07      X          X
                                          10.8M HIGH
                                                                                                                                                                                                                                                                            1.5M3 USED FOR SLAB & TRENCH PUMP
                                          WALL: 1/A-B, 1/B-C, 1C-D, 1D-E, & 1E-F @
SG 34612    CIV/453    COMPRESSOR BLDG                                               HANSON     28-May-07    G30PSM     4.0     100    31-May-07     X          X      4-Jun-07        X         X       11-Jun-07     X          X       25-Jun-07      X          X
                                          10.8M HIGH                                                                                                                                                                                                                        HOUSE (LOCAL ENG) REFER TO RFI/CIV/464

                                          COLUMN:A2, A3, A4, B4, C4, D4, E4,@
SG 34521    CIV/454    COMPRESSOR BLDG                                               HANSON     24-May-07    G30PSM     5.0     115    27-May-07     X          X     31-May-07      30.66     CIV/461   7-Jun-07    40.21     CIV/462    21-Jun-07    47.33     CIV/463
                                          10.8M HIGH
                                          COLUMN:A2, A3, A4, B4, C4, D4, E4,@
SG 34516    CIV/454    COMPRESSOR BLDG                                               HANSON     24-May-07    G30PSM     4.0     110    27-May-07     X          X     31-May-07        X         X       7-Jun-07      X          X       21-Jun-07      X          X
                                          10.8M HIGH
                                          COLUMN:A2, A3, A4, B4, C4, D4, E4,@
SG 34519    CIV/454    COMPRESSOR BLDG                                               HANSON     24-May-07    G30PSM     4.0     110    27-May-07     X          X     31-May-07        X         X       7-Jun-07      X          X       21-Jun-07      X          X
                                          10.8M HIGH
                                          COLUMN:A2, A3, A4, B4, C4, D4, E4,@
SG 34523    CIV/454    COMPRESSOR BLDG                                               HANSON     24-May-07    G30PSM     4.0     110    27-May-07     X          X     31-May-07        X         X       7-Jun-07      X          X       21-Jun-07      X          X
                                          10.8M HIGH
                                          WALL 4/A-B, 4/B-C, 4/C-D, 4/D-E, 4/E-F @
SG 34647    CIV/460    COMPRESSOR BLDG                                               HANSON     31-May-07    G30PSM     6.0     110     3-Jun-07     X          X      7-Jun-07      27.77     CIV/472   14-Jun-07   38.21     CIV/473    28-Jun-07    48.44     CIV/474
                                          10.8M HIGH
                                          WALL 4/A-B, 4/B-C, 4/C-D, 4/D-E, 4/E-F @
SG 34651    CIV/460    COMPRESSOR BLDG                                               HANSON     31-May-07    G30PSM     6.0     100     3-Jun-07     X          X      7-Jun-07        X         X       14-Jun-07     X          X       28-Jun-07      X          X
                                          10.8M HIGH

SG 34673    CIV/460    COMPRESSOR BLDG    WALL A/1-2, A/2-3,A/3-4 @ 10.8M HIGH       HANSON      1-Jun-07    G30PSM     4.5     110     4-Jun-07     X          X      8-Jun-07      29.55     CIV/475   15-Jun-07   36.66     CIV/476    29-Jun-07    44.88     CIV/477



 CONTRACTOR:SETMSB                                                                                                                                                                                                                                     53bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
SG 34674   CIV/460   COMPRESSOR BLDG   WALL A/1-2, A/2-3,A/3-4 @ 10.8M HIGH   HANSON   1-Jun-07   G30PSM   4.0   100   4-Jun-07   X   X   8-Jun-07   X   X   15-Jun-07   X   X   29-Jun-07    X          X

SG 34678   CIV/460   COMPRESSOR BLDG   WALL A/1-2, A/2-3,A/3-4 @ 10.8M HIGH   HANSON   1-Jun-07   G30PSM   4.5   110   4-Jun-07   X   X   8-Jun-07   X   X   15-Jun-07   X   X   29-Jun-07    X          X




 CONTRACTOR:SETMSB                                                                                                                                                                           63bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                                                                                      SUMMARY OF CONCRETE POURING & CUBE TEST RESULT

                                                                                        EPCC FOR SEGAMAT COMPRESSOR STATION EXPANSION PROJECT
      SE-TMSB CONSORTIUM
                                                                                                                                                                                TEST DATE / AVE. STRENGTH (N/mm2)
                                                                                                                                                3 DAYS                             7 DAYS                         14 DAYS                          28 DAYS
BATCH /    PRE CONC.                                                                SUPPLIER               DESIGN    QTY    SLUMP
                         LOCATION / AREA                DESCRIPTION                            DATE CAST                                                                                                                                                                            REMARKS
DO NO.      RFI NO.                                                                   NAME                 (N/mm2)   (M3)    (mm)                AVG.    CUBE TEST                  AVG.   CUBE TEST                AVG.    CUBE TEST               AVG.     CUBE TEST
                                                                                                                                    DATE TEST                      DATE TEST                         DATE TEST                        DATE TEST
                                                                                                                                                N/mm2     RFI NO.                  N/mm2    RFI NO.                N/mm2     RFI NO.               N/mm2      RFI NO.
                                           COLUMN:A1, B1, C1, D1, E1, F1, A2, A3,
SG 34675    CIV/470     COMPRESSOR BLDG                                             HANSON      1-Jun-07   G30PSM    6.0     110     4-Jun-07     X          X      8-Jun-07       29.55    CIV/475    15-Jun-07   36.66     CIV/476   29-Jun-07    44.88     CIV/477
                                           A4 @ 4FT CAST
                                           COLUMN:A1, B1, C1, D1, E1, F1, A2, A3,
SG 34676    CIV/470     COMPRESSOR BLDG                                             HANSON      1-Jun-07   G30PSM    6.0     100     4-Jun-07     X          X      8-Jun-07         X         X       15-Jun-07     X         X       29-Jun-07      X         X
                                           A4 @ 4FT CAST
                                           COLUMN:A1, B1, C1, D1, E1, F1, A2, A3,
SG 34677    CIV/470     COMPRESSOR BLDG                                             HANSON      1-Jun-07   G30PSM    6.0     100     4-Jun-07     X          X      8-Jun-07         X         X       15-Jun-07     X         X       29-Jun-07      X         X
                                           A4 @ 4FT CAST
SG 34681    CIV/471     COMPRESSOR BLDG    WALL F/1-2, F/2-3, F/3-4 @ 10.8M HIGH    HANSON      4-Jun-07   G30PSM    5.0     110     7-Jun-07     X          X     11-Jun-07       31.11    CIV/480    18-Jun-07   42.44     CIV/481   2-Jul-07     47.10     CIV/482

SG 34684    CIV/471     COMPRESSOR BLDG    WALL F/1-2, F/2-3, F/3-4 @ 10.8M HIGH    HANSON      4-Jun-07   G30PSM    5.0     100     7-Jun-07     X          X     11-Jun-07         X         X       18-Jun-07     X         X       2-Jul-07       X         X
                                                                                                                                                                                                                                                                         1.5M3 USED FOR SOC-PUMP HOUSE
SG 34688    CIV/471     COMPRESSOR BLDG    WALL F/1-2, F/2-3, F/3-4 @ 10.8M HIGH    HANSON      4-Jun-07   G30PSM    5.0     100     7-Jun-07     X          X     11-Jun-07         X         X       18-Jun-07     X         X       2-Jul-07       X         X        (LOCAL ENG), REFER TO RFI/CIV/466

SG 34694    CIV/478     COMPRESSOR BLDG    COLUMN:F2, F3, F4 @ 4FT CAST             HANSON      4-Jun-07   G30PSM    4.0     110     7-Jun-07     X          X     11-Jun-07         X         X       18-Jun-07     X         X       2-Jul-07       X         X

SG 34695    CIV/478     COMPRESSOR BLDG    COLUMN:F2, F3, F4 @ 4FT CAST             HANSON      4-Jun-07   G30PSM    4.0     100     7-Jun-07     X          X     11-Jun-07         X         X       18-Jun-07     X         X       2-Jul-07       X         X

SG 34712    CIV/478     COMPRESSOR BLDG    COLUMN:B4, C4, D4, E4 @ 4FT CAST         HANSON      5-Jun-07   G30PSM    4.0     110     8-Jun-07     X          X     12-Jun-07       27.77    CIV/483    19-Jun-07   37.33     CIV/484   3-Jul-07     43.99     CIV/485

