PERT CPM CHART OF PERT
Document Sample


PERT / CPM CHART OF
CIVIL DIVISION GLADA, LUDHIANA
BUILDING WORK
Sr. Name of work Estimat- Preparati Time for Floating of Time for Time for T/ App. Issuing Time of Time for Found- Super- Comp- Time of Remarks.
No. ed cost on & Estimate. scheme Admn. S of DNIT of offer Tenderin Allot-ment ation structure letion final
(Rs. in approval App. L.O.I. g finishing
lacs) of with E.M (Receipt)
Drawing 30.11.08
s.
1. 2. 3. 4. 5. 6. 7. 8. 9. 10 11 12 13 14 15 16 17
1. Construction of 380 LIG 1700.00 30.9.08 15.10.08 31.10.08 31.10.08 15.11.08 15.11.08 30.11.08 10.12.08 20.12.08 31.3.09 31.11.09 31.3.10 31.5.10
Sector-40, Ludhiana.
2. Const.of 400 LIG Urban 1800.00 30.9.08 15.10.08 31.10.08 31.10.08 15.11.08 15.11.08 30.11.08 10.12.08 20.12.08 31.3.09 31.11.09 31.3.10 31.5.10
Estate Dugri Ph-II, Ldh.
3. Const. of 150 MIG U/E 1500.00 30.9.08 15.10.08 31.10.08 31.10.08 15.11.08 15.11.08 30.11.08 10.12.08 20.12.08 31.3.09 31.12.09 30.6.10 31.7.10
Dugri Ph-II.
4. Const. of Senior Citizen 15.00 14.8.08 31.8.08 15.9.08 22.9.08 22.9.08 15.10.08 31.10.08 30.11.08 15.2.08 15.3.09 31.3.09
Club U/E, Dugri Ph-II
5. Const. of Senior Citizen 15.00 31.8.08 15.9.08 30.9.08 10.10.08 10.10.08 31.10.08 15.11.08 15.12.08 28.2.08 31.3.09 15.4.09
Club U/E Dugri Ph-I.
6. Const. of CA’s residence in 85.00 31.7.08 7.8.08 14.8.08 21.8.08 21.8.08 15.9.08 30.9.08 31.10.08 31.1.09 15.3.09 31.3.09
U/E, Dugri Ph-I
7. Const. of Guest House U/E 80.00 31.7.08 7.8.08 14.8.08 21.8.08 21.8.08 15.9.08 30.9.08 30.11.08 31.3.09 31.5.09 30.6.09
Dugri Ph-II.
PERT / CPM CHART OF
CIVIL DIVISION GLADA, LUDHIANA
ON GOING BUILDING WORKS.
Sr. Name of work Estimated Preparation Time for Time for Allotment Found- Super Completion Date of Remarks.
No. cost & approval Estimate Technical No./ Dt. ation Structure final
(in lacs) of Sanction finishing
Drawings
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12.
1. Construction of various component of 82.14 - - - 549-57 31.7.08 30.9.08 31.10.08 13.11.08
Cremation Ground in Urban Estate, Dt.14.3.08
Phase-II, Dugri Raod, Ludhiana.
PERT / CPM CHART OF
CIVIL DIVISION GLADA, LUDHIANA
ROADWORKS.
Sr. Name of work Estimate Time Time for Time for Approval of Time of Time for Earth Consoli- B.M. & Time for Remarks.
No. d cost (in for Admn. Technical DNIT Tendering Allotment work dation P.C completio
lacs) Estimate Approval Sanction (Receipt) n
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14
1. Laying P.C. on 200’bye-pass U/ 40.00 31.9.08 16.10.08 31.10.08 7.11.08 30.11.08 7.12.08 - 31.12.08 28.2.09 31.3.09
E Ph-II & III, Dugri Road, Ldh.
