									                                                  BRUHAT BANGALORE MAHANAGARA PALIKE
                                       WORK WISE SHANTHINAGAR CONSTITUENCY (NURSERIS WORK) FORMAT
                                              PROGRAM OF WORKS -2009-10 HORTICULTURE (EAST)
Sl.No. W.No            Name of work          Tendered   Date of    Work order   Commencem Scheduled date of Probable Expenditur Percentage        Remarks
                                               Cost     tender       Date         ent Date Completion as per   date of  e incurred of physical
                                                                                              Contract       Completion             progress
        76    Rest house park - puts           5.00                                                                                              File under
    1                                                   24.06.09    06.07.09      07.07.09      06-08.09       05.08.09     5.40      100%       process
        76    Rest house park Labour           4.00                                                                                              File under
    2         Component & wages                         24.06.09    06.07.09      07.07.09     06.07.2010     06.07.2010    4.32       10%       process
                                               9.00
                                     WORK WISE SHIVAJINAGAR CONSTITUENCY (NURSERIS WORK) FORMAT
                                           PROGRAM OF WORKS -2009-10 HORTICULTURE (EAST)
Sl.No. W.No            Name of work          Tendered   Date of    Work order   Commencem Scheduled date of Probable Expenditur Percentage        Remarks
                                               Cost     tender       Date         ent Date Completion as per   date of  e incurred of physical
                                                                                              Contract       Completion             progress
                                                                                                                                                 File under
        77    Madhava Nursery - inputs         5.00
    1                                                   24.06.09    06.07.09      07.07.09      06-08.09       05.08.09     5.40      100%       process
              Madhava Nursery - labour                                                                                                           File under
                                               4.00
    2   77    component & wages                         24.06.09    06.07.09      07.07.09     06.07.2010     06.07.2010    4.32       1%        process
                                                                                                                                                 File under
              Head office Nursery - inputs     5.00
    3   77                                              24.06.09    06.07.09      07.07.09      06-08.09       05.08.09     5.40      100%       process
              Head office Nursery - labour                                                                                                       File under
                                               4.00
    4   77    component & wages                         24.06.09    06.07.09      07.07.09     06.07.2010     06.07.2010    4.32       10%       process
                                              18.00
                         WORK WISE MALLESWARAM CONSTITUENCY (NURSERIS WORK) FORMAT
                                PROGRAM OF WORKS -2009-10 HORTICULTURE (EAST)
Sl.No. W.No   Name of work     Tendered   Date of   Work order   Commencem Scheduled date of Probable Expenditur Percentage       Remarks
                                 Cost     tender      Date         ent Date Completion as per   date of  e incurred of physical
                                                                               Contract       Completion             progress
                                   WORK WISE PULIKESHINAGAR CONSTITUENCY (NURSERIS WORK) FORMAT
                                           PROGRAM OF WORKS -2009-10 HORTICULTURE (EAST)
Sl.No. W.No            Name of work         Tendered   Date of    Work order   Commencem Scheduled date of Probable Expenditur Percentage        Remarks
                                              Cost     tender       Date         ent Date Completion as per   date of  e incurred of physical
                                                                                             Contract       Completion             progress
                                                                                                                                                File under
        91    Coles park Nursery - inputs     5.00
    1                                                  24.06.09    06.07.09      07.07.09      06-08.09       05.08.09     5.40      100%       process
              Coles Park Nursery - labour                                                                                                       File under
                                              4.00
    2   91    component & wages                        24.06.09    06.07.09      07.07.09     06.07.2010     06.07.2010    4.32       10%       process
                                              9.00
                      WORK WISE SARVAGNANAGARA CONSTITUENCY (NURSERIS WORK) FORMAT
                              PROGRAM OF WORKS -2009-10 HORTICULTURE (EAST)
Sl.No. W.No   Name of work    Tendered   Date of   Work order   Commencem Scheduled date of Probable Expenditur Percentage       Remarks
                                Cost     tender      Date         ent Date Completion as per   date of  e incurred of physical
                                                                              Contract       Completion             progress
                                WORK WISE C.V. RAMANNAGARA CONSTITUENCY (NURSERIS WORK) FORMAT
                                         PROGRAM OF WORKS -2009-10 HORTICULTURE (EAST)
Sl.No. W.No           Name of work           Tendered   Date of    Work order   Commencem Scheduled date of Probable Expenditur Percentage        Remarks
                                               Cost     tender       Date         ent Date Completion as per   date of  e incurred of physical
                                                                                              Contract       Completion             progress
              Indirangara 13th Cross park                                                                                                        File under
                                               5.00
    1   82    Nursery - inputs                          24.06.09    06.07.09      07.07.09      06-08.09       05.08.09     5.40      100%       process
              Indiranagar 13th Cross park
              Nursery - labour component &     4.00                                                                                              File under
    2   82    wages                                     24.06.09    06.07.09      07.07.09     06.07.2010     06.07.2010    4.32       10%       process
                                               9.00
                         WORK WISE B.T.M. LAYOUT CONSTITUENCY (NURSERIS WORK) FORMAT
                               PROGRAM OF WORKS -2009-10 HORTICULTURE (EAST)
Sl.No. W.No   Name of work     Tendered   Date of   Work order   Commencem Scheduled date of Probable Expenditur Percentage       Remarks
                                 Cost     tender      Date         ent Date Completion as per   date of  e incurred of physical
                                                                               Contract       Completion             progress
                                       WORK WISE HEBBAL CONSTITUENCY (NURSERIS WORK) FORMAT
                                           PROGRAM OF WORKS -2009-10 HORTICULTURE (EAST)
Sl.No. W.No           Name of work         Tendered   Date of    Work order   Commencem Scheduled date of Probable Expenditur Percentage        Remarks
                                             Cost     tender       Date         ent Date Completion as per   date of  e incurred of physical
                                                                                            Contract       Completion             progress
        97    Kempegowda tower Nursery -                                                                                                       File under
                                             5.00
    1         inputs                                  24.06.09    06.07.09      07.07.09      06-08.09       05.08.09     5.40      100%       process
        97    Kempegowda tower Nursery -                                                                                                       File under
                                             4.00
    2         labour component & wages                24.06.09    06.07.09      07.07.09     06.07.2010     06.07.2010    4.32       10%       process
                                             9.00

								