SG 34713    CIV/478     COMPRESSOR BLDG    COLUMN:B4, C4, D4, E4 @ 4FT CAST         HANSON      5-Jun-07   G30PSM    4.0     110     8-Jun-07     X          X     12-Jun-07         X         X       19-Jun-07     X         X       3-Jul-07       X         X
                                           WALL & ROOF BEAM:1/A-B, 1/B-C, 1/C-D,
SG 34777    CIV/488     COMPRESSOR BLDG                                             HANSON     11-Jun-07   G30PSM    6.0     100    14-Jun-07     X          X     18-Jun-07       36.40    CIV/489    25-Jun-07   40.22     CIV/490   9-Jul-07     54.44     CIV/491
                                           1/D-E, 1/E-F @ 4FT CAST
                                           WALL & ROOF BEAM:1/A-B, 1/B-C, 1/C-D,
SG 34778    CIV/488     COMPRESSOR BLDG                                             HANSON     11-Jun-07   G30PSM    6.0     110    14-Jun-07     X          X     18-Jun-07         X         X       25-Jun-07     X         X       9-Jul-07       X         X
                                           1/D-E, 1/E-F @ 4FT CAST
                                           WALL & ROOF BEAM:1/A-B, 1/B-C, 1/C-D,
SG 34780    CIV/488     COMPRESSOR BLDG                                             HANSON     11-Jun-07   G30PSM    4.0     100    14-Jun-07     X          X     18-Jun-07         X         X       25-Jun-07     X         X       9-Jul-07       X         X
                                           1/D-E, 1/E-F @ 4FT CAST
                                           WALL & ROOF BEAM:A/1-2, A/2-3, A/3-4,
SG 34800    CIV/492     COMPRESSOR BLDG                                             HANSON     14-Jun-07   G30PSM    4.0     100    17-Jun-07     X          X     21-Jun-07       33.77    CIV/494    28-Jun-07   43.33     CIV/495   12-Jul-07    49.33     CIV/496
                                           F/1-2, F/2-3, F/3-4 @ 4FT CAST
                                           WALL & ROOF BEAM:A/1-2, A/2-3, A/3-4,
SG 34801    CIV/492     COMPRESSOR BLDG                                             HANSON     14-Jun-07   G30PSM    5.0     90     17-Jun-07     X          X     21-Jun-07         X         X       28-Jun-07     X         X       12-Jul-07      X         X
                                           F/1-2, F/2-3, F/3-4 @ 4FT CAST
                                           WALL & ROOF BEAM:A/1-2, A/2-3, A/3-4,
SG 34802    CIV/492     COMPRESSOR BLDG                                             HANSON     14-Jun-07   G30PSM    4.0     100    17-Jun-07     X          X     21-Jun-07         X         X       28-Jun-07     X         X       12-Jul-07      X         X
                                           F/1-2, F/2-3, F/3-4 @ 4FT CAST
                                           WALL & ROOF BEAM:A/1-2, A/2-3, A/3-4,
SG 34803    CIV/492     COMPRESSOR BLDG                                             HANSON     14-Jun-07   G30PSM    4.0     100    17-Jun-07     X          X     21-Jun-07         X         X       28-Jun-07     X         X       12-Jul-07      X         X
                                           F/1-2, F/2-3, F/3-4 @ 4FT CAST
                                           WALL & ROOF BEAM:A/1-2, A/2-3, A/3-4,
SG 34804    CIV/492     COMPRESSOR BLDG                                             HANSON     14-Jun-07   G30PSM    6.0     110    17-Jun-07     X          X     21-Jun-07       36.66    CIV/494    28-Jun-07   45.77     CIV/495   12-Jul-07    48.88     CIV/496
                                           F/1-2, F/2-3, F/3-4 @ 4FT CAST
                                           WALL & ROOF BEAM:A/1-2, A/2-3, A/3-4,
SG 34805    CIV/492     COMPRESSOR BLDG                                             HANSON     14-Jun-07   G30PSM    6.0     100    17-Jun-07     X          X     21-Jun-07         X         X       28-Jun-07     X         X       12-Jul-07      X         X
                                           F/1-2, F/2-3, F/3-4 @ 4FT CAST
                                           WALL & ROOF BEAM:A/1-2, A/2-3, A/3-4,
SG 34806    CIV/492     COMPRESSOR BLDG                                             HANSON     14-Jun-07   G30PSM    5.0     110    17-Jun-07     X          X     21-Jun-07         X         X       28-Jun-07     X         X       12-Jul-07      X         X
                                           F/1-2, F/2-3, F/3-4 @ 4FT CAST
                                           WALL & ROOF BEAM:4/A-B, 4/B-C, 4/C-D,
SG 34807    CIV/493     COMPRESSOR BLDG                                             HANSON     14-Jun-07   G30PSM    5.0     110    17-Jun-07     X          X     21-Jun-07         X         X       28-Jun-07     X         X       12-Jul-07      X         X
                                           4/D-E, 4/E-F @ 4FT CAST
                                           WALL & ROOF BEAM:4/A-B, 4/B-C, 4/C-D,
SG 34808    CIV/493     COMPRESSOR BLDG                                             HANSON     14-Jun-07   G30PSM    5.0     120    17-Jun-07     X          X     21-Jun-07         X         X       28-Jun-07     X         X       12-Jul-07      X         X
                                           4/D-E, 4/E-F @ 4FT CAST
                                           WALL & ROOF BEAM:4/A-B, 4/B-C, 4/C-D,
SG 34809    CIV/493     COMPRESSOR BLDG                                             HANSON     14-Jun-07   G30PSM    6.0     100    17-Jun-07     X          X     21-Jun-07         X         X       28-Jun-07     X         X       12-Jul-07      X         X
                                           4/D-E, 4/E-F @ 4FT CAST
                       PIPERACK (NON-
SG 34925    CIV/501                        COLUMN @ GL 19,20,21,22 (A/B)            HANSON     22-Jun-07   G30PSM    3.0     100    25-Jun-07     X          X     29-Jun-07       28.44    CIV/502    6-Jul-07    37.10     CIV/503   20-Jul-07    41.99     CIV/504
                       PROCESS AREA)
                       PIPERACK (PROCESS
SG 39527    CIV/505                        FOOTING @ GL 17a(A/B) & 18(A/B)          HANSON     26-Jun-07   G40SM     3.0     80     29-Jun-07     X          X      3-Jul-07       36.22    CIV/506    10-Jul-07   41.77     CIV/507   24-Jul-07    46.44     CIV/508
                       AREA / RO)

SG 39540    CIV/509     COMPRESSOR BLDG    CONC. GUTTER GL. A1-A4 (EAST)            HANSON     27-Jun-07   G30PSM    6.0     100    30-Jun-07     X          X      4-Jul-07       31.55    CIV/510    11-Jul-07   36.44     CIV/511   25-Jul-07    43.99     CIV/512

                                           Column 4 nos & tie beam 2 nos @ GL
SG 39570    CIV/515         PIPERACK                                                HANSON     30-Jun-07   G40SM     3.0     80      3-Jul-07     X          X      7-Jul-07       31.77    CIV/521    14-Jul-07   38.88     CIV/522   28-Jul-07    50.66     CIV/523
                                           17a(A/B) & 18(A/B)
                                           Column (up to 1st upper beam) at GL
SG 39562    CIV/516         PIPERACK                                                HANSON     29-Jun-07   G30NSM    5.0     80      2-Jul-07     X          X      6-Jul-07       31.99    CIV/517    13-Jul-07   35.99     CIV/518   27-Jul-07    53.33     CIV/519
                                           23,24,25,26 & 27 (A/B).
SG 39577    CIV/520     COMPRESSOR BLDG    CONC. GUTTER GL. A1-F1 (SOUTH)           HANSON     30-Jun-07   G30NSM    5.0     75      3-Jul-07     X          X      7-Jul-07        27.1    CIV/524    14-Jul-07   36.88     CIV/525   28-Jul-07    51.99     CIV/526

SG 39579    CIV/520     COMPRESSOR BLDG    CONC. GUTTER GL. A1-F1 (SOUTH)           HANSON     30-Jun-07   G30NSM    1.5     75      3-Jul-07     X          X      7-Jul-07         X         X       14-Jul-07     X         X       28-Jul-07      X         X

SG 39594    CIV/527      FIREWATER TANK       CONC. TO WALL UP TO 2.60m HIGH        HANSON      3-Jul-07   G35TM 1   6.0     120     6-Jul-07     X          X      10-Jul-07      27.55    CIV/528    17-Jul-07   36.66     CIV/529   31-Jul-07    43.55     CIV/530

SG 39595    CIV/527      FIREWATER TANK       CONC. TO WALL UP TO 2.60m HIGH        HANSON      3-Jul-07   G35TM 1   6.0     130     6-Jul-07     X          X      10-Jul-07        X         X       17-Jul-07     X         X       31-Jul-07      X         X

SG 39596    CIV/527      FIREWATER TANK       CONC. TO WALL UP TO 2.60m HIGH        HANSON      3-Jul-07   G35TM 1   6.0     120     6-Jul-07     X          X      10-Jul-07        X         X       17-Jul-07     X         X       31-Jul-07      X         X

SG 39598    CIV/527      FIREWATER TANK       CONC. TO WALL UP TO 2.60m HIGH        HANSON      3-Jul-07   G35TM 1   6.0     120     6-Jul-07     X          X      10-Jul-07        X         X       17-Jul-07     X         X       31-Jul-07      X         X

SG 39600    CIV/527      FIREWATER TANK       CONC. TO WALL UP TO 2.60m HIGH        HANSON      3-Jul-07   G35TM 1   6.0     110     6-Jul-07     X          X      10-Jul-07        X         X       17-Jul-07     X         X       31-Jul-07      X         X

SG 39602    CIV/527      FIREWATER TANK       CONC. TO WALL UP TO 2.60m HIGH        HANSON      3-Jul-07   G35TM 1   6.0     110     6-Jul-07     X          X      10-Jul-07      26.88    CIV/528    17-Jul-07   35.55     CIV/529   31-Jul-07    43.55     CIV/530

SG 39603    CIV/527      FIREWATER TANK       CONC. TO WALL UP TO 2.60m HIGH        HANSON      3-Jul-07   G35TM 1   6.0     125     6-Jul-07     X          X      10-Jul-07        X         X       17-Jul-07     X         X       31-Jul-07      X         X

SG 39604    CIV/527      FIREWATER TANK       CONC. TO WALL UP TO 2.60m HIGH        HANSON      3-Jul-07   G35TM 1   6.0     125     6-Jul-07     X          X      10-Jul-07        X         X       17-Jul-07     X         X       31-Jul-07      X         X

SG 39605    CIV/527      FIREWATER TANK       CONC. TO WALL UP TO 2.60m HIGH        HANSON      3-Jul-07   G35TM 1   6.0     120     6-Jul-07     X          X      10-Jul-07        X         X       17-Jul-07     X         X       31-Jul-07      X         X

SG 39606    CIV/527      FIREWATER TANK       CONC. TO WALL UP TO 2.60m HIGH        HANSON      3-Jul-07   G35TM 1   6.0     120     6-Jul-07     X          X      10-Jul-07        X         X       17-Jul-07     X         X       31-Jul-07      X         X

 CONTRACTOR:SETMSB                                                                                                                                                                                                                                  73bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                                                                                     SUMMARY OF CONCRETE POURING & CUBE TEST RESULT

