									   Minnesota Department of Transportation
   District 6
   Rochester, Owatonna & Winona

   2009 Regular Construction Projects
   Includes Chapter 152 Bond Funded Projects
1. Highway 14 in Steele County
Description: Grade and surface from Waseca County Road 5 to Steele County Road 7 and
construct the I-35/Hwy. 14 interchange. Project is about 14 miles.
Construction Dates: Phase 1: July 2009 – Nov. 2009 (3 year project)
Construction Estimate: $51,823,568
Traffic Impacts: Intermittent lane closures on Interstate 35 for 2009.
Status: Contract let on Jan. 23, 2009 – Mathiowetz Construction Co. (apparent low bidder)

2. Highway 30 in Dodge and Steele Counties
Description: Bituminous mill and overlay on Hwy. 30 from Blooming Prairie to Hayfield (Hwy. 218 to
Hwy. 56). Project is about 11 miles.
Construction Dates: May – June 2009
Construction Estimate: $1,858,438
Traffic Impacts: Daily lane closures with flaggers. Detour in effect during the railroad crossing
replacement work in Blooming Prairie.
Status: Contract let on Jan. 23, 2009 – Rochester Sand & Gravel/Division of Mathy Construction Co.
(apparent low bidder)

3. Highway 30 in Fillmore and Olmsted Counties
Description: Preventive maintenance – Bituminous mill and overlay on Hwy. 30 in Olmsted County
from the Root River Bridge to Hwy. 52. This project is tied to the overlay on Hwy. 52 for a total project
length of about 17 miles.
Construction Dates: July – Aug. 2009
Construction Estimate: $306,445
Traffic Impacts: Daily lane closures with flaggers.
Status: Contract to be let April 24, 2009

4. Interstate 35 in Rice County
Description: Bridge rehabilitation on ten bridges on Interstate 35 north and southbound lanes in
Faribault, from Rice County Road 48 to Hwy. 21. This project will be staged with the I-35 overlay
project, an American Recovery and Reinvestment Project.
Construction Dates: May – Sept. 2009
Construction Estimate: $8,222,358 (cost of both projects)
Traffic Impacts: Head to head traffic on southbound lanes, then head to head traffic on northbound
lanes.
Status: Contract let on March 27, 2009 – Crane Creek Asphalt/Division of Mathy Construction Co.
(apparent low bidder)

5. Interstate 35 in Steele County
Description: Unbonded concrete overlay, culvert replacements and guardrail work on Interstate 35
northbound lanes, from about a half miles north of Hwy. 30 to three miles south of Owatonna. Project
is about nine miles.
Construction Dates: July – Nov. 2009
Construction Cost: $9,402,700
Traffic Impacts: Head to head traffic on southbound lanes.
Status: Contract let on Feb. 27, 2009 – Ulland Brothers Inc. (apparent low bidder)



                                                 -more-
2009 Construction Projects (page 2)
6. Interstate 35 in Freeborn County
Description: Install six permanent variable message signs on Interstate 35 in various locations.
Construction Dates: July – Aug. 2009
Construction Cost: $119,142
Traffic Impacts: Intermittent shoulder closures
Status: Contract to be let on Feb. 27, 2009 – Mankato Electric, Inc. (apparent low bidder)

7. Interstate 35 in Freeborn County
Description: Signing upgrade for safety in various locations on Interstate 35 from Interstate 90 to
Hwy. 19.
Construction Dates: June 15 – Oct. 23, 2009
Construction Cost: $800,000
Traffic Impacts: Minimal traffic impacts
Status: Contract to be let on May 15, 2009

8. Highway 42 in Wabasha County
Description: Install wet reflective pavement markings on Hwy. 42 from Plainview to Kellogg. Project
is about 12 miles.
Construction Dates: May 2009
Construction Cost: $47,614
Traffic Impacts: Daily lane closures with flaggers.
Status: Contract let on Jan. 23, 2009 – Century Fence Co. (apparent low bidder)

