LIST OF PPP PROJECTS AWARDED DURING 2008-09 2009-10
Document Sample


LIST OF PPP PROJECTS AWARDED DURING 2008-09 & 2009-10
NHDP LOA
S.No. Name of the Project State Length(Km.) TPC(Rs. Cr) Contractor
Phase Issued
NHDP
1 Badarpur Elevated Highways Delhi/Haryana 4.4 340 Jun-2008 M/s BFTL
Phase V
NHDP M/s HCC -Laing-Sadbhav
2 MP/Maharashtra Border-Dhule Maharashtra 98 835 Jan-2009
Phase III Consortium
New 4-Lane Elevated Road from NHDP M/s Chennai Elevated
3 Tamil Nadu 19 1655 Jan-2009
Chennai Port - Maduravoyal Phase VII Tollway std
NHDP M/s L & T - ABL
4 Pimpalgaon - Nasik - Gonde Maharashtra 60 940 Jan-2009
Phase III Consortium
Six lanning of Vadakkancherry - NHDP M/s KMC- CR18G
5 Kerala 30 617 Feb-2009
Thrissuresection Phase II Consortium
Pune-Sholapur Pkg-I(Approved Length NHDP Navinya Buildcon-Atlantia
6 Maharashtra 110.05 1110 Feb-2009
Pkg I & II 170 Km) Phase III Spa(JV)
Gujarat/Maharashtra Border-Surat - NHDP Isolux-Soma Consortium
7 Gujarat 132.9 1509.1 Feb-2009
Hazira Port Section Phase III (JV)
NHDP M/s KMC - IVRCL
8 Cuddapah-Mydukur-Kurnool Andhra Pradesh 188.752 1585 Feb-2009
Phase III Consortium
NHDP M/s Isolux-Soma
9 Kishangarh-Ajmer-Beawar Rajasthan 82 795 Apr-2009
Phase III Consortium
NHDP GMR-Punj LLOYD
10 Hyderabad-Vijayawada Andhra Pradesh 181.63 1740 May-2009
Phase III Consortium
Armur to Kadloor Yellareddy (NS-2/AP-
NHDP M/s Navyouga KPCL
11 1) (Approved Length Andhra Pradesh 59 390.56 May-2009
Phase II Consortium
60.25)
4-lanning of Kannur Vengalem NHDP
12 Kerala 83.2 1366 Jul-2009 KMC Ltd
Kuttipuram (Package -I) Phase III
4-lanning of Kannur Vengalem NHDP
13 Kerala 81.5 1312 Jul-2009 KMC Ltd
Kuttipuram (Package -II) Phase III
LIST OF PPP PROJECTS AWARDED DURING 2008-09 & 2009-10
Amritsar - Pathankot (Approved Length NHDP
14 Punjab 106 705 Jul-2009 IRB-MRM Pvt Ltd.
101Km) Phase III
Pune-Sholapur Pkg-II(Approved Length NHDP IL & FS Transportation
15 Maharashtra 105 835 Aug-2009
I & II 170 Km) Phase III Network Ltd
Talegaon-Amravat(Approved Length NHDP
16 Maharashtra 67.8 567 Aug-2009 IRB-MRM Consortium
58Km) Phase III
Four laning from MP/Maharashtra
NHDP Oriental Structural
17 border to Nagpur I/C Kamptee Kanoon Maharashtra 95 1170.52 Aug-2009
Phase II Engineers Ltd.
and Nagpur bypass
NHDP
18 Hazaribagh-Ranchi Jharkhand 75 625.07 Aug-2009 ITNL-Punj Lloyd Ltd.(JV)
Phase III
Jaipur-Reengus(Approved Length 52.65 NHDP RIL-AAA- JTEG
19 Rajasthan 54 267.81 Oct-2009
Km ) Phase III Consortium
Jaipur-Tonk - Deoli(Approved Length NHDP
20 Rajasthan 150 792.06 Oct-2009 IRB-MRM Consortium
148.77 Km ) Phase III
Kundapur-Surathkal & Mangalore- NHDP Navayuga - KPCL
21 Karnataka 90 671 Nov-2009
KNT/Kerala Border Phase III Consortium
NHDP Gammon Infrastructure
22 Patna- Muzzaffarpur Bihar 63 671.3 Nov-2009
Phase III Ltd
Muradabad-Bareily (Approved Length NHDP IL & FS Transportation
23 Uttar Pradesh 121 1267 Dec-2009
112) Phase III Ltd.
Indore-Jhabua-Gujrat/MP (Approved NHDP IVRCL Infrastructure
24 Madhya Pradesh 155.15 1175 Dec-2009
Length 168) Phase III Projects Ltd.
Hyderabad-Yadgiri (Approved Length NHDP
25 Andhra Pradesh 35.65 388 Dec-2009 Sadbhav Engineering Ltd.
30) Phase III
Ghaziabad-Aligarh (Approved Length NHDP SREI - PNC - GALFAR
26 Uttar Pradesh 126 1141 Dec-2009
106 ) Phase III Consortium
Uttar
Muzaffarnagar - Haridwar (Approved NHDP
27 Pradesh[21]/Uttar 80 754 Dec-2009 ERA-SIBMOST
Length 77 ) Phase III
anchal[56]
Haridwar - Dehradun (Approved Length NHDP
28 Uttaranchal 39 478 Dec-2009 ERA - SIBMOST(JV)
69) Phase III
LIST OF PPP PROJECTS AWARDED DURING 2008-09 & 2009-10
NHDP
29 Gujarat 83.85 785
Godhra-Gujrat/MP Border Phase III 01.01.2010 BSCPL Infrastructure Ltd
NHDP
30 Haryana 80.86 807 Sadbhav Engineering Ltd.
Rohtak-Panipat Phase III 04.01.2010
NHDP
31 Goa 69 471 IRB MRM Consortium
Goa/KNT Border-Panji Phase III 05.01.2010
NHDP Isolux-Soma Consortium
32 Kerala 83.6 1535
Charthalai-Ochira Phase III 05.01.2010 (JV)
Changapali-Walayar Section(Excluding NHDP IVRCL Infrastructure
33 Tamil Nadu 54.83 852
coimbatore By Pass) Phase II Projects Ltd.
11.01.2010
NHDP ESSEL Infra Projects Ltd
34 Gujarat 117.6 1009
Ahmedabad-Godhra Phase III 11.01.2010 CRI8G Consortium
NHDP Reliance Infrastructure
35 Gujarat 71.4 953.88
Kandla Mundra Port Phase III 12.01.2010 Ltd
NHDP Reliance-JTEG
36 Maharashtra 140.35 1724.55
Pune-Satara Phase V 20.01.2010 Consortium
NHDP
37 Gujarat 56.16 805.39 Larsen & Toubro Ltd
Samakhiali-Gandhidham Phase V 20.01.2010