ADB FUNDED WATER SECTOR LOANS WITH DAM COMPONENT
Project Serial Number 1 2 3 4 5 6 1 4 30.0 138.0
existing dam, hydroelectric eqpt only 7,280 mcm reservoir new dam TA loan 13,692 mcm reservoir

Loan Number 38 57 67 77 81 83 86 96 118 168 169 190 196 200 201 223 224 237 260 262 266 291 299 304 312 318

Country KOR SIN TAP PHI INO INO KOR PHI SRI PAK PAK PHI PHI PAK PAK PHI MAL INO INO SIN MYA PHI SRI THA AFG PNG

Title Andong Dam Multipurpose Development Water Supply Li-Wu Chi Hydroelectric Power Development Mindanao Power Sempor Dam and Irrigation West Sumatra Power Supply Andong Dam Multipurpose Development* Second Mindanao Power Bowatenna Power Mangla Hydropower Mangla Hydropower Manila Water Supply Third Mindanao Power Tarbela Hydropower Tarbela Hydropower First and Second Mindanao Power (Supplementary) Tenom Pangi Power Garung Hydroelectric Maninjau Hydropower Second Water Supply Third Sedawgyi Multipurpose Dam and Irrigation Fourth Mindanao Power Canyon Hydropower Third Power Khanabad Hydropower Provincial Mini-Hydropower
1

Fund OCR OCR OCR OCR ADF ADF OCR OCR ADF ADF OCR OCR OCR ADF OCR OCR OCR OCR OCR OCR ADF OCR ADF OCR ADF OCR

Amount ($M) 0.50 8.30 0.50 23.40 9.20 7.10 22.00 21.00 8.00 3.90 12.80 51.30 1.00 34.00 13.00 22.70 1.20 19.80 39.70 23.60 45.90 52.00 17.50 47.00 9.00 2.70

Date Approved 6-Oct-70 23-Dec-70 18-May-71 2-Nov-71 2-Dec-71 7-Dec-71 16-Dec-71 13-Jul-72 19-Dec-72 17-Dec-73 17-Dec-73 28-Aug-74 7-Nov-74 28-Nov-74 28-Nov-74 27-May-75 17-Jun-75 13-Nov-75 8-Apr-76 13-Apr-76 22-Jun-76 21-Dec-76 26-Jul-77 25-Aug-77 13-Oct-77 22-Nov-77

Year Completion

Dam Height Subsector (m) W, I, H, F 72.0 20.0 53 & 40 32.0 50.5 8.0

Remarks 1,243 mcm reservoir, TA loan 20.5 mcm reservoir 0.5 & 0.4 mcm- two dams, TA loan lake reservoir 46.5 mcm reservoir diversion weir, 0.116 mcm

1975

W, F HP

1975 1978 1976 1979 1980 1981 1983 1983 1985

HP I, F HP W, I, H, F H H, I H H W HP

7 8 8

30.0

9 4 10 10 4

1984 1984 1980

H H H HP

143.0

260 mcm, TA loan

11 12 13 14 15 4

1987 1983 1981 1987 1985 1983 1983

H HP W H, I H HP HP HP

35.0 diversion weir 3.0 20.0 39.0

14 mcm reservoir 240 mcm lake 28.4 mcm reservoir 379 mcm reservoir

108 mcm exisitng dam existing dam, hydroelectric eqpt only

16 17 18 19

1988

HP

barrage diversion weir

run-of-river run-of-river

ADB Dams Database

Page 1 of 28

Draft, 31 August 2005

ADB FUNDED WATER SECTOR LOANS WITH DAM COMPONENT
Project Serial Number 4 20 10 9 130.0 150.0
640 mcm, TA loan 7,400 mcm reservoir, with 8 saddle dams 45-8m

Loan Number 326 324 332 351 365 372 395 414 415 427 465 512 518 521 522 556 557 601 605 612 613 638 674 698 701 702