9. Highway 52 in Fillmore County
Description: Bituminous mill and overlay on Hwy. 52, from Fountain (junction of Hwy. 80) to
Chatfield. Project is about 9 miles.
Construction Dates: May – July 2009
Construction Cost: $3,065,674
Traffic Impacts: Daily lane closures with flaggers. Detour in Fountain during culvert replacement.
Status: Contract let on Jan. 23, 2009 – Rochester Sand & Gravel (apparent low bidder)

10. Highway 52 in Olmsted County
Description: Bituminous overlay on Hwy. 52 in Olmsted County from Chatfield to Marion (I-90). This
project is tied to the mill and overlay on Hwy. 30 for a total project length of about 16 miles.
Construction Dates: July – Aug. 2009
Construction Estimate: $1,367,574
Traffic Impacts: Daily lane closures with flaggers.
Status: Contract to be let April 24, 2009

11. Highway 60 in Goodhue County
Description: Bituminous mill and overlay on Hwy. 60, from Kenyon to Zumbrota (north junction of
Hwy. 56 to Hwy. 52). Project is about 15 miles.
Construction Dates: July – Sept. 2009
Construction Cost: $3,297,589
Traffic Impacts: Daily lane closures with flaggers. A detour will be in effect between Kenyon and
Wanamingo during culvert replacement.
Status: Contract let on Jan. 23, 2008 – Mathy Construction Company (apparent low bidder)

12. Highway 60 in Goodhue and Rice Counties
Description: Bituminous mill and overlay on Hwy. 60, from the east end of the Straight River Bridge
to Huseth Ave. in Kenyon. Project is about 14 miles.
Construction Dates: May 2009
Construction Estimate: $1,107,038
Traffic Impacts: Daily lane closures with flaggers.
Status: Contract to be let Feb. 27, 2009 – Mathy Construction Company (apparent low bidder)

                                                -more-
2009 Construction Projects (page 3)
13. Highway 60 in Rice County
Description: Replace two bridges on Hwy. 60 over the Cannon River in Morristown.
Construction Dates: June – Sept. 2009
Construction Estimate: $1,773,086
Traffic Impacts: Traffic detoured – motorists should follow posted route.
Status: Contract let on Jan. 23, 2009 – Minnowa Construction, Inc. (apparent low bidder)

14. Highway 60 in Rice County
Description: Reconstruct the historic Viaduct Bridge over the Straight River in Faribault. The project
also includes grading, surfacing and widening the road in addition to curb and gutter work and signing
and lighting installation.
Construction Dates: Feb. – Oct. 2009
Construction Cost: $8,892,177
Traffic Impacts: Hwy. 60 will be closed from First Ave. to Sixth Ave. in Faribault. Detour is Ravine
Street and Sixth Ave.
Status: Contract let on Nov. 21, 2008 – Ames Construction is the prime contractor.

15. Highway 61 in Wabasha County
Description: Bituminous mill and overlay on Hwy. 61 northbound lanes from Winona to Kellogg
(Hwy. 14 to Hwy. 42) and southbound lanes from Hwy. 14 to Hwy. 248. Project is about 24 miles.
Construction Dates: May – Sept. 2009
Construction Cost: $6,797,553
Traffic Impacts: There will be a 10 calendar day detour for culvert replacements between 54th Ave
in Goodview and Winona County Road 32. Detour is 54th Ave. and County Road 32. The remaining
work will be completed under daily lane closures.
Status: Contract let on Jan. 23, 2009 – Knife River Corporation – North Central (apparent low
bidder)

16. Highway 63 in Olmsted County
                                                                       th
Description: Widen southbound ramp and construct right turn lane at 48 Street South in Rochester
Construction Dates: July 2009
Construction Cost: $250,000
                   th                                                     th
Traffic Impacts: 48 Street South exit ramp closed. Traffic detoured on 40 Street SW and St.
Bridget’s Road.
Status: Contract to be let on April 24, 2009

17. Interstate 90 in Mower County
Description: Preventive maintenance – concrete pavement rehabilitation on Interstate 90 eastbound
lanes from Mower County Road 19 to Hwy. 16 in Dexter. Project is about eight miles.
Construction Dates: May – July 2009
Construction Estimate: $1,697,445
Traffic Impacts: Long term lane closures.
Status: Contract let on March 27, 2009 – Interstate Improvement, Inc. (apparent low bidder)