                                                                                       EPCC FOR SEGAMAT COMPRESSOR STATION EXPANSION PROJECT
      SE-TMSB CONSORTIUM
                                                                                                                                                                                  TEST DATE / AVE. STRENGTH (N/mm2)
                                                                                                                                                  3 DAYS                             7 DAYS                         14 DAYS                          28 DAYS
BATCH /    PRE CONC.                                                               SUPPLIER                DESIGN     QTY    SLUMP
                         LOCATION / AREA               DESCRIPTION                            DATE CAST                                                                                                                                                                              REMARKS
DO NO.      RFI NO.                                                                  NAME                  (N/mm2)    (M3)    (mm)                 AVG.    CUBE TEST                  AVG.   CUBE TEST                AVG.    CUBE TEST               AVG.     CUBE TEST
                                                                                                                                     DATE TEST                       DATE TEST                         DATE TEST                        DATE TEST
                                                                                                                                                  N/mm2     RFI NO.                  N/mm2    RFI NO.                N/mm2     RFI NO.               N/mm2      RFI NO.
                                           CONC. TO CG1,CG3,CB1 @ GL
SG 39629    CIV/531         PIPE RACK                                              HANSON      4-Jul-07    G30N(SM)   4.0     80      7-Jul-07      X          X      11-Jul-07      34.44    CIV/534    18-Jul-07   39.33     CIV/535   1-Aug-07     45.99     CIV/536
                                           19,20,21,22
                                           CONC. TO CG1,CG3,CB1 @ GL
SG 39631    CIV/531         PIPE RACK                                              HANSON      4-Jul-07    G30N(SM)   3.5     80      7-Jul-07      X          X      11-Jul-07        X      CIV/534    18-Jul-07     X       CIV/535   1-Aug-07       X       CIV/536
                                           19,20,21,22
                                           CONC. TO COLUMNS @ GL. 17a,18(A&B)
SG 39692    CIV/538         PIPE RACK                                              HANSON      7-Jul-07    G30N(SM)   4.0     90      10-Jul-07     X          X      14-Jul-07      30.66    CIV/539    21-Jul-07   38.21     CIV/540   4-Aug-07     44.21     CIV/541
                                           @ EL 39.80 4 NOS.
                                           CONC. TO BEAMS @ GL. 23,24,25,26,27
SG 39698    CIV/542         PIPE RACK                                              HANSON      9-Jul-07    G30N(SM)   6.0     80      12-Jul-07     X          X      16-Jul-07      29.55    CIV/543    23-Jul-07    35.1     CIV/544   6-Aug-07     44.88     CIV/545
                                           (A&B) @ EL 39.80 4 NOS.
            CIV/546         PIPE RACK      1ST BEAM @ CG1,CG1,CG3 EL. 39.80m       HANSON      12-Jul-07   G30N(SM)   2.3     90      15-Jul-07     X          X      19-Jul-07      33.99    CIV/547    26-Jul-07   38.44     CIV/548   9-Aug-07     44.66     CIV/549    INCLUDED CASTING OF DIESEL
SG 39728
            CIV/546A     SOC-GEN. ROOM     CABLE TRENCH SLAB                       HANSON      12-Jul-07   G30N(SM)   1.7     90      15-Jul-07     X          X      19-Jul-07        X         X       26-Jul-07     X         X       9-Aug-07       X         X        STORAGE SLAB EDGING 0.5m3

SG 39750    CIV/550        COMP. BLDG      ROOF SLAB                               HANSON      14-Jul-07   G30N(SM)   6.0     80      17-Jul-07     X          X      21-Jul-07      29.32    CIV/551    28-Jul-07   42.44     CIV552    11-Aug-07    48.44     CIV/553

SG 39751    CIV/550        COMP. BLDG      ROOF SLAB                               HANSON      14-Jul-07   G30N(SM)   6.0     80      17-Jul-07     X          X      21-Jul-07        X         X       28-Jul-07     X         X       11-Aug-07      X         X

SG 39752    CIV/550        COMP. BLDG      ROOF SLAB                               HANSON      14-Jul-07   G30N(SM)   6.0     90      17-Jul-07     X          X      21-Jul-07        X         X       28-Jul-07     X         X       11-Aug-07      X         X

SG 39754    CIV/550        COMP. BLDG      ROOF SLAB                               HANSON      14-Jul-07   G30N(SM)   6.0     80      17-Jul-07     X          X      21-Jul-07        X         X       28-Jul-07     X         X       11-Aug-07      X         X

SG 39756    CIV/550        COMP. BLDG                                              HANSON      14-Jul-07   G30N(SM)   6.0     90      17-Jul-07     X          X      21-Jul-07        X         X       28-Jul-07     X         X       11-Aug-07      X         X
                                           ROOF SLAB
SG 39757    CIV/550        COMP. BLDG                                              HANSON      14-Jul-07   G30N(SM)   6.0     90      17-Jul-07     X          X      21-Jul-07      30.88    CIV/551    28-Jul-07   43.77     CIV/552   11-Aug-07    49.11     CIV/553
                                           ROOF SLAB
SG 39758    CIV/550        COMP. BLDG                                              HANSON      14-Jul-07   G30N(SM)   6.0     80      17-Jul-07     X          X      21-Jul-07        X         X       28-Jul-07     X         X       11-Aug-07      X         X
                                           ROOF SLAB
SG 39760    CIV/550        COMP. BLDG                                              HANSON      14-Jul-07   G30N(SM)   6.0     80      17-Jul-07     X          X      21-Jul-07        X         X       28-Jul-07     X         X       11-Aug-07      X         X
                                           ROOF SLAB
SG 39761    CIV/550        COMP. BLDG                                              HANSON      14-Jul-07   G30N(SM)   6.0     90      17-Jul-07     X          X      21-Jul-07        X         X       28-Jul-07     X         X       11-Aug-07      X         X
                                           ROOF SLAB
SG 39762    CIV/550        COMP. BLDG                                              HANSON      14-Jul-07   G30N(SM)   2.0     80      17-Jul-07     X          X      21-Jul-07        X         X       28-Jul-07     X         X       11-Aug-07      X         X
                                           ROOF SLAB
                                           CONC. TO WALL UP TO 2.30m   HIGH (2ND
SG 39792    CIV/554      FIREWATER TANK                                            HANSON      17-Jul-07   G35TM 1    6.0     100     20-Jul-07     X          X      24-Jul-07      31.11    CIV/555    31-Jul-07   41.32     CIV/556   14-Aug-07    50.66     CIV/557
                                                         LAYER)
                                           CONC. TO WALL UP TO 2.30m   HIGH (2ND
SG 39793    CIV/554      FIREWATER TANK                                            HANSON      17-Jul-07   G35TM 1    6.0     110     20-Jul-07     X          X      24-Jul-07        X         X       31-Jul-07     X         X       14-Aug-07      X         X
                                                         LAYER)
                                           CONC. TO WALL UP TO 2.30m   HIGH (2ND
SG 39795    CIV/554      FIREWATER TANK                                            HANSON      17-Jul-07   G35TM 1    6.0     100     20-Jul-07     X          X      24-Jul-07        X         X       31-Jul-07     X         X       14-Aug-07      X         X
                                                         LAYER)
                                           CONC. TO WALL UP TO 2.30m   HIGH (2ND
SG 39796    CIV/554      FIREWATER TANK                                            HANSON      17-Jul-07   G35TM 1    6.0     110     20-Jul-07     X          X      24-Jul-07        X         X       31-Jul-07     X         X       14-Aug-07      X         X
                                                         LAYER)
                                           CONC. TO WALL UP TO 2.30m   HIGH (2ND
SG 39797    CIV/554      FIREWATER TANK                                            HANSON      17-Jul-07   G35TM 1    6.0     100     20-Jul-07     X          X      24-Jul-07        X         X       31-Jul-07     X         X       14-Aug-07      X         X
                                                         LAYER)
                                           CONC. TO WALL UP TO 2.30m   HIGH (2ND
SG 39798    CIV/554      FIREWATER TANK                                            HANSON      17-Jul-07   G35TM 1    6.0     110     20-Jul-07     X          X      24-Jul-07      29.32    CIV/555    31-Jul-07   42.22     CIV/556   14-Aug-07     53.1     CIV/557
                                                         LAYER)
                                           CONC. TO WALL UP TO 2.30m   HIGH (2ND
SG 39799    CIV/554      FIREWATER TANK                                            HANSON      17-Jul-07   G35TM 1    6.0     100     20-Jul-07     X          X      24-Jul-07        X         X       31-Jul-07     X         X       14-Aug-07      X         X
                                                         LAYER)
                                           CONC. TO WALL UP TO 2.30m   HIGH (2ND
SG 39801    CIV/554      FIREWATER TANK                                            HANSON      17-Jul-07   G35TM 1    6.0     110     20-Jul-07     X          X      24-Jul-07        X         X       31-Jul-07     X         X       14-Aug-07      X         X
                                                         LAYER)
                                           CONC. TO WALL UP TO 2.30m   HIGH (2ND
SG 39803    CIV/554      FIREWATER TANK                                            HANSON      17-Jul-07   G35TM 1    6.0     100     20-Jul-07     X          X      24-Jul-07        X         X       31-Jul-07     X         X       14-Aug-07      X         X
                                                         LAYER)
                                           CONC. TO WALL UP TO 2.30m   HIGH (2ND
SG 39805    CIV/554      FIREWATER TANK                                            HANSON      17-Jul-07   G35TM 1    3.0     100     20-Jul-07     X          X      24-Jul-07        X         X       31-Jul-07     X         X       14-Aug-07      X         X
                                                         LAYER)
                       ROAD CROSSING
SG 39772    CIV/558                        CONC. SLAB 870mm X 2.0m X 150mm         HANSON      16-Jul-07   G30N(SM)   5.0     90      19-Jul-07    27.1     CIV/559   23-Jul-07      32.66    CIV/559    30-Jul-07    43.1     CIV/560   13-Aug-07    49.55     CIV/561
                       CONC. SLAB

SG 39816    CIV/562    SOC-GEN. ROOM       CONC. TO CABLE TRENCH WALL              HANSON      18-Jul-07   G30N(SM)   6.0     90      21-Jul-07     X          X      25-Jul-07      33.77    CIV/563    1-Aug-07     41.1     CIV/564   15-Aug-07    49.33     CIV/565

SG 39848    CIV/566         PIPE RACK      2ND. BEAM @ 41.25 (CG2,CB2,CG4)         HANSON      20-Jul-07   G30N(SM)   6.0     90      23-Jul-07     X          X      27-Jul-07      40.44    CIV/567    3-Aug-07    44.21     CIV/568   17-Aug-07    50.88     CIV/569