Country PHI SRI PAK PHI THA MAL MYA PNG PNG PHI KOR NEP INO MAL INO THA THA PAK MAL SRI THA INO INO LAO PAK PAK

Title Fifth Mindanao Power Kirindi Oya Irrigation and Settlement Tarbela Hydropower (Supplementary and Extension) Second Manila Water Supply Kud Multipurpose Trengganu Hydropower Sedawgyi Hydropower Upper Warangoi Hydropower Upper Warangoi Hydropower Sixth Mindanao Power Samrangjin Pumped Storage Power Mini-Hydropower Wadaslintang Multipurpose Batang Ai Hydropower Bali Irrigation Sector Medium Scale Irrigation Package Medium Scale Irrigation Package Tarbela Hydropower Extension (Units 9 & 10) Mini-Hydropower Sector Kirindi Oya Irrigation and Settlement (Supplementary) Second Power System Expansion Second Irrigation Sector Power XVIII Xeset Hydropower Tarbela Hydropower Extension (Units 11 &12) Tarbela Hydropower Extension (Units 11 & 12)

Fund OCR ADF OCR OCR OCR OCR ADF OCR ADF OCR OCR ADF OCR OCR OCR ADF OCR OCR OCR ADF OCR OCR OCR ADF OCR ADF

Amount ($M) 29.00 24.00 38.00 49.00 1.38 45.40 14.60 6.25 6.00 60.70 52.63 8.30 87.70 40.40 33.60 15.00 25.00 29.00 24.00 10.00 81.60 75.79 135.00 1.00 137.20 31.80

Date Year Approved Completion 9-Dec-77 1985 9-Dec-77 15-Dec-77 7-Sep-78 14-Nov-78 5-Dec-78 24-Apr-79 27-Sep-79 27-Sep-79 27-Nov-79 18-Sep-80 21-Apr-81 23-Jun-81 17-Sep-81 17-Sep-81 10-Dec-81 10-Dec-81 23-Nov-82 25-Nov-82 9-Dec-82 9-Dec-82 22-Sep-83 20-Dec-83 23-Oct-84 25-Oct-84 25-Oct-84 1994 1994 1993 1992 1989 1987 1985 1990 1989 1986 1989 1990 1990 1986 1989 1983 1989 1984 1987

Dam Height Subsector (m) H I H W H, I H,F H HP HP H HP H, I I, H, F, W H I I, F I, F HP HP I HP I H HP H H 135 & 59 weir 33.0 6.0 overflow weir 20.0 upper = 104 m, lower 62 m diversion weir 12.0 25.0

Remarks 198 mcm reservoir

21 22 15

diversion weir, runof-river diversion dam, 67 mcm upper = 5.0 mcm, lower = 5.4 mcm reservoir 8 mini-hydros, various location

23 23 24 25 26 27 28 29 30 30 10

408 mcm reservoir 125.0 Main dam = 85, saddle 750 mcm reservoir dams 26 & 40 small weirs various locations

21.0

4.3 mcm reservoir

9 schemes

31 20

HP project in two areas sector project 21.5 mcm reservoir diversion weir, TA loan

32 33 34 35 10 10

ADB Dams Database

Page 2 of 28

Draft, 31 August 2005

ADB FUNDED WATER SECTOR LOANS WITH DAM COMPONENT
Project Serial Number 36 37 38 10 20 20.0
10 mcm reservoir

Loan Number 713 750 757 760 794 813 846 952 953 962 986 1032 1063 1101 1128

Country MAL PAK MAL PAK SRI SAM LAO INO INO PNG PHI INO LAO PAK SRI

Title Sungai Piah Hydropower Small Dams Perlis Agricultural Development
TARBELA Units 13 & 14 and 500kV Transmission

Fund OCR ADF OCR OCR ADF ADF ADF ADF OCR OCR OCR OCR ADF ADF ADF

Amount ($M) 64.20 39.00 43.00 117.80 26.60 5.40 15.50 25.00 84.53 8.43 130.00 235.00 3.00 20.00 38.00

Date Year Approved Completion 6-Dec-84 31-Oct-85 26-Nov-85 28-Nov-85 30-Oct-86 4-Dec-86 27-Oct-87 7-Feb-89 7-Feb-89 6-Jul-89 14-Nov-89 25-Sep-90 11-Dec-90 26-Sep-91 26-Nov-91 1999 2000 1999 1998 1995 1993 1994 1995 1994 1993 1995 1995