18. Interstate 90 in Winona County
Description: Bituminous overlay on Interstate 90 westbound lanes from Hwy. 43 to Hwy. 76. Project
is about eight miles.
Construction Dates: May – June 2009
Construction Cost: $2,663,563
Traffic Impacts: Long term lane closures.
Status: Contract to be let Feb. 27, 2009 – Dunn Blacktop CO/Division of Mathy Construction
(apparent low bidder)




                                               -more-
2009 Construction Projects (page 4)
19. Interstate 90 in Winona County
Description: Replace four bridges on Interstate 90 at Dresbach Township (just southeast of the
north junction of Hwy. 61).
Construction Dates: May – Nov. 2009 (will continue next year)
Construction Cost: $4,393,797
Traffic Impacts: Head to head traffic on eastbound lanes.
Status: Contract let on March 27, 2009 – Lunda Construction Co. (apparent low bidder)

20. Interstate 90 in Olmsted County
Description: Replace signs in various locations on Interstate 90 from Hwy. 63 to the Wisconsin
border.
Construction Dates: May – June 2009
Construction Cost: $777,233
Traffic Impacts: Minimal traffic impacts.
Status: Contract let on Jan. 23, 2009 – H&R Construction Co. (apparent low bidder)

21. Highway 218 in Mower County
Description: Traffic signal installation at Interstate 90 (Hwy. 218 north ramp).
Construction Dates: June 2009
Construction Estimate: $108,600
Traffic Impacts: Minimal traffic impacts
Status: Contract let Jan. 23, 2009 – Nietz Electric Inc. (apparent low bidder)

22. Various highways in District 6
Description: Install centerline and shoulder rumple strips in various locations.
Construction Dates: Aug. 2009
Construction Cost: $162,511
Traffic Impacts: Daily lane closures with flaggers
Status: Contract let Jan. 23, 2009 – Century Fence Co. (apparent low bidder)

23. Various highways in District 6
Description: Install intersection lighting at 27 intersections in various locations.
Construction Dates: Aug. – Sept. 2009
Construction Cost: $325,222
Traffic Impacts: Minimal traffic impacts
Status: Contract let on Jan. 23, 2009 – Affordable Electric of Roseau, Inc. (apparent low bidder)

24. Various highways in District 6
Description: Guardrail end treatment improvements in various locations.
Construction Dates: Sept. – Oct. 2009
Construction Cost: $695,000
Traffic Impacts: Minimal traffic impacts.
Status: Contract to be let on May 15, 2009

25. Various highways in District 6
Description: Preventative maintenance - bituminous pavement crack treatment in various locations.
Construction Dates: May 2009
Construction Cost: $173,080
Traffic Impacts: Daily lane closures.
Status: Contract let on Feb. 27, 2009 – Interstate Improvement Inc. (apparent low bidder)

26. Various highways in District 6
Description: Install radio towers for Group D.
Construction Dates: April - June 2009
Construction Cost: $2,000,000
Traffic Impacts: Minimal traffic impacts.
Status: Contract letting TBD
                                                 - more -
2009 Construction Projects (page 5)
27. Various highways in District 6
Description: Rehabilitate 46 bridges in Dodge, Fillmore, Goodhue, Mower, Olmsted, Wabasha and
Winona counties.
Construction Dates: Aug. – Sept. 2009
Construction Cost: $180,000
Traffic Impacts: Temporary lane closures.
Status: Contract to be let on May 15, 2009


Carryover projects
28. Highway 61 in Houston County
Description: Preventive Maintenance – Concrete pavement rehabilitation, plane, replace shoulders,
reseal joints and fix guardrail on Hwy. 61 from Fourth St. in La Crescent to the junction of I-90.
Construction Dates: May – June 2009
Total Construction Cost: $687,488
Traffic Impacts: Traffic will be restricted to one lane in each direction with long term lane closures.
Status: Contract was let on March 23, 2007 – Mathy Construction Company is the prime contractor.

                                                 ###

								
To top