							   Early Adopter           Dorset PCT Summary Care Records
   Project Progress Report

             Project Title    Dorset PCT Summary Care Records                               Early Adopter
         Project Manager      Cat Smith
     Report Editor - Name     Cat Smith
          Period Starting     10/3/2007         Period Ending 10/16/2007
   Project Status Summary
                       Overall status rationale
                       Summary

                       Re-planning activity now complete and non-EMIS sites have been brought forward and are being
                       engaged currently.
                       Wave 2 patient drop in sessions continuing due to complete 20th October
         Amber
                       Patient response to HealthSpace is still proving positive with over 210 people having registered at the
                       front office sessions.
                       Engagement event took place on 3rd Octover for future Wave's - postive response overall
                       Further Engagement event currently being organised for 7th November for South and East Dorset sites




   Core Aspect RAG Ratings
   Dimension                       Previous Period Current Period                           Reasoning
                   Engagement                                       Engagement event held 3rd October. Further one being
                                                                    arranged for 7th November. Currently engaging with non
                                                                    EMIS sites to bring forward those deployments - 5 out of 8
                                       Green           Green        approached.
                                                                    Dorchester A&E lead seems positive and has agreed to
                                                                    attend project board from next week. Further CSA work
                                                                    underway
               Communications                                        Wave 2 patients drop in sessions have commenced with
                                                                    high attendance for both SCR and HealthSpace
                                       Amber           Green        applications. Wave 3 mail out planned for 12th November
                                                                    with Wave 4 following in early December and Wave 5 in
                                                                    early January.
                   Data Quality                                     All Wave 1 sites have been audited and completed for
                                                                    Data Quality. Second lot of auditing at Wave 2 now
                                                                    commenced, most practices booked in.All Wave 2 sites
                                                                    green. The original Dorchester Wave 3 sites have - 7 of
                                                                    12 practices have green e-audit, however the newly
                                        Red             Red         identified Wave 3 Non-EMIS sites have yet to have DQF
                                                                    visits. Paperlight accreditation process review meeting
                                                                    took place Tuesday 25th.
                                                                    Currently no DQF in Dorset - interviews held 20th
                                                                    September unsuccessful, further interviews to be
                                                                    arranged. Urgent requirement now for DQF.
           Business Processes                                        PCT currently looking for resource to provide support to
                                                                    PM for this role. Job description has been written and
                                                                    provided to Director of IT. Further discussions had at
                                                                    project board 15th August. Director of IT to review
                                       Amber           Green
                                                                    resources available within PCT to fill this role. To be raised
                                                                    at board on October 17th. Trainers are now carrying out
                                                                    business process training to Wave 1 and Wave 2 sites
                                                                    where required.
                   IT & Security       Green           Green        To be reviewed

                       Benefits                                      PCT currently looking for resource to provide support to
                                                                    PM for this role. Benefits meeting took place Tuesday 2nd
                                                                    October to review Benefits identified to date and
                                       Green           Green        discussion to be held at project board on 17th October.




                     Resources                                       Job description written and provided to PCT's Director of
                                                                    IT for Change management role (benefits and process
                                                                    mapping). Project support role to be advertised
                                                                    externally.PM currently fulfilling support role. No DQF for
                                       Amber            Red
                                                                    Dorset currently. Comms work is being completed by PM
                                                                    also and requirement for support to take on some of that
                                                                    work

                       Training                                     All Wave1 and 2 training complete. Wave 3 sites are
                                       Green           Green
                                                                    currently booking training.