Dam Height Subsector (m) HP 3.0 I I, W H I H HP I, H I, H HP WSS HP HP I, W, F I 6.5 4 m water level range 15 - 36 15.0

Remarks diversion weir 12 storage dams in various areas, 1.14.1 mcm

Kirindi Oya Irrigation and Settlement (Phase II) Afulilo Hydroelectric Xeset Hydropower Nusa Tenggara Agricultural Development Nusa Tenggara Agricultural Development Divune Hydropower Project Angat Water Supply Optimization Power XX Xeset Hydropower (Supplementary) Kotri Barrage Rehabilitation Southern Province Rural Development North Western Province Water Resources Development Nam Song Hydropower Development Afulilo Hydroelectric Power (Supplementary) Guangzhou Pumped Storage Stage II Power XXIII Hunan Lingjintan Hydropower Theun-Hinboun Hydropower Fujian Soil Conservation and Rural Development Fujian Mianhuatan Hydropower

39 35 40 40 41 9

diversion weir & 10 m & 12 m supplementary left bank dam, 0.3 mcm

34.0

21 mcm reservoir run-of-river regulating weir on lake outlet, 450 mcm barrage gate rehabilitation diversion weir, tank bunds various locations rehabilitation tank bunds, various loactions diversion weir

42 35 43 44

1166 1214 1228 1242 1271 1318 1329 1386 1417

SRI LAO SAM PRC INO PRC LAO PRC PRC

ADF ADF ADF OCR OCR OCR ADF OCR OCR

30.00 31.50 2.00 200.00 275.00 116.00 60.00 65.00 170.00

25-Jun-92 21-Dec-92 22-Apr-93 3-Aug-93 25-Nov-93 27-Sep-94 8-Nov-94 28-Sep-95 14-Dec-95

2000 1997 1994

I H H HP HP upper = 68 m, lower 43.5 m 25.0 53.5 25.0 44.7 111.0 21.0

45 46 39

upper = 24 mcm, lower = 24.5 mcm reservoir diversion dam reregulating dam 20mcm reservoir 7 dams, 3 < 15m, 4 > 15 m 1,122 mcm

47 48 49 50 51 52

2001 1998 2002 2002

H, N H, F H, W H, F, N

ADB Dams Database

Page 3 of 28

Draft, 31 August 2005

ADB FUNDED WATER SECTOR LOANS WITH DAM COMPONENT
Project Serial Number

Loan Number

Country

Title

Fund

Amount ($M)

Date Approved

Year Completion

Dam Height Subsector (m)

Remarks Gated barrage height not specified, >15m, small headponds allow reregualtion of peak Tarbela flows

1424

PAK

Ghazi Barotha Hydropower

OCR

300.00

16-Jan-96

2004

HP

53

1452 1456 1462

NEP LAO SRI

Kali Gandaki "A" Hydroelectric Power Nam Leuk Hydropower North Central Province Rural Development

ADF ADF ADF

160.00 52.00 20.03

23-Jul-96 10-Sep-96 24-Sep-96

2004 2003

H H Irrigation

44.0 45.0

3.1 mcm reservoir 185 mcm reservoir No new dam construction existing tank rehabilitation

54 55 56

1544 1668

PRC PHI

Zhejiang-Shanxi Water Supply Project (Phase I) Southern Philippines Irrigation Sector

OCR OCR

100.00 60.00

24-Sep-97 18-Dec-98

2003 2006

W, I, H, F I

130m & 16m

storage dam & diversion dam Small reservoir projects - height not specified Barrage with adjustable crest to manage water levels. Height not specified.

57 58

1757

SRI

Water Resource Management

ADF

30.00

19-Sep-00

2005

W

59

1814 1922 1995 2025 2032 2161/2162

PRC PRC PRC VIE PRC LAO Note:

West Henan Agricultural Development Project Hebei Zhanghewan Pumped Storage Project Harbin Water Supply Phuoc Hoa Multipurpose Water Resources Gansu Clean Energy Development GMS Nam-Theun II Hydropower Development

OCR OCR OCR ADF OCR OCR
*2

64.30 144.00 100.00 90.00 35.00 120.00

19-Dec-00 18-Oct-02 11-Mar-03 27-Nov-03 5-Dec-03 4-Apr-05

2006 2009 2007 2011 2008 2009

W, I H W I, W H H

45.0
Raise lower dam from 54 to 77m

24.6 mcm reservoir

60 61

45.0 28.0 18.0 48.0 Legend:
H I W F N

356 mcm reservoir 18.5 mcm reservoir

62 63 64 65

3530 mcm reservoir

1 Data as of 31 August 2005. 2 Dam details based on Report and Recommendation of the President (RRP) and/or Project Completion Report (PCR) 3 List is not exhaustive, for some sector projects dam component will only be known during design and implementation.