SG 39849    CIV/566         PIPE RACK      2ND. BEAM @ 41.25 (CG2,CB2,CG4)         HANSON      20-Jul-07   G30N(SM)   4.5     85      23-Jul-07     X          X      27-Jul-07        X         X       3-Aug-07      X         X       17-Aug-07      X         X

                                           PRECAST AIR INTAKE DUCK SUPPORT &
SG 39879    CIV/570        COMP. BLDG                                              HANSON      24-Jul-07   G40N(SM)   5.5     80      27-Jul-07     X          X      31-Jul-07      36.66    CIV/571    7-Aug-07    42.21     CIV/572   21-Aug-07    49.55     CIV/573
                                           OIL COOLER FDTN (F1, F1a,F4)

SG 39940    CIV/574        COMP. BLDG      CONC. GUTTER (WEST) @ GL. F1- F4        HANSON      26-Jul-07   G30N(SM)   6.0     90      29-Jul-07     X          X      2-Aug-07       30.44    CIV/575    9-Aug-07    37.77     CIV/576   23-Aug-07    45.77     CIV/577

SG 39941    CIV/574        COMP. BLDG      CONC. GUTTER (WEST) @ GL. F1- F4        HANSON      26-Jul-07   G30N(SM)   2.5     90      29-Jul-07     X          X      2-Aug-07         X         X       9-Aug-07      X         X       23-Aug-07      X         X

SG 39940    CIV/578        COMP. BLDG      CONC. GUTTER (NORTH) @ GL. A4 - F4      HANSON      26-Jul-07   G30N(SM)   6.0     90      29-Jul-07     X          X      2-Aug-07       30.44    CIV/579    9-Aug-07    37.77     CIV/580   23-Aug-07    45.77     CIV/581

SG 39941    CIV/578        COMP. BLDG      CONC. GUTTER (NORTH) @ GL. A4 - F4      HANSON      26-Jul-07   G30N(SM)   2.5     90      29-Jul-07     X          X      2-Aug-07         X         X       9-Aug-07      X         X       23-Aug-07      X         X

                                            2ND UPPER BEAM & COLUMN @ GL. 23
SG 39957    CIV/582         PIPE RACK                                              HANSON      28-Jul-07   G30N(SM)   6.0     90      31-Jul-07     X          X      4-Aug-07       29.11    CIV/583    11-Aug-07   36.88     CIV/584   25-Aug-07    45.33     CIV/585
                                                   TO 27 (A&B) EL. 41.25
                                            2ND UPPER BEAM & COLUMN @ GL. 23
SG 39962    CIV/582         PIPE RACK                                              HANSON      28-Jul-07   G30N(SM)   1.0     90      31-Jul-07     X          X      4-Aug-07         X         X       11-Aug-07     X         X       25-Aug-07      X         X
                                                   TO 27 (A&B) EL. 41.25




 CONTRACTOR:SETMSB                                                                                                                                                                                                                                    83bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                                                                                     SUMMARY OF CONCRETE POURING & CUBE TEST RESULT

                                                                                       EPCC FOR SEGAMAT COMPRESSOR STATION EXPANSION PROJECT
      SE-TMSB CONSORTIUM
                                                                                                                                                                                 TEST DATE / AVE. STRENGTH (N/mm2)
                                                                                                                                                 3 DAYS                             7 DAYS                         14 DAYS                          28 DAYS
BATCH /    PRE CONC.                                                               SUPPLIER                DESIGN     QTY    SLUMP
                         LOCATION / AREA               DESCRIPTION                            DATE CAST                                                                                                                                                                             REMARKS
DO NO.      RFI NO.                                                                  NAME                  (N/mm2)    (M3)    (mm)                AVG.    CUBE TEST                  AVG.   CUBE TEST                AVG.    CUBE TEST               AVG.     CUBE TEST
                                                                                                                                     DATE TEST                      DATE TEST                         DATE TEST                        DATE TEST
                                                                                                                                                 N/mm2     RFI NO.                  N/mm2    RFI NO.                N/mm2     RFI NO.               N/mm2      RFI NO.
                                           LUBE OIL COOLER PRECAST STUMP
SG 39980    CIV/586        COMP. BLDG                                              HANSON      31-Jul-07   G40N(SM)   4.5     90      3-Aug-07     X          X      7-Aug-07       31.55    CIV/587    14-Aug-07   38.44     CIV/588   28-Aug-07    51.77     CIV/589
                                           (F1,F1a)
                                           CONC. GUTTER (FASCIA - NORTH) GL A4 -
SG 39982    CIV/590        COMP. BLDG                                              HANSON      31-Jul-07   G30N(SM)   4.5     90      3-Aug-07     X          X      7-Aug-07       30.66    CIV/591    14-Aug-07   37.99     CIV/592   28-Aug-07     45.1     CIV/593
                                           F4)                                                                                                                                                                                                                              TEST REPORT: USE SAME
                                           CONC. GUTTER (FASCIA - WEST) GL F1 -                                                                                                                                                                                             RESULT (NORTH & WEST)
SG 39983    CIV/594        COMP. BLDG                                              HANSON      31-Jul-07   G30N(SM)   1.0     90      3-Aug-07     X          X      7-Aug-07       30.66    CIV/595    14-Aug-07   37.99     CIV/596   28-Aug-07     45.1     CIV/597
                                           F4)
                                           CONC. WALL ABCDE @ 6.9M (3RD
SG 40023    CIV/598            FWT                                                 HANSON      4-Aug-07     G35T1     6.0     120     7-Aug-07     X          X      11-Aug-07      30.21    CIV/599    18-Aug-07   38.66     CIV/600   1-Sep-07     48.66     CIV/601
                                           LAYER)
                                           CONC. WALL ABCDE @ 6.9M (3RD
SG 40024    CIV/598            FWT                                                 HANSON      4-Aug-07     G35T1     6.0     120     7-Aug-07     X          X      11-Aug-07        X         X       18-Aug-07     X         X       1-Sep-07       X         X
                                           LAYER)
                                           CONC. WALL ABCDE @ 6.9M (3RD
SG 40026    CIV/598            FWT                                                 HANSON      4-Aug-07     G35T1     6.0     110     7-Aug-07     X          X      11-Aug-07        X         X       18-Aug-07     X         X       1-Sep-07       X         X
                                           LAYER)
                                           CONC. WALL ABCDE @ 6.9M (3RD
SG 40028    CIV/598            FWT                                                 HANSON      4-Aug-07     G35T1     6.0     120     7-Aug-07     X          X      11-Aug-07        X         X       18-Aug-07     X         X       1-Sep-07       X         X
                                           LAYER)
                                           CONC. WALL ABCDE @ 6.9M (3RD
SG 40030    CIV/598            FWT                                                 HANSON      4-Aug-07     G35T1     6.0     120     7-Aug-07     X          X      11-Aug-07        X         X       18-Aug-07     X         X       1-Sep-07       X         X
                                           LAYER)
                                           CONC. WALL ABCDE @ 6.9M (3RD
SG 40031    CIV/598            FWT                                                 HANSON      4-Aug-07     G35T1     6.0     100     7-Aug-07     X          X      11-Aug-07      30.88    CIV/599    18-Aug-07    37.1     CIV/600   1-Sep-07     50.88     CIV/601
                                           LAYER)
                                           CONC. WALL ABCDE @ 6.9M (3RD
SG 40032    CIV/598            FWT                                                 HANSON      4-Aug-07     G35T1     6.0     120     7-Aug-07     X          X      11-Aug-07        X         X       18-Aug-07     X         X       1-Sep-07       X         X
                                           LAYER)
                                           CONC. WALL ABCDE @ 6.9M (3RD
SG 40034    CIV/598            FWT                                                 HANSON      4-Aug-07     G35T1     6.0     110     7-Aug-07     X          X      11-Aug-07        X         X       18-Aug-07     X         X       1-Sep-07       X         X
                                           LAYER)
                                           ROAD CROSSING SLAB (870MM X 2M X
SG 40027    CIV/602           PIPING                                               HANSON      4-Aug-07    G30N(SM)   5.0     90      7-Aug-07   27.33     CIV/603   11-Aug-07      32.44    CIV/603    18-Aug-07   38.44     CIV/604   1-Sep-07     46.44     CIV/605
                                           150MM) PRECAST
                                           LUBE OIL COOLER STUMP 4NOS & AIR
SG 40042    CIV/606        COMP. BLDG                                              HANSON      4-Aug-07    G40N(SM)   2.5     90      7-Aug-07     X          X      11-Aug-07      31.55    CIV/607    18-Aug-07   38.44     CIV/608   1-Sep-07     57.55     CIV/609
                                           INTAKE STUMP 2 NOS
SG 40104    CIV/611            E&1         LIGHTING POLE 2 NOS PRECAST             HANSON      8-Aug-07    G40N(SM)   2.0     90     11-Aug-07     X          X      15-Aug-07      29.98    CIV/612    22-Aug-07   40.44     CIV/613   5-Sep-07     55.11     CIV/614

SG 40104    CIV/615        COMP. BLDG      FOOTING R11 (12 NOS) PRECAST            HANSON      8-Aug-07    G40N(SM)   2.0     90     11-Aug-07     X          X      15-Aug-07      29.98    CIV/616    22-Aug-07   40.44     CIV/617   5-Sep-07     55.11     CIV/618

