Wind power on roofs
Document Sample


M
Structural design ideas
30 Winter 2005/6
Ecological design features
Winter 2005/6 31
Project team & contributors to
this article
www.ecoarc.co.uk
Conclusion
www.greenoakcarpentry.co.uk
32 Winter 2005/6
BFF 03/05
White
Death!
34 Winter 2005/6
Winter 2005/6 35
36 Winter 2005/6
Contaminated land officers have joined planning,
Health and Safety Executive, Environment Agency
and primary care trust representatives and specialist
consultants to find remediation solutions for a ‘grossly
contaminated’ factory site.
The working group has been formed in response to
Countryside Properties’ application to build 650 houses
plus offices and community facilities at the former
Turner and Newall asbestos factory, Rochdale. The
application, filed last December, is held in abeyance for
failing to fully investigate contamination of the site.
Planners have divided the 72 acres into an area of
opportunity, based on the footprint of the old factory,
and adjoining woodland. The HSE says there are
hotspots of up to 100 per cent asbestos contamination
in dumps in the woods but the application does not
include the wooded area.
Surface contamination including visible asbestos,
contaminated rubble from demolished buildings and
asbestos in remaining buildings complicate the situ-
ation, not to mention former coal mines, at least one
filled with asbestos.
Rochdale MBC’s chief planner Ken Smith said there
were questions about the methodology as well as
the extent of the land investigations. ‘We didn’t have
the specialist knowledge within the council to be able
to properly assess the planning application,’ he said.
‘Even if we felt the extent of investigation had been
dealt with we’d still look for specialist advice.’
The council drafted in contaminated land consultants
Atkins Global this April to analyse relevant risk assess-
ments and best practice. Contaminated land officer
Mark Brown said: ‘We need strong technical back up.
No-one’s made a decision that it’s impossible.
‘It’s not the level of contamination it’s the level of risk to
those who use it. The whole issue is about adequately
understanding the site to make an assessment of the
actual risks.’ The consultants are expected to report
next month.
HSE principal inspector Anna Bliss, of the Greater
Manchester construction team, said the last attempt
to improve the site had not succeeded: ‘Because it was
so steep it was very difficult work,’ she said. ‘As they
took some off the surface more was coming through.
‘It’s not helpful to dig around, what we need is the big
solution. At the moment we’re not able to put people’s
minds at rest but we’re working towards it.’
Sheila Will, Rochdale PCT’s director of public health,
added: ‘One of the things that makes the site unique
is that it’s a wild environment, and how we manage
that is really important. We must not increase the risk.’
Marie-Claire Kidd
Working group meeting the
press at Rochdale MBC.
Winter 2005/6 37
38 Winter 2005/6
Winter 2005/6 39
www.rics.org/greenvalue
40 Winter 2005/6
42 Winter 2005/6
Winter 2005/6 43
44 Winter 2005/6
Winter 2005/6 45
Olwyn
46 Winter 2005/6
Winter 2005/6 47
48 Winter 2005/6
Winter 2005/6 49
50 Winter 2005/6
Winter 2005/6 51
www.dti.gov.uk/
renewables/technologies/windspeed
www.windandsun.co.uk
52 Winter 2005/6
Winter 2005/6 53
54 Winter 2005/6
Winter 2005/6 55
Key
Fig.1.
56 Winter 2005/6
Winter 2005/6 57
58 Winter 2005/6
Get documents about "