Hydroelectric power Irrigation Water supply Flood control Navigation

*1 entries in blue represent follow-on investments for earlier loans *2 comprises of $20 million public sector loan, $50M direct loan to the project company, and political risk guarantee of $50M.

ADB Dams Database

Page 4 of 28

Draft - 31 August 2005

LARGE DAM PROJECTS SINCE 1994 COMPLETED PROJECTS

Loan Number

Country

Title

Amount ($M)

Date Approved

Status/Date Loan Closure

Sector

Project Benefits at Design

1318

PRC

Hunan Lingjintan Hydropower

116.00

27-Sep-94

close 8 Nov 2001

HP

240 MW capacity 1173 GWh annual generation

1329

LAO

Theun-Hinboun Hydropower

60.00

8-Nov-94 close 14 Oct 98

HP

210 MW

1386

PRC

Fujian Soil Conservation and Rural Development

65.00

28-Sep-95

close 30 Jun 2002

Multi

9,800 ha orchards, 4000 ha forestry, 340 ha fishponds,

1417

PRC

Fujian Mianhuatan Hydropower

170.00

14-Dec-95

close / 15 Oct 2002

HP

600 Mw capacity 1510 GWh annual generation, secondary flood mgmt.

1424

PAK

Ghazi Barotha Hydropower

300.00

16-Jan-96

close / 20 Jan 2004

HP

1450MW capacity 6600 GWh annual generation

1452

NEP

Kali Gandaki "A" Hydroelectric Power

160.00

23-Jul-96

close / 28 Apr 2004

HP

144MW capacity, 842 GWh annual generation

5

Draft - 31 August 2005

LARGE DAM PROJECTS SINCE 1994 COMPLETED PROJECTS

Loan Number

Country

Title

Type and Height of Dam

Components financed by ADB

Co-financiers Hunan Provincial Government & State Development Bank

Resettlement

1318

PRC

Hunan Lingjintan Hydropower

Reregulating Dam 53.5m

About 90% of the foreign exchange cost

2,937 people

1329

LAO

Theun-Hinboun Hydropower

Dam 25m, 20mcm reservoir Four small storage dams, 1 to 4 MW, 81 GWh, reservoirs of 1.4 to 5 mcm

Main civil works and portion of hydraulic steel works Soil conservation, aquaculture, agricultural marketing infrastructure, small scale hydropower

Commercial banks, export credit

No resettlement

1386

PRC

Fujian Soil Conservation and Rural Development

Local Govt., Domestic Banks, Beneficiary 77 families enterprises

1417

PRC

Fujian Mianhuatan Hydropower

Provincial Electric Bureau, State Development Bank, Dam 111m, Dam, underground power Construction Bank, 36,000 people 1122mcm reservoir station, transmission lines Development Companies, Provincial Govt Gated barrage height not specified, >15m, small headponds allow reregualtion of peak Tarbela flows Dam 44m reservoir of 3.1 mcm

1424

PAK

Ghazi Barotha Hydropower

Barrage, 52km power channel, power station

World Bank, OECF, 130 families KfW, EIB, IsDB, Govt.

1452

NEP

Kali Gandaki "A" Hydroelectric Power

Dam, power station, transmission lines

OECF, Nepal Electricity 125 families Authority

6

Draft - 31 August 2005

LARGE DAM PROJECTS SINCE 1994 COMPLETED PROJECTS

Loan Number

Country

Title

Enhancement or restoration Restoration / construction opportunities

Indigenous Peoples

1318

PRC

Hunan Lingjintan Hydropower

No

1329

LAO

Theun-Hinboun Hydropower

Restoration / new school facilities

Tai/Lao ethnic category.

