Docstoc

Dost Mohammad Mohammad Gopang

Document Sample
Dost Mohammad Mohammad Gopang Powered By Docstoc
					Dost Mohammad Gopang
Flate # G/301 – Rufi Lake Drive, Gulistan-I-Juhar, Karachi Mobile # 0092-321-8250036 Residences # 0092-214618456 dostengr@yahoo.com

Objective:
Looking for a Senior Position in an established organization, this will make use of my potential and take advantage of my extensive experience of Civil, Electro-Mechanical works and administrative skills. I have more than 10 years experience of working at different projects (About 4 years in Kingdom of Saudi Arabia and 6 years in Pakistan). I have a technical education with a proven track record with healthy experience of Middle East Countries.

Strength:
       Dedicated Personality-Team Player Initiative and innovative Excellent Communication-Inter Personal Skills Problem Solving-Organizational Skills Commitment to exceptional service Qualified-Talented-Well Trained Professional Ability to interact with various levels of management

Education:
Mehran university of engineering & Technology, Jamshoro Bachelors in Civil Engineering with an emphasis in Computer Technology 1992-1998

Computer Skills:
    AutoCAD (14, 2000& 2004) Short Course in Primavera Project Planner (P3) Short Course in MS Project 2002 Perfect Knowledge of MS Windows, Word, Excel & Power Point : : : : : : : : : Late Noor Mohammad Gopang 07th April, 1973 Larkana (R) Married AA4005611 Issue Date 25 Dec 2007 Expiry Date 23 Dec 2012 Civil/26067 House # D-37, Mehran University Co-operative Colony Nawabshah Valid for Saudi Arabia & Pakistan Easily handle Total Station, Thodolite & Level Machine

Personal Data:
Father’s Name Date of Birth Domocile Marital Status Pass Port # PEC # Permanent Address Driving License Other Skills

Work Experience:
Company Position Held Project Duration Responsibilities                : : : : : Sachal Engineering Works (Pvt) Ltd, Islamabad Project Manager Lyari Expressway Project April, 2006 to Present

Planning the site execution on Primavera P3. Planning of Human resource as per requirement of the firm at different stages To determine the appropriate structure and jobs to meet firms’ requirements. Take all the Managerial decision for the construction of Freyssosil Panels , Installation for Reinforced Earth Wall & Traffic Safety Concrete Barrier To determine the appropriate structure and jobs to meet firms’ requirements. Co-Ordinate & attend meetings with various Agencies contractor, Sub-Contractors & Consultants Supervision & Monitoring of works as per the approved drawings and specification Prepare Presentation for the high ups Managing all over project. Submission of monthly Interim Payment Certificate (IPC) Checking the of Bar Bending Schedule Preparation of monthly schedule on P3 Preparation of Daily, Weekly & Monthly Progress Report Submission of Escalation Claims (Material & Manpower) Preparation of various Rate Analysis

Company

:

Position Held : Project : Duration : Responsibilities :  Construction of 40mX34m 12m high Mosque building.  Construction of 15mX15m 12m high four Story Service Building to Mosque  Construction of Main Dome of mosque 12m Dai 10m high over mosque.  Construction of Minaret 12mX12mX1m Footing 5m below ground 44m Above Ground 4x4m.  Construction of 2Km fence for the mosque area.  Out side elevation work with Jordanian stone works (Hajar) total area 2200 Sqm work.  Factory ready cut curved stone for main dome and minaret work.  Aluminum work for windows of mosque which is 8.5m high 2m wide with double layer tinted glass, between glass architactul figures.  GRC work for windows screen, mihrab and minaret opening, Gypsum board work for false ceiling for both building and minaret.  Raft Foundation for main Building Upto 550 Cum Concrete. 250 Cum Concrete for Service Bld, 100 cum Concrete for Minaret.

