					                                                                                                    Daily Field Report
 Mountain View Tel: 650.967.2365 Fax: 650.967.2785                                 Oakland Tel: 510.267.1970 Fax: 510.267.1972
 Fairfield Tel: 707.423.2523 Fax: 707.423.1725                                     San Ramon Tel: 925.275.2550 Fax: 925.275.2555
 Fullerton Tel: 714.441.3090 Fax: 714.441.3091

                                                                                                        Job No.                           Page
                                                                                                            1993-1                           1              of             1
Project                                                     Client                                                  Report No.
Leona Quarry                                                City of Oakland                                                                  161
Location                                                    Grading or Excavation Contractor                        Date                           Day of Week
Oakland, CA                                                 DeSilva Gates                                            3/22/05                           Tuesday
General Contractor                                          Contractor’s Foreman                                    Eng. Tech                      Assistants
DeSilva Gates                                               Clayton Haskins/Mark                                             PF                                  -
General Contractor’s Superintendent                         Specialty Contractor                                    Contractor’s Foreman
Kent Peyton


Field Observations                                                                      Time:     11AM      Weather: Raining, cool




- I was on site from 10AM to 11AM.
- No scrapers were running at the time of my visit. A Cat D10 dozer was ripping the cut areas. An
excavator was trimming the slope to the north of “K” Street near the intersection with “A” Street.
- I did not observe any major damage from the rain that fell during the period between Friday (3/18)
and this morning. There was water flowing in “A” Street in some minor ruts. The water flowing in “A”
Street was channeled into the on site storm drain catch basins by check dams trenched across the
roadway. It appeared as though channels cut in “A” Street were effective in channeling water into the
on site storm drain catch basins. The “I” Street pond had about 2-feet of water. The water level in the
large basin was about 6-feet below the opening in the spillway. The filtration system was in operation
and pumped relatively clear water into the storm drain. I did not observe any water flowing from the
site onto Edward’s Avenue.
- Peter told me that DeSilva Gates would most likely resume grading operations next Tuesday. Heavy
rain is forecast for later today.




Follow-up from prior report           Yes            No


What should be observed, checked, or tested during the next visit:




The DFR is preliminary                  This DFR is final                      Continued on next page          P:\1-STANDARDS\Forms\Construction Svc\DFR Masters\DFR10 Verdana.doc