DorsetPCT weekly report 111007
Document Sample


Early Adopter Dorset PCT Summary Care Records
Project Progress Report
Project Title Dorset PCT Summary Care Records Early Adopter
Project Manager Cat Smith
Report Editor - Name Cat Smith
Period Starting 10/3/2007 Period Ending 10/16/2007
Project Status Summary
Overall status rationale
Summary
Re-planning activity now complete and non-EMIS sites have been brought forward and are being
engaged currently.
Wave 2 patient drop in sessions continuing due to complete 20th October
Amber
Patient response to HealthSpace is still proving positive with over 210 people having registered at the
front office sessions.
Engagement event took place on 3rd Octover for future Wave's - postive response overall
Further Engagement event currently being organised for 7th November for South and East Dorset sites
Core Aspect RAG Ratings
Dimension Previous Period Current Period Reasoning
Engagement Engagement event held 3rd October. Further one being
arranged for 7th November. Currently engaging with non
EMIS sites to bring forward those deployments - 5 out of 8
Green Green approached.
Dorchester A&E lead seems positive and has agreed to
attend project board from next week. Further CSA work
underway
Communications Wave 2 patients drop in sessions have commenced with
high attendance for both SCR and HealthSpace
Amber Green applications. Wave 3 mail out planned for 12th November
with Wave 4 following in early December and Wave 5 in
early January.
Data Quality All Wave 1 sites have been audited and completed for
Data Quality. Second lot of auditing at Wave 2 now
commenced, most practices booked in.All Wave 2 sites
green. The original Dorchester Wave 3 sites have - 7 of
12 practices have green e-audit, however the newly
Red Red identified Wave 3 Non-EMIS sites have yet to have DQF
visits. Paperlight accreditation process review meeting
took place Tuesday 25th.
Currently no DQF in Dorset - interviews held 20th
September unsuccessful, further interviews to be
arranged. Urgent requirement now for DQF.
Business Processes PCT currently looking for resource to provide support to
PM for this role. Job description has been written and
provided to Director of IT. Further discussions had at
project board 15th August. Director of IT to review
Amber Green
resources available within PCT to fill this role. To be raised
at board on October 17th. Trainers are now carrying out
business process training to Wave 1 and Wave 2 sites
where required.
IT & Security Green Green To be reviewed
Benefits PCT currently looking for resource to provide support to
PM for this role. Benefits meeting took place Tuesday 2nd
October to review Benefits identified to date and
Green Green discussion to be held at project board on 17th October.
Resources Job description written and provided to PCT's Director of
IT for Change management role (benefits and process
mapping). Project support role to be advertised
externally.PM currently fulfilling support role. No DQF for
Amber Red
Dorset currently. Comms work is being completed by PM
also and requirement for support to take on some of that
work
Training All Wave1 and 2 training complete. Wave 3 sites are
Green Green
currently booking training.
Status Report Template v1.0 1 12/25/200912:38 AM