					               FP420 Manchester Workshop
                          December 2006


  FP420 Connection Cryostat
Mechanical Design & Construction



               Key capabilities of
               CERN TS/MME




                Thierry RENAGLIA / Ramon FOLCH
                      FP420 Connection Cryostat
Mechanical design & construction
Key capabilities of CERN TS/MME         CONTENT

  1. DESIGN                              2. CONSTRUCTION
     FP420 versus DFB ATM                  Main processes involved
     Pre-design Version #1                 Schedule and possible lead times
     Pre-design Version #2                 Cost drivers
     Mechanical analysis                   DFB ATM assembly experience
     Pre-design Version #3
     Open issues




                  3. CONCLUSION
                     Advantages with CERN TS/MME
                     Required framework conditions


                FP420 Manchester Workshop - December 2006              2 / 23
                     FP420 Connection Cryostat
FP420 versus DFB ATM

   Continuity of the X and C lines
   Higher contraction of the busbar lines
   Fixed point to be relocated
   Longer interconnection bellow length
   Detector constraints (accessibility, precision)
   Radiation shielding
                                                         Distribution
                                                                Feed
                                                                 Box

                                          Arc
      FP420                               Termination
      Cryostat                            Module
                 FP420 Manchester Workshop - December 2006              3 / 23
                  FP420 Connection Cryostat
Pre-design Version #1
   Dipole cold foot to replace compensation system
   Couple two DFB ATM
   Allow contraction of the BB line




              FP420 Manchester Workshop - December 2006   4 / 23
                 FP420 Connection Cryostat
Pre-design Version #2

   Redesigned supporting beam
   Double cold feet to free space for line X




             FP420 Manchester Workshop - December 2006   5 / 23
              FP420 Connection Cryostat
Version #2 – Displacement analysis
      VACUUM CONDITION




          FP420 Manchester Workshop - December 2006   6 / 23
                 FP420 Connection Cryostat
Version #2 – Displacement analysis
     VACUUM CONDITION + INTERCONNECTION at cold (operation conditions)




            FP420 Manchester Workshop - December 2006                    7 / 23
                        FP420 Connection Cryostat
Version #2 – Reaction analysis

             Cold condition
             (vacuum, bellow force)


  Bellow
   force
- 10’000 N




                                                                        Reaction y
                                                                        55’000 N




                                 Reaction z             Reaction z
                                 70’000 N               - 32’500 N

                  FP420 Manchester Workshop - December 2006          8 / 23
                FP420 Connection Cryostat
Pre-design Version #3

   Two lowered supporting beams
   One single piece




            FP420 Manchester Workshop - December 2006   9 / 23
                 FP420 Connection Cryostat
Version #3 – Open issues & next steps

   Detector supported by the cryostat: need to
    deal with movements during cooling down
    and operation
   Need of additional central fixed point and
    supporting jack
   Use the transport buggies and the lifting
    beams of the DFBAs
   Pre-design v#3 approval awaited




             FP420 Manchester Workshop - December 2006   10 / 23
                 FP420 Connection Cryostat
Construction – Processes involved

   Machining (both heavy and accurate)
   Sheet metal forming (vacuum tanks, piping)
   MIG/TIG welding
   Thermal treatments / Surface treatments
   Mechanical fitting (Beam screen integration)
   Metrology / Alignment
   Vacuum test / x-Ray inspection
   Thermal super-insulation
   Electrical insulation assembly and test

             FP420 Manchester Workshop - December 2006   11 / 23
                              FP420 Connection Cryostat
Schedule projection attempt

                               2007                             2008                    2009
                   J   F M A M J J    A S O N D     J   F M A M J J    A S O N D   J     F M
Project Approval

Design

Engineering

Construction

Installation




       Green light needed                    The production
       on time to allow the                cannot start before
       design work to start                 the design is fully
                                                approved


                        FP420 Manchester Workshop - December 2006             12 / 23
                     FP420 Connection Cryostat
Cost drivers – What helps cutting them

   Re-use existent designed parts (cold feet, jacks, dished heads, etc)
   Experienced and multi-skilled workforce
   Avoid specific tooling
   Optimize the logistics between operations



                                     Material

                                     Production

                                     Assembly&cleaning

                                     Tests




                 FP420 Manchester Workshop - December 2006      13 / 23
                      FP420 Connection Cryostat
CERN TS/MME experience on DFB ATM

   Design and mechanical analysis
   Full production and assembly of 16 ATM
   Budget and time constraints sealed in a
    interdepartmental workpackage agreement
                                       Units
                                                                                       E
                                        14

                        Distribution    13
                                        12
                                                                               CD
                                                                                                             Results:
                               Feed     11
                                                                          MB                               Early deliveries
                                Box     10
                                                                      L
                                                                                                           and costs below
                                         9
                                         8                        K                                       expectations after
                                                                GJ
                                         7                                                                  the 3 first units
                                         6
                                         5                  F
                                                           HI
                                         4
    Arc                                  3
                                                       PA                                            ATM delivery
    Termination                          2
                                                                                                     DFBA schedule
                                         1
    Module
                                               J   F   M    A    M    J   J    A   S   O   N   D   2006




                  FP420 Manchester Workshop - December 2006                                                          14 / 23
            FP420 Connection Cryostat
Shuffling Box assembly




        FP420 Manchester Workshop - December 2006   15 / 23
            FP420 Connection Cryostat
Welding of the dished heads




        FP420 Manchester Workshop - December 2006   16 / 23
            FP420 Connection Cryostat
Cryostating of the Shuffling Module




        FP420 Manchester Workshop - December 2006   17 / 23
            FP420 Connection Cryostat
Thermal Super-insulation




        FP420 Manchester Workshop - December 2006   18 / 23
            FP420 Connection Cryostat
Final assembly




        FP420 Manchester Workshop - December 2006   19 / 23
           FP420 Connection Cryostat
DFBA (ATM & HCM) Transport




       FP420 Manchester Workshop - December 2006   20 / 23
                     FP420 Connection Cryostat
Conclusions

   Advantages with CERN/TS/MME
    –   Design and construction synergy benefits
    –   Shortened learning curve (skilled resources and appropriate
        equipment available)
    –   Highly responsive multi-technological environment
    –   Reduction of the logistics time and cost
    –   Design and construction traceability (CDD/ EDMS / MTF)


   Required framework conditions
    –   Obtain the formal approval of the pre-design
    –   Obtain the final version of the technical specification
    –   Adopt a workpackage oriented approach combining the
        mechanical design and the construction
                 FP420 Manchester Workshop - December 2006        21 / 23
     FP420 Connection Cryostat




                                                     The CERN TS/MME
                                                Mechanical and Materials
                                                     Engineering group
                                                             received the
                                                  Golden Hadron Award
                                                     (LHC best suppliers)




               Fair and efficient partnership
                 with CERN Member States
                      (here: December
FP420 Manchester Workshop - Bulgaria) 2006              22 / 23
                    FP420 Connection Cryostat
Thanks for their contribution …
   Utilisation des ATM pour le projet FP420 - EDMS 771549 –
    Thierry Renaglia
   Use of the ATM for the FP420 Project EDMS 743628 –
    Thierry Colombet
   General information from the TS/MME ATM assembly team
    (Said Atieh, Laurent Préver-Loiri, Didier Lombard, and al.)




    …and thanks for your attention.


                FP420 Manchester Workshop - December 2006     23 / 23