									Meeting of Avon Primary Care Support Agency Management Board – 24 January 2007: Agenda Item 7

Risk Register – Operational Services
All risks reported to APCSA Board have a risk assessment score greater than 9. Risks that have risk protection action completed are not reported
JC - Julie Cooper, DM - Declan McLaughlin, VV - Val Veysey, EG - Eileen Grindey, DW Denise Williams, PS – Phil Shrimpton, SG-Sue Graham

General
Description of Risk Action to be taken Old Assessment Score as at 10.11.06 9 Probability /Likelihood as at 12.01.07 Possible (3) Consequences /Impact as at 12.01.07 Major (3) Assessment Priority Lead Score as at Rating as Manager 12.01.07 at 12.01.07 9 Medium JC Target Date Completed

Access to PCSA by unauthorised personnel (eg. Break In) that could lead to breach of patient/contractor confidentiality or loss of paper based information. NB. Copies of contractor qualifications and passports are held in filing cabinets Loss of key systems, e.g. through IT failure/software supplier failure (not Exeter System) e.g. Unable to access internet to make pharmacy/ophthalmic payments

Request Landlords of the building to assess ways in which security of the building can be improved. A person has been charged with two previous break-ins. Consider purchasing ‘locking cabinets’ and ‘smart water’

Ongoing

Avon IM&T Consortium 12 responsible for business continuity planning in place for KSH. Would need to access internet via another source e.g. Another PCT base. Agreement with South Gloucestershire PCT to access internet from their base.

Possible (3) Major (3)

9

Medium

JC

March 07

Board Paper Page 1 of 4

Meeting of Avon Primary Care Support Agency Management Board – 24 January 2007: Agenda Item 7

Failure of mailing machine

PCT’s do not wish APCSA to work collaboratively across health community

Insufficient System Documentation about internally developed procedures. This is not a problem while staff that developed the procedures are still in post, but is a problem if those staff leave the Agency Staff shortages – and inability to Multi-skilling & prioritisation 12 employ commercial agency staff Agency will have to assess and no availability of Bank staff services that cannot be provided and advise PCTs Excess demand Monitor demand and identify 9 risk areas may result in reduced ability to satisfy customer demand – unmet targets

Disaster recovery suite available at NHS Connecting for Health (NHSCFH). Avon IM&T have provided a solution for access to the Exeter System and has been successfully tested. Now working with the NHSCFH to secure BACS process can be run without KSH IT Network. Ensure maintenance agreement 9 in place with PFE, maintenance agreement gives 1 day call out. Use alternative machine in Patient Data/Child Health PCT responsibility additional 9 costs may be incurred as a result. PCTs should discuss at Board meetings. Many procedure notes already 9 documented. Ensure they are regularly reviewed.

Possible (3) Major (3)

9

Medium

DW

April 05

Possible (3) Major (3)

9

Medium

JC, DM, VV, EG, DW, PS JC, DM, VV, EG, DW, PS Ongoing Ongoing

Possible (3) Major (3)

9

Medium

Probable (4)

Major (3)

12

High

JC, DM, VV, EG, DW, PS JC, DM, VV, EG, DW, PS Ongoingregular Managers meeting to assess situation

Possible (3) Major (3)

9

Medium

Board Paper Page 2 of 4

Meeting of Avon Primary Care Support Agency Management Board – 24 January 2007: Agenda Item 7

Finance
Knowledge held by an individual is lost should the individual leave. Cover is also needed for unexpected sickness Procedure notes to be written as soon as processes are simplified. Ensure procedure notes are tested and another member of staff trained in their use. Bristol South & West Finance Team have successfully covered position during long term sickness 9 Possible (3) Major (3) 9 Medium EG, JC September 04 February 05

Contracts
A PCT is unable to provide Clinical Governance Managers authorisation of now administer process within references/decision making due PCTs to clinical governance lead being unavailable. Could result in not being approved to practise and result in loss of earnings 9 Possible (3) Major (3) 9 Medium VV September 05 November 05

Board Paper Page 3 of 4

Meeting of Avon Primary Care Support Agency Management Board – 24 January 2007: Agenda Item 7

The Assessment Score
Probability/Likelihood

Certain = 5

5

Act soon 10 Act soon 8 6

Act now 15 Act soon 12 Act soon 9 6

Act now 20 Act now 16 Act soon 12

STOP 25 Act now 20

Probable = 4

4

Possible = 3

3

Act now 15 Act soon 10 5

Improbable = 2

2

4

Act soon 8 4

Remote = 1

1

2

3

Trivial = 1

Minor = 2

Major = 3

Severe = 4

Fatal = 5

Consequences/severity

Board Paper Page 4 of 4


								