SG 40104    CIV/620        COMP. BLDG      FIRE CART SHED FOOTING 4 NOS            HANSON      8-Aug-07    G40N(SM)   2.0     90     11-Aug-07     X          X      15-Aug-07      29.98    CIV/621    22-Aug-07   40.44     CIV/622   5-Sep-07     55.11     CIV/623
                                           SCREEDING 1ST LAYER CEMENT MOTAR
SG 40192    CIV/626        COMP. BLDG                                              HANSON     16-Aug-07      1:3      5.0      -     19-Aug-07     X          X      23-Aug-07        X         X       30-Aug-07     X         X       13-Sep-07      X         X
                                                       ROOF SLAB
                                           SCREEDING 1ST LAYER CEMENT MOTAR
SG 40202    CIV/626        COMP. BLDG                                              HANSON     16-Aug-07      1:3      4.0      -     19-Aug-07     X          X      23-Aug-07        X         X       30-Aug-07     X         X       13-Sep-07      X         X
                                                       ROOF SLAB
                                           SCREEDING 1ST LAYER CEMENT MOTAR
SG 40219    CIV/626        COMP. BLDG                                              HANSON     16-Aug-07      1:3      5.0      -     19-Aug-07     X          X      23-Aug-07        X         X       30-Aug-07     X         X       13-Sep-07      X         X
                                                       ROOF SLAB
                                           SCREEDING 1ST LAYER CEMENT MOTAR
SG 40226    CIV/626        COMP. BLDG                                              HANSON     16-Aug-07      1:3      5.0      -     19-Aug-07     X          X      23-Aug-07        X         X       30-Aug-07     X         X       13-Sep-07      X         X
                                                       ROOF SLAB
                                           SCREEDING 1ST LAYER CEMENT MOTAR
SG 40264    CIV/626        COMP. BLDG                                              HANSON     20-Aug-07      1:3      4.0      -     23-Aug-07     X          X      27-Aug-07        X         X       3-Sep-07      X         X       17-Sep-07      X         X
                                                       ROOF SLAB
                                           SCREEDING 1ST LAYER CEMENT MOTAR
SG 40274    CIV/626        COMP. BLDG                                              HANSON     21-Aug-07      1:3      1.5      -     24-Aug-07     X          X      28-Aug-07        X         X       4-Sep-07      X         X       18-Sep-07      X         X
                                                       ROOF SLAB
SG 40201    CIV/627            FWT                      ROOF SLAB                  HANSON     16-Aug-07     G35T1     6.0     120    19-Aug-07     X          X      23-Aug-07      28.44    CIV/628    30-Aug-07    33.1     CIV/629   13-Sep-07    50.44     CIV/630

SG 40203    CIV/627            FWT                      ROOF SLAB                  HANSON     16-Aug-07     G35T1     6.0     110    19-Aug-07     X          X      23-Aug-07        X         X       30-Aug-07     X         X       13-Sep-07      X         X

SG 40206    CIV/627            FWT                      ROOF SLAB                  HANSON     16-Aug-07     G35T1     6.0     115    19-Aug-07     X          X      23-Aug-07        X         X       30-Aug-07     X         X       13-Sep-07      X         X

SG 40209    CIV/627            FWT                      ROOF SLAB                  HANSON     16-Aug-07     G35T1     6.0     120    19-Aug-07     X          X      23-Aug-07        X         X       30-Aug-07     X         X       13-Sep-07      X         X

SG 40210    CIV/627            FWT                      ROOF SLAB                  HANSON     16-Aug-07     G35T1     6.0     118    19-Aug-07     X          X      23-Aug-07        X         X       30-Aug-07     X         X       13-Sep-07      X         X

SG 40211    CIV/627            FWT                      ROOF SLAB                  HANSON     16-Aug-07     G35T1     6.0     110    19-Aug-07     X          X      23-Aug-07      29.32    CIV/628    30-Aug-07   32.66     CIV/629   13-Sep-07    48.44     CIV/630

SG 40214    CIV/627            FWT                      ROOF SLAB                  HANSON     16-Aug-07     G35T1     3.0     115    19-Aug-07     X          X      23-Aug-07        X         X       30-Aug-07     X         X       13-Sep-07      X         X

                       R11 & ACCESS        12NOS STUMP & 25NOS. FOOTING (R11)
SG 40221    CIV/631                                                                HANSON     17-Aug-07    G40N(SM)   6.0     80     20-Aug-07     X          X      24-Aug-07      31.77    CIV/632    31-Aug-07   37.77     CIV/633   14-Sep-07    46.66     CIV/634
                       PLATFORM            & 6NOS ACCESS PLATFORM

                       R11 & ACCESS        12NOS STUMP & 25NOS. FOOTING (R11)
SG 40228    CIV/631                                                                HANSON     17-Aug-07    G40N(SM)   3.0     95     20-Aug-07     X          X      24-Aug-07        X         X       31-Aug-07     X         X       14-Sep-07      X         X
                       PLATFORM            & 6NOS ACCESS PLATFORM
                                           ROAD CROSSING SLAB (870MM X 2M X
SG 40220    CIV/635           PIPING                                               HANSON     17-Aug-07    G30N(SM)   5.0     80     20-Aug-07   26.88     CIV/636   24-Aug-07      35.77    CIV/636    31-Aug-07   38.66     CIV/637   14-Sep-07    44.88     CIV/638
                                           150MM)

SG 40227    CIV/639            RO          FOOTING PS-749-004-VS                   HANSON     17-Aug-07    G40N(SM)   4.0     90     20-Aug-07     X          X      24-Aug-07      31.77    CIV/640    31-Aug-07   37.77     CIV/641   14-Sep-07    46.66     CIV/642

                                           ROAD CROSSING SLAB (870MM X 2M X
SG 40265    CIV/643           PIPING                                               HANSON     17-Aug-07    G30N(SM)   5.5     80     20-Aug-07   25.55     CIV/644   24-Aug-07      31.11    CIV/644    31-Aug-07    37.1     CIV/645   14-Sep-07    46.22     CIV/646
                                           150MM)
                                           STUMP PIPE SUPPORT R11 (15NOS)
SG 40334    CIV/649        COMP. BLDG                                              HANSON     24-Aug-07    G40N(SM)   0.7     90     27-Aug-07     X          X      31-Aug-07      32.44    CIV/650    7-Sep-07     39.1     CIV/651   21-Sep-07     53.1     CIV/652
                                           PRECAST
                                                                                                                                                                                                                                                                               SAME TEST RESULT
                                           FOOTING COVERED WALKWAY (6NOS)
SG 40334    CIV/653        COMP. BLDG                                              HANSON     24-Aug-07    G40N(SM)   4.3     90     27-Aug-07     X          X      31-Aug-07      32.44    CIV/654    7-Sep-07     39.1     CIV/655   21-Sep-07     53.1     CIV/656
                                           PRECAST



 CONTRACTOR:SETMSB                                                                                                                                                                                                                                   93bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
CONTRACTOR:SETMSB   103bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                                                                                      SUMMARY OF CONCRETE POURING & CUBE TEST RESULT

                                                                                        EPCC FOR SEGAMAT COMPRESSOR STATION EXPANSION PROJECT
      SE-TMSB CONSORTIUM
                                                                                                                                                                                TEST DATE / AVE. STRENGTH (N/mm2)
                                                                                                                                                 3 DAYS                            7 DAYS                         14 DAYS                          28 DAYS
BATCH /    PRE CONC.                                                                SUPPLIER               DESIGN     QTY    SLUMP
                        LOCATION / AREA                 DESCRIPTION                            DATE CAST                                                                                                                                                                           REMARKS
DO NO.      RFI NO.                                                                   NAME                 (N/mm2)    (M3)    (mm)                AVG.    CUBE TEST                 AVG.   CUBE TEST                AVG.    CUBE TEST               AVG.     CUBE TEST
                                                                                                                                     DATE TEST                      DATE TEST                        DATE TEST                        DATE TEST
                                                                                                                                                 N/mm2     RFI NO.                 N/mm2    RFI NO.                N/mm2     RFI NO.               N/mm2      RFI NO.
                                           STUMP SERVICE PLT.FRM FOR FILTER
                       PIPERACK & FILTER
SG 40339    CIV/657                        SPR. & PIPE SUPPORT UNDER P/RACK         HANSON     25-Aug-07   G40N(SM)   1.3     80     28-Aug-07     X          X      1-Sep-07      30.66    CIV/658    8-Sep-07    42.21     CIV/659   22-Sep-07    54.44     CIV/660
                          SEPARATOR
                                           (PRECAST)
                                                                                                                                                                                                                                                                              SAME TEST RESULT

SG 40339    CIV/661    PIPE VALVE SUPPORT FOOTING PVS 12 NOS                        HANSON     25-Aug-07   G40N(SM)   1.3     80     28-Aug-07     X          X      1-Sep-07      30.66    CIV/662    8-Sep-07    42.21     CIV/663   22-Sep-07    54.44     CIV/664


            CIV/668     GAS COOLER AREA    CONCRETE SLAB                            HANSON     27-Aug-07   G30N(SM)           80     30-Aug-07     X          X      3-Sep-07      29.32    CIV/669    10-Sep-07   37.32     CIV/670   24-Sep-07    46.77     CIV/671


                          OIL / WATER
            CIV/668A                       SLAB FOR OIL / WATER SEPARATOR           HANSON     27-Aug-07   G30N(SM)           90     30-Aug-07     X          X      3-Sep-07      27.77    CIV/669    10-Sep-07   35.77     CIV/670   24-Sep-07    44.44     CIV/671
                          SEPARATOR


            CIV/672           PVS          PS-749-004-VS & PS-750-004-VS            HANSON      3-Sep-07   G40N(SM)           90      6-Sep-07     X          X     10-Sep-07      29.33    CIV/673    17-Sep-07    37.1     CIV/674   1-Oct-07     54.88     CIV/675


            CIV/676        PIPE RACK       STUMP OF PIPE SUPPORT                    HANSON      4-Sep-07   G40N(SM)           90      7-Sep-07     X          X     11-Sep-07      31.55    CIV/677    18-Sep-07   39.33     CIV/678   2-Oct-07     54.22     CIV/679


                                           STUMP PIPE SUPPORT FOOTING R11
            CIV/680        COMP.BLDG                                                HANSON      4-Sep-07   G40N(SM)           90      7-Sep-07     X          X     11-Sep-07      31.55    CIV/681    18-Sep-07   39.33     CIV/682   2-Oct-07     54.22     CIV/683
                                           (PRECAST) 600 x 600 x 175


            CIV/686        COMP.BLDG       CONCRETE TO WALL                         HANSON      6-Sep-07   G35TM-1            90      9-Sep-07     X          X     13-Sep-07      30.44    CIV/687    20-Sep-07   37.33     CIV/688   4-Oct-07     47.66     CIV/689