1386

PRC

Fujian Soil Conservation and Rural Development

Compensation

No

1417

PRC

Fujian Mianhuatan Hydropower

Income retoration, better housing.

No

1424

PAK

Ghazi Barotha Hydropower

Compesnation plus support through Inetgrated Regional Development Plan

No

1452

NEP

Kali Gandaki "A" Hydroelectric Power

Compensation

No

7

Draft - 31 August 2005

LARGE DAM PROJECTS SINCE 1994 COMPLETED PROJECTS
Extent of consumptive use

Loan Number

Country

Title

1318

PRC

Hunan Lingjintan Hydropower

1329

LAO

Theun-Hinboun Hydropower

Instream / offstream Instream - reregulating station for the Wuqiangxi hydropower plant located immediately upstream Instream dam offstream basin diversion waterways to powerhouse

Inter-basin diversion?

PCR No. and date

PPAR No. and date

No

None

IN.280-03 19 Nov 03

Yes - from Nam Theun basin to Nam Hinboun None basin

IN.322-00 14 IN.335-02 Dec 00 24 Dec 02

1386

PRC

Fujian Soil Conservation and Rural Development

Instream

No

Yes, for 1,020 ha PRC 26004 cropland Sep 03

1417

PRC

Fujian Mianhuatan Hydropower

Part of cascade

No

None

1424

PAK

Ghazi Barotha Hydropower

Instream -Reregulating hydropower downstream of existing Tarbela project

No - diversion of 1600 cumecs through 52 None km tunnel back to river downstream No - diversion through power tunnel back to None river 50km downstream

1452

NEP

Kali Gandaki "A" Hydroelectric Power

Instream

NEP 26362 Apr 2004

8

Draft - 31 August 2005

LARGE DAM PROJECTS SINCE 1994 COMPLETED PROJECTS

Loan Number

Country

Title

1318

PRC

Hunan Lingjintan Hydropower

1329

LAO

Theun-Hinboun Hydropower

1386

PRC

Fujian Soil Conservation and Rural Development

1417

PRC

Fujian Mianhuatan Hydropower

1424

PAK

Ghazi Barotha Hydropower

1452

NEP

Kali Gandaki "A" Hydroelectric Power

9

Draft - 31 August 2005

LARGE DAM PROJECTS SINCE 1994 COMPLETED PROJECTS

Loan Number

Country

Title

1318

PRC

Hunan Lingjintan Hydropower

1329

LAO

Theun-Hinboun Hydropower

1386

PRC

Fujian Soil Conservation and Rural Development

1417

PRC

Fujian Mianhuatan Hydropower

1424

PAK

Ghazi Barotha Hydropower

1452

NEP

Kali Gandaki "A" Hydroelectric Power

10

Draft - 31 August 2005

1456

LAO

Nam Leuk Hydropower

52.00

10-Sep-96

close / 13 Mar 2003

HP

60MW capacity 215GWh annual generation plus additional 30GWh at Nam Ngum Improved agricultural productivity on 5000ha and higher rural incomes for 43,000 households

1462

SRI

North Central Province Rural Development

20.03

24-Sep-96

Ongoing 31 Dec 2004

Irrigation

1544

PRC

Zhejiang-Shanxi Water Supply Project (Phase I)

100.000

24-Sep-97

close /10 Jul 2003

1.8 mcm per day good quality raw water, WSS, flood improve flood protection mgmt. and for 250,000 people, irrigation irrigation for 60,000 ha and 220MW generating capacity Irrigation Irrigation and drainage for 18,000ha benifiting 10,000 housholds

1668

PHI

Southern Philippines Irrigation Sector

60.000

18-Dec-98

Ongoing

PROPOSED PROJECTS AND PROJECTS UNDER IMPLEMENTATION
Loan Number Country Title Amount ($M) Date Approved Status/Date Loan Closure Sector Project Benefits at Design Improved water supply to 330,000 people. Sustainable management of water resources 900,000 people from pro poor economic growth opportunities