Al-Jawad Trading, Industry and Contracting Company AL-Ahsa, Al-Hofuf, Kingdom of Saudi Arabia Assistant Project Manager Mosques (BUKHAMSEEN, AL-HULALA, AL-GHARA) & 12 No Villas 2002 to April, 2006

                    

12m High from GL main building supported on columns, down beams & solid slab. Mass concrete work for columns, beams and slab used very high-density steel used in the structural members. 12m Dai and 10m high Main doom for Mosque bld with architacal concrete. Very big Minaret 4mX4m Area 5m below ground and 45m above ground, with changing elevation. RCC Solid blocks work for whole project. Outside Stone work. HVAC Work Electric Wiring, Public Address, Telephone, Intercom, Fire Fighting, TV System. Plumbing Work, Waste & Soil Pipe used HDPE pipe with Electro-fusion coupling used for jointing. Water supply lines with hot and cold water system with circulating electric heaters. Ducting work for HVAC. Marble Work for Inside Walls and Flooring and Stair case. Water proofing with bitumen Sheet work and protecting with 50mm geo-textile sheet. Aluminum work for Windows and doors GRC work for Window Openings Gypsum Board, False Ceiling work. All works executed before submitting shop drawings drawn through Auto CAD. All billing and quantities work on MS-Office. All Paint work Oil, Emulsion, Texture, with there primer work. Lift Machine work for passenger upto mezzanine floor. Semi-Mechanical Marble Work 5m high walls, total area 600 Sqm. Installation of Earthling & lightening system for 45m high Minaret & Main Dome. Metal work for spiral stair for Minaret 1.8m Dai and 40m height.

Company : Royal Construction Company Project : Mehnaz Complex (Commercial Plaza) Position Held : Deputy Project Manager Duration : 2000 to 2002 Responsibilities :  Footing Foundation For Ground Floor Shopping Center, next three floor for housing apartment, area of building 45mX50m 20m high, with 6mX6m overhead water tank.  20m high building supported on columns, down beams & solid slab. Mass concrete work for columns, beams and slab used very high-density steel used in the structural members.  Clay brick work for patron wall  Outside Elevation Red Brick Work.  Electric Wiring, Telephone, Intercom, Fire Fighting, TV System.  Plumbing Work, Waste & Soil Pipe used PVC pipe. Water supply lines with hot and cold water system with circulating electric heaters.  Marble Work for Inside Walls and Flooring and Stair case.  Water proofing with bitumen Sheet work and protecting Bath rooms from seepage.  Aluminum work for Windows and doors.  All works executed before submitting shop drawings drawn through Auto CAD.  All billing and quantities work on MS-Office.  All Paint work Oil, Emulsion, Texture, with there primer work.

 

Spanish Tiles work for Front Elevation Building. Metal work for handrail and windows grill.

Company : Royal Construction Company Project : Chemi Visco Fibre Projct (A Multi Purpose Industrial Project at Nawabshah) Position Held : Site Engineer Duration : 1998 to 2000 Responsibilities :  More then 26 building project 32 acre was the area of project. A chemical plant with collaboration of Chines Company.  2000 No. Foundation of pile works 560mm Dai 18m deep, 36m high buildings for heavy machine vibration.  All layouts on total station through angle distance and co-ordinate system.  Landscape and parking work.  Storm darin work.  Outside elevation Work.  Finishing work for administration block  Electric Wiring, Public Address, Telephone, Intercom, Fire Fighting, Security system for whole plant.  All plumbing work of the plant.  Acid & Alkaline Drain channel with acid proof brick work lining.  Effluent treatment plant and his tank with acid proof brick work lining.  Marble Work for Inside Walls and Flooring and Staircase.  Water proofing with bitumen Sheet to protect the slabs of plant.  Aluminum work for Windows and doors  Water tank for smooth supply of water to plant.  Construction of circulating cooling water tower for plant.  Steel doors and windows for the whole plant.  Construction of Equipment Foundation of Whole project.  Under ground foundation for baling pressing machine foundation.  Foundation work of Boiler of factory.  200Nos. Construction of RCC T-Support for Pipes of Plant.  Construction of 6 No. Watch Towers for Security guards.  All works executed before submitting shop drawings drawn through Auto CAD.  All billing and quantities work on MS-Office.  Updating the project by using MS-Project.  All Paint work Oil, Emulsion, with there primer work.  Lift machine erection work both for passenger and material shifting upto 36m high.


				