                                           STUMP & GB F/C SHED FOOTING CCTV
            CIV/690      FIRE CART SHED                                             HANSON      7-Sep-07   G40N(SM)           80     10-Sep-07     X          X     14-Sep-07      31.11    CIV/691    21-Sep-07   39.77     CIV/692   5-Oct-07     55.99     CIV/693
                                           (4NOS)

                                           CONCRETING TO FOOTING FOR CCTV
            CIV/694        COMP.BLDG                                                HANSON      7-Sep-07   G40N(SM)           80     10-Sep-07     X          X     14-Sep-07      31.11    CIV/695    21-Sep-07   39.77     CIV/696   5-Oct-07     55.99     CIV/697
                                           FOUNDATION

                                           STUMP (4 NOS) & FOOTING (2 NOS) FOR
            CIV/701        COMP.BLDG                                                HANSON     11-Sep-07   G40N(SM)           75     14-Sep-07     X          X     18-Sep-07      31.77    CIV/702    25-Sep-07   41.32     CIV/703   9-Oct-07     55.33     CIV/704
                                           CCTV


            CIV/720        COMP.BLDG       ROAD CROSSING CONCRETE AND SLAB          HANSON     18-Sep-07   G30N(SM)           80     21-Sep-07     X          X     25-Sep-07      29.44    CIV/721    2-Oct-07    35.55     CIV/722   16-Oct-07    42.44     CIV/723


            CIV/728        COMP.BLDG       STUMP FOR CCTV                           HANSON     27-Sep-07   G40N(SM)           80     30-Sep-07     X          X      4-Oct-07      30.44    CIV/729    11-Oct-07   39.33     CIV/730   25-Oct-07     55.1     CIV/731


            CIV/732        COMP.BLDG       Base slab for valve chamber VC1&VC2      HANSON     27-Sep-07   G40N(SM)           80     30-Sep-07     X          X      4-Oct-07      30.44    CIV/733    11-Oct-07   39.33     CIV/734   25-Oct-07     55.1     CIV/735


            CIV/736        COMP.BLDG       Slump pipe support R11-G, precast        HANSON     27-Sep-07   G40N(SM)           80     30-Sep-07     X          X      4-Oct-07      30.44    CIV/737    11-Oct-07   39.33     CIV/738   25-Oct-07     55.1     CIV/739


                                           Footing for PS-751B, PS-764B, PS-752B,
            CIV/740        COMP.BLDG                                                HANSON     27-Sep-07   G40N(SM)           80     30-Sep-07     X          X      4-Oct-07      30.44    CIV/741    11-Oct-07   39.33     CIV/742   25-Oct-07     55.1     CIV/743
                                           PS-758B, precast


            CIV/743      FIRE CART SHED    SLAB, APRON &RAMP                        HANSON     24-Oct-07   G35TM-1            120    27-Oct-07     X          X     31-Oct-07       29.1    CIV/744    7-Nov-07    35.99     CIV/745   21-Nov-07    47.77     CIV/746


            CIV/748      HOARDING AREA     MISC. SERVICE & ACCESS PLATFORM          HANSON     29-Oct-07   G40N(SM)           90      1-Nov-07     X          X      5-Nov-07      31.33    CIV/749    12-Nov-07   37.32     CIV/750   26-Nov-07    53.77     CIV/751


                         NEW COVERED
            CIV/752                        GROUND BEAM                              HANSON     29-Oct-07   G40N(SM)           90      1-Nov-07     X          X      5-Nov-07      31.33    CIV/753    12-Nov-07   37.32     CIV/754   26-Nov-07    53.77     CIV/755
                           WALKWAY

                         NEW COVERED       FOOTING (16B) &GROUND BEAM (16B
            CIV/756                                                                 HANSON      3-Nov-07   G40N(SM)           90      6-Nov-07     X          X     10-Nov-07      34.88    CIV/757    17-Nov-07    43.1     CIV/758   1-Dec-07      57.1     CIV/759
                           WALKWAY         &17 B)

                                           BRICK SUMP, SUB BASE & LEAN
            CIV/760        COMP.BLDG                                                HANSON      3-Nov-07   G40N(SM)           100     6-Nov-07     X          X     10-Nov-07      31.33    CIV/761    17-Nov-07   40.21     CIV/762   1-Dec-07     55.99     CIV/763
                                           CONCRETE


            CIV/764        COMP.BLDG       DRAIN SUB BASE                           HANSON     10-Nov-07   G25N(SM)           80     13-Nov-07     X          X     17-Nov-07      19.55    CIV/765    24-Nov-07   23.33     CIV/766   8-Dec-07      33.1     CIV/767


            CIV/769      FIRE CART SHED    WALL & ROOF SLAB                         HANSON     19-Nov-07   G30N(SM)           90     22-Nov-07     X          X     26-Nov-07      29.55    CIV/770    3-Dec-07    34.21     CIV/771   17-Dec-07    42.21     CIV/772


            CIV/773        COMP.BLDG       GL 16B, 17B, 18B, 19B, 20B, 21B          HANSON     19-Nov-07   G30N(SM)           90     22-Nov-07     X          X     26-Nov-07      29.55    CIV/774    3-Dec-07    34.21     CIV/775   17-Dec-07    42.21     CIV/776




 CONTRACTOR:SETMSB                                                                                                                                                                                                                                 113bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
        CIV/777       COMP.BLDG      WALL PRECAST DRAIN             HANSON   19-Nov-07   G25N(SM)   90   22-Nov-07   X   X   26-Nov-07   18.66   CIV/778   3-Dec-07   23.11   CIV/779   17-Dec-07   30.66      CIV/780


        CIV/781     NEW GAS COOLER   LIGHTNING ARESTOR FOUNDATION   HANSON   19-Nov-07   G40N(SM)   90   22-Nov-07   X   X   26-Nov-07   31.99   CIV/782   3-Dec-07   40.44   CIV/783   17-Dec-07   53.77      CIV/784


        CIV/785     RO & HOARDING    BASE SLAB VALVE CHAMBER        HANSON   22-Nov-07   G40N(SM)   95   25-Nov-07   X   X   29-Nov-07   31.72   CIV/786   6-Dec-07   42.21   CIV/787   20-Dec-07   56.44      CIV/788




CONTRACTOR:SETMSB                                                                                                                                                                                   123bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                                                                                  SUMMARY OF CONCRETE POURING & CUBE TEST RESULT

                                                                                    EPCC FOR SEGAMAT COMPRESSOR STATION EXPANSION PROJECT
     SE-TMSB CONSORTIUM
                                                                                                                                                                            TEST DATE / AVE. STRENGTH (N/mm2)
                                                                                                                                             3 DAYS                            7 DAYS                         14 DAYS                           28 DAYS
BATCH /   PRE CONC.                                                             SUPPLIER               DESIGN     QTY    SLUMP
                        LOCATION / AREA                  DESCRIPTION                       DATE CAST                                                                                                                                                                            REMARKS
DO NO.     RFI NO.                                                                NAME                 (N/mm2)    (M3)    (mm)                AVG.    CUBE TEST                 AVG.   CUBE TEST                AVG.    CUBE TEST                AVG.     CUBE TEST
                                                                                                                                 DATE TEST                      DATE TEST                        DATE TEST                        DATE TEST
                                                                                                                                             N/mm2     RFI NO.                 N/mm2    RFI NO.                N/mm2     RFI NO.                N/mm2      RFI NO.

                         NEW COVERED
           CIV/789                          NEW COVERED WALKWAY (16B - 19B)     HANSON     27-Nov-07    G30NS             90     30-Nov-07     X          X      4-Dec-07      29.55    CIV/790    11-Dec-07   37.99     CIV/791    25-Dec-07     45.1     CIV/792
                           WALKWAY


           CIV/792A       COMP.BLDG         DRAIN SUB BASE                      HANSON     29-Nov-07   G25N(SM)           85      2-Dec-07     X          X      6-Dec-07      29.55    CIV/792B   13-Dec-07   31.33     CIV/792C   27-Dec-07    33.55     CIV/792D


                         NEW COVERED
           CIV/793                          BEAM, WALKWAY                       HANSON     28-Nov-07    G30SM             90      1-Dec-07     X          X      5-Dec-07      26.66    CIV/794    12-Dec-07    35.1     CIV/795    26-Dec-07    43.77     CIV/796
                           WALKWAY

                                            CONCRETING WALL FOR VALVE
           CIV/799         RO AREA                                              HANSON     29-Nov-07   G25N(SM)           80      2-Dec-07     X          X      6-Dec-07      19.33    CIV/800    13-Dec-07   23.44     CIV/801    27-Dec-07    31.99     CIV/802
                                            CHAMBER NO. 6


           CIV/803        COMP.BLDG         BASE SLAB FOR VALVE CHAMBER NO. 4   HANSON      3-Dec-07   G40N(SM)           95      6-Dec-07     X          X     10-Dec-07       33.1    CIV/804    17-Dec-07   43.77     CIV/805    31-Dec-07    54.22     CIV/806

                                            PRECAST FOUNDATION, SAFETY
           CIV/807        COMP.BLDG         SHOWER FOUNDATION, TRAFFIC          HANSON      3-Dec-07   G40N(SM)           95      6-Dec-07     X          X     10-Dec-07       33.1    CIV/808    17-Dec-07   43.77     CIV/809    31-Dec-07    54.22     CIV/810
                                            BARRIER FOUNDATION

           CIV/811           FWT            PIPE SUPPORT                        HANSON     13-Dec-07   G40N(SM)           85     16-Dec-07     X          X     20-Dec-07      31.99    CIV/812    27-Dec-07   40.88     CIV/813    10-Jan-08    57.55     CIV/814


           CIV/815         RO AREA          BASE SLAB VALVE CHAMBER VC7         HANSON     13-Dec-07   G40N(SM)           85     16-Dec-07     X          X     20-Dec-07      31.55    CIV/816    27-Dec-07   43.99     CIV/817    10-Jan-08    58.88     CIV/818