ONGOING
1757 SRI Water Resource Management 30.00 19-Sep-00 Ongoing WS

1814

PRC

West Henan Agricultural Development Project

64.30

19-Dec-00

Ongoing

WS/I

11

Draft - 31 August 2005

1456

LAO

Nam Leuk Hydropower

Dam 45m reservoir of 185 mcm

Dam, power station, diversion weir, transmission lines Rehabilitation of existing tanks covering approx 5,000 ha - 50 medium an 130 minor tanks,fisheries devt and credit

OECF, Electricity of Laos

None

1462

SRI

North Central Province Rural Development

No new dam construction existing tank rehabilitation

Govt. and local credit instituitons

None

1544

PRC

Zhejiang-Shanxi Water Supply Project (Phase I)

(i) 130m storage dam with ??mcm reservoir (ii) 16m diversion dam

Dams, power station, transmission lines, conveyance channels

Local financial, development and 37,000 people investment companies

1668

PHI

Southern Philippines Irrigation Sector

Small reservoir projects - height not specified

Irrigation infrastruture

National and Local Govt. and beneficiaries

30 families in sample subproject. Total to be determined.

PROPOSED PROJECTS AND PROJECTS UNDER IMPLEMENTATION
Loan Number Country Title Type and Height of Dam Barrage with adjustable crest to manage water levels. Height not specified. Dam - 45m 24.6 mcm resr. Components financed by ADB Co-financiers Resettlement

ONGOING
1757 SRI Water Resource Management Instittuional development, barrage and water supply infrstaructure All forex cost of dams, treatment plant and transmission pipes Government None

1814

PRC

West Henan Agricultural Development Project

Government, local enterprises and households

1,603 people

12

Draft - 31 August 2005

1456

LAO

Nam Leuk Hydropower

Project affected people will receive social and economic benefits

Yes, but not to be resettled

1462

SRI

North Central Province Rural Development

n/a

No

1544

PRC

Zhejiang-Shanxi Water Supply Project (Phase I)

Compenstaion

No

1668

PHI

Southern Philippines Irrigation Sector Compenstaion

Yes

PROPOSED PROJECTS AND PROJECTS UNDER IMPLEMENTATION
Loan Number Country Title Enhancement or restoration Indigenous Peoples

ONGOING
1757 SRI Water Resource Management n/a No

1814

PRC

West Henan Agricultural Development Project

Restoration / housing improved

No

13

Draft - 31 August 2005

1456

LAO

Nam Leuk Hydropower

Instream

Yes - from Nam Leuk into nam Xan and from None Nam Pun to Nam Leuk

LAO-29163 Feb 02

1462

SRI

North Central Province Rural Development

n/a

No

Increase existing stroage capacity

1544

PRC

Zhejiang-Shanxi Water Supply Project (Phase I)

Instream

Irrigation - for 60,000ha Water supply Diversion to cosatal approx one third towns for water supply of average flows for smaller diversion dam. Not specified Not specified, irrigation water for 18,000ha

PRC 28207 Aug 04

1668

PHI

Southern Philippines Irrigation Sector Not specified

PROPOSED PROJECTS AND PROJECTS UNDER IMPLEMENTATION
Loan Number Country Title Instream / offstream? Inter-basin diversion? Extent of consumptive use PCR No. and date PPAR No. and date

ONGOING
1757 SRI Water Resource Management Instream No For water supply

1814

PRC

West Henan Agricultural Development Project

Instream

No

83mcm/yr <4% min flow

14

Draft - 31 August 2005

1456

LAO

Nam Leuk Hydropower

1462

SRI

North Central Province Rural Development

1544

PRC

Zhejiang-Shanxi Water Supply Project (Phase I)

1668

PHI

Southern Philippines Irrigation Sector

PROPOSED PROJECTS AND PROJECTS UNDER IMPLEMENTATION
Loan Number Country Title

Processing Schedule PPTA No. Date Loan FF Date Loan Appraisal EIA circulation and hyperlink Date Loan Approval

ONGOING
1757 SRI Water Resource Management 3030 17 Jan - 4 Feb 2000 29 Mar - 7 Apr 2000 NR 19-Sep-00

1814

PRC

West Henan Agricultural Development Project

2042

19 - 27 Jan 1999

23 Apr - 11 May 2000

4-Nov-98

19-Dec-00

15

Draft - 31 August 2005

1456

LAO

Nam Leuk Hydropower

1462

SRI

North Central Province Rural Development

1544

PRC

Zhejiang-Shanxi Water Supply Project (Phase I)