2. Providing P.C. repair of Kerb 60.00 31.7.08 10.8.08 21.8.08 21.8.08 15.9.08 25.9.08 - 30.9.08 30.10.08 15.11.08
Channel Painting in commercial
pocket phase-I, D/R Ldh.
3. Providing P.C., repair of Kerb 45.00 16.8.08 23.08.08 31. 08.08 31.8.08 21.9.08 30.9.08 - 15.10.08 30.11.08 30.11.08
Channel & Painting in
commercial pocket phase-II, D/
R Ldh.
4. Dev.of commercial pocket 50.00 31.7.08 16.08.08 31.8.08 7.9.08 30.9.08 7.10.08 15.11.08 31.12.08 31.3.09 31.3.09
200’ Bye-Pass bye-pass
5. Dev.of commercial pocket 50.00 31.8.08 15.09.08 30.9.08 30.9.08 21.10.08 31.10.08 28.2.09 31.3.09 30.4.09 30.4.09
opposite M.S.Flats in Sect-38.
6. Dev.of Commercial pocket ph- 23.00 - - 31.7.08 31.7.08 21.8.08 31.8.08 - 30.9.08 31.10.08 31.10.08
III, (Exhibition Ground)
7. Dev. of commercial pocket 27.00 31.8.08 15.9.08 30.9.08 30.9.08 21.10.08 31.10.08 28.2.09 31.3.09 30.4.09 30.4.09
Sect-39, (opposite Convent
School)
8. Dev. of service lane for 18.00 31.7.08 7.8.08 14.8.08 14.8.08 10.9.08 15.9.08 - 30.9.08 31.10.08 31.10.08
commercial plot no. 1 to 6
Ferozepur Road, Ldh.
9. Providing pavers, replacing 25.00 15.8.08 20.8.08 25.8.08 31.8.08 30.9.08 10.10.08 15.11.08 - - 28.2.09
damaged kerbs/paint and
restoration of berms etc Sec-32-
A, Ldh.
-2-
Sr. Name of work Estimate Time Time for Time for Approval of Time of Time for Earth Consoli- B.M. & Time for Remarks.
No. d cost (in for Admn. Technical DNIT Tendering Allotment work dation P.C completio
lacs) Estimate Approval Sanction (Receipt) n
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14
10. Construction of second lane of 40.00 25.8.08 31.8.08 10.9.08 20.9.08 20.10.08 31.10.08 15.12.08 15.1.09 31.3.09 15.4.09
80’ wide road Sect-39-A, Ldh.
11. Providing B.M. & P.C., repair 85.00 30.8.08 15.9.08 15.9.08 15.9.08 7.10.08 15.10.08 - - 31.10.08 15.11.09
of foot path & kerb & channels
etc Sect-39-A (existing roads)
12. Providing BM & PC on 80’ 25.00 15.8.08 21.8.08 31.8.08 31.8.08 20.9.08 30.9.08 - - 31.10.08 31.10.08
wide road sect-39-A
13. Maintenance & upkeep of 496 20.00 20.8.08 30.8.08 10.9.08 20.9.08 20.10.08 15.11.08 - - - 31.3.09
MIG houses Sect-32
PERT/CPM CHART OF ELECTRICAL DIVISION GLADA LUDHIANA.
Sr.No. Name of Work Estimated Time for Time for Time for Time for Time for Time for Remarks
Cost Estimate Admn. Technical Tendering Allotment Completion
Approval Sanction
1. Providing Air Cooling in PUDA Office 10.00 Lacs 11.07.2008 20.07.2008 15.07.2008 30.07.2008 15.08.2008 15.10.2008
Complex F/R Ludhiana.
2. Dev. Of Commercial pocket along 80’ 52.60 Lacs --- 11.07.2008 05.08.2008 18.08.2008 28.08.2008 15.05.2009 Subject to
wide road Opp. B.C.M School Sector-32- Approval From
A S/R Ludhiana. P.S.E.B.
