									Project Overview

Universal Road Reconstruction Fairwood Avenue to Progress Avenue
Description: Project reconstructs severely deteriorated pavement and builds sidewalks and curb ramps along this industrial roadway. Project length is approximately 2,200 feet.

Above: Existing section of Universal Road.

Benefits: Reconstructs deteriorated roadway and provides pedestrian access. Costs: Schedule: Construction: $1.5 Million (estimate). Design: Completed. Right-of-way acquisition: December 2009 – May 2010. Construction: Tentative start July 2010, ending November 2010.

City of Columbus Department of Public Service Div. of Design & Construction 109 North Front Street Columbus, Ohio 43215 www.Columbus.gov

Status: Design work completed; anticipate starting construction pending completion of right-of-way acquisition and availability of construction funding. Project Manager: Carl Walters, P.E., tel. (614) 645-7858 Designer: W.E. Stilson Consulting Group
As of December 1, 2009

Universal Road Reconstruction Fairwood Avenue to Progress Avenue, p. 2


								