                                            CONCRETING TO ADDITIONAL STEEL &
           CIV/819        COMP.BLDG                                             HANSON     26-Dec-07   G40N(SM)           90     29-Dec-07     X          X      2-Jan-08      32.88    CIV/820    9-Jan-08    43.55     CIV/821    23-Jan-08    55.99     CIV/822
                                            RC SUPPORT


           CIV/823        COMP.BLDG         DRAIN WALL                          HANSON     28-Dec-07   G25N(SM)           85     31-Dec-07     X          X      4-Jan-08      23.99    CIV/824    11-Jan-08   30.88     CIV/825    25-Jan-08     37.1     CIV/826


           CIV/827        COMP.BLDG         BASE SLAB COVER WALKWAY             HANSON     29-Dec-07   G30(SM)            90      1-Jan-08     X          X      5-Jan-08      28.66    CIV/828    12-Jan-08    35.1     CIV/829    26-Jan-08    46.66     CIV/830


                         NEW COVERED
           CIV/831                          DRAIN SUBBASE WALKWAY               HANSON      3-Jan-08   G25(SM)            80      6-Jan-08     X          X     10-Jan-08      21.99    CIV/832    17-Jan-08   29.32     CIV/833    31-Jan-08     35.1     CIV/834
                           WALKWAY

                                            PRECAST PIPE SUPPORT FOR FUEL
           CIV/835         RO AREA                                              HANSON      3-Jan-08   G40N(SM)           80      6-Jan-08     X          X     10-Jan-08      29.99    CIV/836    17-Jan-08   40.21     CIV/837    31-Jan-08    53.55     CIV/838
                                            FILTER SEPARATOR


           CIV/839        COMP.BLDG         SUB BASE                            HANSON     15-Jan-08   G25(SM)            80     18-Jan-08     X          X     22-Jan-08      21.77    CIV/840    29-Jan-08   29.32     CIV/841    12-Feb-08     33.1     CIV/842


           CIV/844        COMP.BLDG         WALL DRAIN S3 - S2 & S4             HANSON     17-Jan-08   G25(SM)            80     20-Jan-08     X          X     24-Jan-08       27.1    CIV/845    31-Jan-08   34.21     CIV/846    14-Feb-08    36.99     CIV/847


           CIV/848        COMP.BLDG         DRAIN SUB BASE                      HANSON     25-Jan-08   G25(SM)            80     28-Jan-08     X          X      1-Feb-08      21.77    CIV/849    8-Feb-08    26.21     CIV/850    22-Feb-08     32.1     CIV/851


           CIV/852    RO AREA & COMP.BLDG EFM SHED FOUNDATION                   HANSON     24-Jan-08   G40(SM)            80     27-Jan-08     X          X     31-Jan-08      32.21    CIV/853    7-Feb-08    40.21     CIV/854    21-Feb-08    56.21     CIV/855


           CIV/856        COMP.BLDG         DRAIN SUB BASE                      HANSON     26-Jan-08   G25N(SM)           80     29-Jan-08     X          X      2-Feb-08      18.44    CIV/857    9-Feb-08    23.77     CIV/858    23-Feb-08    31.11     CIV/859


           CIV/860        COMP.BLDG         DRAIN BENCHING                      HANSON     28-Jan-08   G25N(SM)           80     31-Jan-08     X          X      4-Feb-08      18.66    CIV/861    11-Feb-08   23.55     CIV/862    25-Feb-08    30.88     CIV/863


           CIV/864        COMP.BLDG         DRAIN BENCHING                      HANSON     29-Jan-08   G25(SM)            80      1-Feb-08     X          X      5-Feb-08      22.44    CIV/865    12-Feb-08   29.33     CIV/866    26-Feb-08    33.07     CIV/867


           CIV/868        COMP.BLDG         SUB BASE DRAINAGE S11 - S12         HANSON     30-Jan-08   G25(SM)            80      2-Feb-08     X          X      6-Feb-08      22.44    CIV/869    13-Feb-08    29.1     CIV/870    27-Feb-08    33.32     CIV/871


           CIV/872        COMP.BLDG         DRAIN BENCHING                      HANSON     31-Jan-08   G25(SM)            90      3-Feb-08     X          X      7-Feb-08      18.44    CIV/873    14-Feb-08   22.44     CIV/874    28-Feb-08    29.77     CIV/875


                                            CONCRETING STUMP FOR EFM SHED
           CIV/876    RO AREA & COMP.BLDG                                       HANSON      2-Feb-08   G40N(SM)           80      5-Feb-08     X          X      9-Feb-08       29.1    CIV/877    16-Feb-08   39.99     CIV/878    1-Mar-08     51.99     CIV/879
                                            FOUNDATION


           CIV/880        COMP.BLDG         WALL DRAIN LINE S11 TO S12          HANSON      2-Feb-08   G25(SM)            80      5-Feb-08     X          X      9-Feb-08      30.66    CIV/881    16-Feb-08   30.99     CIV/882    1-Mar-08     35.33     CIV/883




CONTRACTOR:SETMSB                                                                                                                                                                                                                               133bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                    STATION FILTER
        CIV/884                      TEMPORARY SUPPORT TP-02          HANSON   4-Feb-08    G40(SM)    90   7-Feb-08    X   X   11-Feb-08   31.55   CIV/885    18-Feb-08   44.44   CIV/886    3-Mar-08    57.32      CIV/887
                     SEPARATOR


        CIV/888       COMP.BLDG      PRIOR CONCRETING TO APRON        HANSON   11-Feb-08   G35N(SM)   90   14-Feb-08   X   X   18-Feb-08   27.1    CIV/889    25-Feb-08   31.99   CIV/890    10-Mar-08   42.66      CIV/891


        CIV/892       COMP.BLDG      CONCRETE PAVING                  HANSON   18-Feb-08   G30N(SM)   90   21-Feb-08   X   X   25-Feb-08   27.1    CIV/893    3-Mar-08    37.55   CIV/894    17-Mar-08   45.77      CIV/895


       CIV/895B       COMP.BLDG      DRAIN SUBBASE                    HANSON   18-Feb-08   G25(SM)    85   21-Feb-08   X   X   25-Feb-08   21.77   CIV/895C   3-Mar-08    28.44   CIV/895D   17-Mar-08   32.66     CIV/895E


        CIV/896       COMP.BLDG      CONCRETE PAVING                  HANSON   19-Feb-08   G30N(SM)   90   22-Feb-08   X   X   26-Feb-08   27.99   CIV/897    4-Mar-08    40.21   CIV/898    18-Mar-08   45.99      CIV/899


       CIV/899A       COMP.BLDG      CONCRETE PAVING                  HANSON   21-Feb-08   G30N(SM)   85   24-Feb-08   X   X   28-Feb-08   29.77   CIV/899B   6-Mar-08    39.99   CIV/899C   20-Mar-08   47.33     CIV/899D


                                     PRIOR CONCRETING TO NEW ACCESS
        CIV/900       COMP.BLDG                                       HANSON   21-Feb-08   G40N(SM)   80   24-Feb-08   X   X   28-Feb-08   33.1    CIV/901    6-Mar-08    41.55   CIV/902    20-Mar-08   51.99      CIV/903
                                     ROAD


        CIV/904       COMP.BLDG      ACCESS ROAD PAVEMENT             HANSON   22-Feb-08   G40(SM)    80   25-Feb-08   X   X   29-Feb-08   27.1    CIV/905    7-Mar-08    36.44   CIV/906    21-Mar-08   44.21      CIV/907


        CIV/908       COMP.BLDG      ACCESS ROAD PAVEMENT             HANSON   25-Feb-08   G40(SM)    90   28-Feb-08   X   X   3-Mar-08    32.21   CIV/909    10-Mar-08   41.55   CIV/910    24-Mar-08   57.32      CIV/911


        CIV/914       COMP.BLDG      CONCRETE BENCHING                HANSON   26-Feb-08   G25(SM)    80   29-Feb-08   X   X   3-Mar-08    22.21   CIV/915    10-Mar-08   28.88   CIV/916    24-Mar-08   32.88      CIV/917


                                     CONCRETE PAVEMENT UNDER
        CIV/918       COMP.BLDG                                       HANSON   3-Mar-08    G40(SM)    90   6-Mar-08    X   X   10-Mar-08   32.88   CIV/919    17-Mar-08   44.88   CIV/920    31-Mar-08   57.11      CIV/921
                                     EXHAUST STACK

                  HOARDING AREA (GAS
        CIV/922                      CONCRETE PAVING                  HANSON   3-Mar-08    G30N(SM)   85   6-Mar-08    X   X   10-Mar-08   27.99   CIV/923    17-Mar-08   38.66   CIV/924    31-Mar-08   45.99      CIV/925
                       COOLER)

                  HOARDING AREA (GAS
        CIV/927                      CONCRETE PAVING                  HANSON   4-Mar-08    G30N(SM)   90   7-Mar-08    X   X   11-Mar-08   26.88   CIV/928    18-Mar-08   38.66   CIV/929    1-Apr-08    44.21      CIV/930
                       COOLER)




CONTRACTOR:SETMSB                                                                                                                                                                                        143bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                                                                                  SUMMARY OF CONCRETE POURING & CUBE TEST RESULT

                                                                                    EPCC FOR SEGAMAT COMPRESSOR STATION EXPANSION PROJECT
     SE-TMSB CONSORTIUM
                                                                                                                                                                               TEST DATE / AVE. STRENGTH (N/mm2)
                                                                                                                                               3 DAYS                             7 DAYS                         14 DAYS                           28 DAYS
BATCH /   PRE CONC.                                                             SUPPLIER                DESIGN     QTY    SLUMP
                        LOCATION / AREA                 DESCRIPTION                        DATE CAST                                                                                                                                                                               REMARKS
DO NO.     RFI NO.                                                                NAME                  (N/mm2)    (M3)    (mm)                 AVG.    CUBE TEST                  AVG.   CUBE TEST                AVG.    CUBE TEST                AVG.     CUBE TEST
                                                                                                                                  DATE TEST                       DATE TEST                         DATE TEST                        DATE TEST
                                                                                                                                               N/mm2     RFI NO.                  N/mm2    RFI NO.                N/mm2     RFI NO.                N/mm2      RFI NO.