3. Mast System in commercial pocket 15.00 Lacs --- 30.07.2008 15.08.2008 30.08.2008 15.09.2008 15.01.2009
abutting Chandigarh Road in Sector-32-
A S/R Ludhiana.
4. Replacement of 40 watt fitting with 70 2.50 Lacs 01.08.2008 11.08.2008 21.08.2008 06.09.2008 21.09.2008 06.12.2008
watt fitting in Sector-33 S/R Ludhiana.
5. Dev. Of Commercial pocket along 55.83 Lacs --- 11.07.2008 05.08.2008 18.08.2008 28.08.2008 15.05.2009 Subject to
Chandigarh Road Sector-38 S/R Approval From
Ludhiana. P.S.E.B.
6. Dev. Of Commercial pocket Sector-39, 10.00 Lacs 10.08.2008 21.08.2008 01.09.2008 01.10.2008 16.10.2008 16.07.2009
S/R (Opp. Convent School) Ludhiana.
7. Const. of Internal Road in Sector-39-A 25.50 Lacs --- --- 15.08.2008 30.08.2008 15.09.2008 25.03.2009
S/R Ludhiana.
8. Replacement of 40 watt fitting with 70 5.00 Lacs 01.08.2008 11.08.2008 21.08.2008 06.09.2008 21.09.2008 06.12.2008
watt fitting in Sector-40 S/R Ludhiana.
9. Prov. Air Condition in Community 10.00 Lacs 20.08.2008 30.08.2008 10.09.2008 10.10.2008 25.10.2008 04.04.2009
Centre Phase-IV Dhandhari Kalan,
Ludhiana.
10. Dev. Of Crematorium Ground Phase-2 4.00 Lacs --- --- 01.08.2008 01.08.2008 05.08.2008 15.03.2009
Dugri Road Ludhiana.
11. Prov. Air Condition of Community 15.00 Lacs 31.07.2008 10.08.2008 20.08.2008 20.09.2008 05.10.2008 04.01.2009
Centre Phase-2 Dugri Road Ludhiana.
12. Dev. Of Residential plot Phase-3 Dugri 16.00 Lacs --- --- 05.08.2008 18.08.2008 28.08.2008 15.05.2009 Subject to
Road Ludhiana. Approval From
P.S.E.B.
13. Replacement of 40 watt fitting with 70 11.00 Lacs 15.08.2008 25.08.2008 10.09.2008 10.10.2008 25.10.2008 25.12.2008
watt fitting in Phase-3 Dugri Road
Ludhiana.
PERT/CPM CHART OF PUBLIC HEALTH DIVISION GLADA LUDHIANA
Sr. Name of work Estimated Time for Time for Time for Approval Time of Time for Time for Remarks
No cost (In Estimate Approval technical of DNIT tendering Allotment complectio
lacs) sanction n
1 Prov. Estate Water Supply, 27.43 - Admn approval 15.08.2008 DNIT 06.08.2008 21.08.2008 31.01.2009
Sewerage & Storm Swer In accorded approved
residential plots in Urban
Estate Phase-III Dugri
Road, Ludhiana
2 Prov. Estate Water Supply, 27.17 - Admn approval 31.08.2008 - - Work 30.09.2008 Work out side the
Sewerage & Storm Swer In accorded alloted pockjet is linked with
Commerical pocket at widening of 100' wide
Dhandhra Road in Urban road
Estate Phase-I Dugri Road,
Ludhiana
3 Prov. Estate Water Supply, 29.38 - Admn approval 20.08.2008 DNIT 06.08.2008 21.08.2008 20.10.2008
Sewerage & Storm Swer In accorded approved
Sector-38 Samrala Road
Ludhiana
4 Prov. Estate Water Supply 27.12 - Admn approval 31.08.2008 - - Work 31.10.2008 Work could not be
& Sewerage In Sector-39- accorded alloted started due to
A Samrala Road Ludhiana nonavailbility of
compacted berms
Divisional Engineer (P.H)
GLADA,Ludhiana