           CIV/927A    FIRE WATER TANK     PIPE SUPPORT TYPE R13                HANSON     19-Sep-07    G40(SM)            80     22-Sep-07      X          X      26-Sep-07      35.33    CIV/725A   3-Oct-07    41.11     CIV/725B   17-Oct-07    50.00     CIV.725C


                      HOARDING AREA (GAS
           CIV/931                       CONCRETE PAVING                        HANSON      5-Mar-08    G30N(SM)           80      8-Mar-08      X          X      12-Mar-08       27.1    CIV/932    19-Mar-08    39.1     CIV/933    2-Apr-08     45.99     CIV/934
                           COOLER)

                      HOARDING AREA (GAS
           CIV/935                       CONCRETE PAVING                        HANSON     11-Mar-08    G30N(SM)           85     14-Mar-08      X          X      18-Mar-08      27.99    CIV/936    25-Mar-08    39.1     CIV/937    8-Apr-08     43.77     CIV/938
                           COOLER)


           CIV/939        COMP.BLDG        APRON (WEST SIDE)                    HANSON     15-Mar-08    G35N(SM)           90     18-Mar-08      X          X      22-Mar-08      29.55    CIV/940    29-Mar-08   35.99     CIV/941    12-Apr-08    42.88     CIV/942


                        STATION FILTER
           CIV/951                         PIPE & VALVE SUPPORT PS-750-020-VS   HANSON     10-May-08    G40(SM)            80     13-May-08    20.11     CIV/952   17-May-08      31.77    CIV/953    24-May-08   39.33     CIV/954    7-Jun-08     55.11     CIV/955
                         SEPARATOR


           CIV/956     GAS COOLER AREA     PS-617, PS-628, PS-628A              HANSON     15-May-08    G40(SM)            90     18-May-08      X          X      22-May-08      32.44    CIV/957    29-May-08   40.44     CIV/958    12-Jun-08    56.88     CIV/959


           CIV/960     GAS COOLER AREA     PRIOR CONCRETING TO PS-628A-020-VS   HANSON     15-May-08    G40(SM)            90     18-May-08      X          X      22-May-08      32.44    CIV/961    29-May-08   40.44     CIV/962    12-Jun-08    56.88     CIV/963


           CIV/964     GAS COOLER AREA     PRIOR CONCRETING TO PS-628-020-VS    HANSON     15-May-08    G40(SM)            90     18-May-08      X          X      22-May-08      32.44    CIV/965    29-May-08   40.44     CIV/966    12-Jun-08    56.88     CIV/967


           CIV/968        COMP.BLDG        WATER MIST                           HANSON     15-May-08    G40(SM)            80     18-May-08      X          X      22-May-08      30.88    CIV/969    29-May-08    39.1     CIV/970    12-Jun-08    57.55     CIV/971


           CIV/978        COMP.BLDG        PRIOR CONCRETING TO PS-752-004-R11   HANSON     29-May-08    G40(SM)            95      1-Jun-08      X          X      5-Jun-08       31.33    CIV/979    12-Jun-08    43.1     CIV/980    26-Jun-08    56.21     CIV/981


                      PIPE RACK (HOARDING
           CIV/982                        CONCRETE SLAB FOR METERING SKID       HANSON     29-May-08    G40(SM)            80      1-Jun-08      X          X      5-Jun-08       32.88    CIV/983    12-Jun-08   43.77     CIV/984    26-Jun-08    58.88     CIV/985
                             AREA)

                        STATION FILTER     PS-751, PS-752 SUPPORT FOR ROTARY
           CIV/986                                                              HANSON     29-May-08    G40(SM)            95      1-Jun-08      X          X      5-Jun-08       31.33    CIV/987    12-Jun-08    43.1     CIV/988    26-Jun-08    56.21     CIV/989
                         SEPARATOR         GAS METER

                        STATION FILTER
           CIV/990                         PRIOR CONCRETING TO PS-752-004-VS    HANSON     29-May-08    G40(SM)            95      1-Jun-08      X          X      5-Jun-08       31.33    CIV/991    12-Jun-08    43.1     CIV/992    26-Jun-08    56.21     CIV/993
                         SEPARATOR

                        STATION FILTER     PRIOR CONCRETING TO SUPPORT FOR
           CIV/994                                                              HANSON     29-May-08    G40(SM)            95      1-Jun-08      X          X      5-Jun-08       31.33    CIV/995    12-Jun-08    43.1     CIV/996    26-Jun-08    56.21     CIV/997
                         SEPARATOR         ROTARY GAS METER


           CIV/1005        RO AREA         CONCRETE PAVEMENT INSIDE RO          HANSON     10-Jun-08    G30(SM)            80     13-Jun-08      X          X      17-Jun-08       27.1    CIV/1006   24-Jun-08   39.33     CIV/1007    8-Jul-08    46.44     CIV/1008


           CIV/1009        RO AREA         CONCRETE PAVEMENT INSIDE RO          HANSON     23-Jun-08    G30(SM)            75     26-Jun-08      X          X      30-Jun-08      26.66    CIV/1010    7-Jul-08   35.33     CIV/1011   21-Jul-08    40.21     CIV/1012


                                           PRIOR CONCRETING TO CONCRETE
           CIV/1013     HOARDING AREA                                           HANSON      15-Jul-08   G30(SM)            95      18-Jul-08     X          X      22-Jul-08      30.88    CIV/1014   29-Jul-08   36.66     CIV/1015   12-Aug-08    43.99     CIV/1016
                                           PAVEMENT

                        STATION FILTER     CONCRETING TO MISC. SERVICE
           CIV/1017                                                             HANSON      15-Jul-08   G40N(SM)           80      18-Jul-08     X          X      22-Jul-08      30.88    CIV/1018   29-Jul-08   39.11     CIV/1019   12-Aug-08    47.11     CIV/1020
                         SEPARATOR         PLATFORM FOUNDATION

                      BUFFER AIR RECEIVER PRIOR CONCRETING TO PIPE SUPPORT
           CIV/1021                                                             HANSON      15-Jul-08   G40(SM)            80      18-Jul-08     X          X      22-Jul-08      30.88    CIV/1022   29-Jul-08   39.11     CIV/1023   12-Aug-08    47.11     CIV/1024
                             AREA         (1 NOS)


           CIV/1025    PIPE RACK RO AREA   SUPPORT FOR ROTARY GAS METER         HANSON      15-Jul-08   G40(SM)            80      18-Jul-08     X          X      22-Jul-08      30.88    CIV/1026   29-Jul-08   39.10     CIV/1027   12-Aug-08    49.11     CIV/1028


          CIV/1040F        RO AREA         PRECAST FOOTING R11 - 12 NOS         HANSON      8-Aug-08    G40(SM)            90     11-Aug-08      X          X      15-Aug-08      29.98   CIV/1030A   22-Aug-08   40.44    CIV/1030B   5-Sep-08     55.11    CIV/1030C


           CIV/1054        RO AREA         CONCRETE SFETY SHOWER SLAB           HANSON     11-Nov-08    G30N(SM)           80     14-Nov-08      X          X      18-Nov-08      30.44    CIV/1055   25-Nov-08   35.33    CIV/1055A   9-Dec-08     43.99    CIV/1055B


                                           CONCRETE CROSSING FOR LAYING RR
          CIV/1055D    ROAD AT RO AREA                                          HANSON     11-Dec-08    G30N(SM)           80     14-Dec-08      X          X      18-Dec-08      30.66   CIV/1055E   25-Dec-08   35.33    CIV/1055F   8-Jan-09     38.66    CIV/1055G
                                           CABLES

                         PIPE SINKING      CONCRETE FOR FOOTING (INCLUDING
           CIV/1063                                                             HANSON     20-Feb-09    G40N(SM)           80     23-Feb-09      X          X      27-Feb-09      31.56    CIV/1065   6-Mar-09    40.22     CIV/1066   20-Mar-09    44.00     CIV/1067
                         (DISCHARGE)       STUMP)




CONTRACTOR:SETMSB                                                                                                                                                                                                                                  153bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010
                    PIPE SINKING   CONCRETE FOR FOOTING (INCLUDING
        CIV/1064                                                       HANSON   20-Feb-09   G40N(SM)   80   23-Feb-09   X   X   27-Feb-09   31.56   CIV/1065   6-Mar-09    40.22   CIV/1066   20-Mar-09   44.00     CIV/1067
                     (SUCTION)     STUMP)


        CIV/1069    PIPE SINKING   CONCRETE PAVING (2 LOCATION)        HANSON   11-Mar-09   G30N(SM)   80   14-Mar-09   X   X   18-Mar-09   32.66   CIV/1065   25-Mar-09   40.44   CIV/1071   8-Apr-09    44.44     CIV/1072


        CIV/1073    AIR INTAKE     CONCRETE PAVING                     HANSON   11-Mar-09   G30N(SM)   80   14-Mar-09   X   X   18-Mar-09   31.99   CIV/1074   25-Mar-09   39.10   CIV/1075   8-Apr-09    43.77     CIV/1076


                                   CONCRETE 1" DRAIN LINE & CONCRETE
        CIV/1077    COMP.BLDG                                          HANSON   11-Mar-09   G30N(SM)   80   14-Mar-09   X   X   18-Mar-09   31.99   CIV/1078   25-Mar-09   39.10   CIV/1079   8-Apr-09    43.77     CIV/1080
                                   SLAB AT EXHAUST

                                   INSPECTION PRIOR CONCRETING OF
        CIV/1088    COMP.BLDG                                          HANSON   27-Apr-09   G40N(SM)   80   30-Apr-09   X   X   4-May-09    34.44   CIV/1089   11-May-09   39.77   CIV/1090   25-May-09   44.89     CIV/1091
                                   TRUNNION SUPPORT


                                                                                                                        X   X                       #VALUE!                        #VALUE!                          #VALUE!


                                                                                                                        X   X                       #VALUE!                        #VALUE!                          #VALUE!


                                                                                                                        X   X                       #VALUE!                        #VALUE!                          #VALUE!




CONTRACTOR:SETMSB                                                                                                                                                                                         163bb60a5f-8041-484a-b0dd-91c3c9283a10.xls2/16/2010

				