1668

PHI

Southern Philippines Irrigation Sector

PROPOSED PROJECTS AND PROJECTS UNDER IMPLEMENTATION Processing Schedule
Loan Number Country Title

Date Loan Effective

ONGOING
1757 SRI Water Resource Management 22-Oct-01

1814

PRC

West Henan Agricultural Development Project

10-Jul-01

16

Draft - 31 August 2005

1922

PRC

Hebei Zhanghewan Pumped Storage Project

144.00

18-Oct-02

Ongoing

HP I/WS

1000MW capacity avoided emissions

1995

PRC

Harbin Water Supply

100.00

11-Mar-03

Ongoing

WS

Improved water supply to 3 million people and poverty intervantion program for 325,000

2025

VIE

Phuoc Hoa Multipurpose Water Resources

90.00

27-Nov-03

Ongoing

I/WS

Improved production from 48,130 ha covering 30,200 households, salinity control for water supply to municipal areas 98MW capacity, 351 GWh annual generation, avoided emissions

2032

PRC

Gansu Clean Energy Development

35.00

5-Dec-03

Ongoing

HP

2162

LAO

GMS Nam-Theun II Hydropower Development

120.00

4-Apr-05

Ongoing

HP

1070MW capacity forex earnings from power sales to Thailand

PIPELINE
IND PRC PRC SAM Uttaranchai Power sector development Rural Electrification Development Project (formerly Renewable Energy in Rural Areas) Guiyang Integrated Water Resources Management Savaii Renewable Energy 300 100 150 10 2005 2006 2006 2006 firm medium** standby firm medium firm high HP HP WS HP 3 to 25 MW small scale per facility 25 MW for each province

17

Draft - 31 August 2005

1922

PRC

Hebei Zhanghewan Pumped Storage Project

Raise lower dam from 54 to 77m New top dam ht, ??

Dam and forex of generating and transmission equipment

Hebei Electric Power Corp., Construction Corp, Local Govt, China Development Bank, Agric. Bank of China

3,254 people

1995

PRC

Harbin Water Supply

Dam 45m 356 mcm resr.

all forex cost - treatment plant & pipeline

domestic banks

6,022 people

2025

VIE

Phuoc Hoa Multipurpose Water Resources

Dam - 28m 18.5 mcm resr.

all forex + abt 42% local cost for dams and canals

AFD

11,138 people + 1,009 households loss of ag land

2032

PRC

Gansu Clean Energy Development

Dam - 18m run of river

all forex cost - dam civil works & powerplant

domestic development companies and power 17 people bureau

2162

LAO

GMS Nam-Theun II Hydropower Development

Dam - 48m 3530 mcm resr.

Electricty of France Consortium, World Dam, power statsion and Bank, EIB, ADF, NDB, transmission lines Commercial Banks, Export Credit Agencies,

1050 families to resettle 5000 people restricted access to resources

PIPELINE
IND PRC PRC SAM Uttaranchai Power sector development Rural Electrification Development Project (formerly Renewable Energy in Rural Areas) Guiyang Integrated Water Resources Management Savaii Renewable Energy run-of-the-river run-of-the-river 20 small & 1 medium reservoir Sili River Basin

18

Draft - 31 August 2005

1922

PRC

Hebei Zhanghewan Pumped Storage Restoration Project

No

1995

PRC

Harbin Water Supply

Restoration

Minimal

2025

VIE

Phuoc Hoa Multipurpose Water Resources

Restoration

2% of population

2032

PRC

Gansu Clean Energy Development

Restoration / construction opportunities

Minor

2162

LAO

GMS Nam-Theun II Hydropower Development

Restoration and benefit sharing, improved housing

Yes

PIPELINE
IND PRC PRC SAM Uttaranchai Power sector development Rural Electrification Development Project (formerly Renewable Energy in Rural Areas) Guiyang Integrated Water Resources Management Savaii Renewable Energy

19

Draft - 31 August 2005

1922

PRC

Hebei Zhanghewan Pumped Storage Lower-instream Project Upper-offstream

No

for 6,700 ha irrig. WS 2.4 mcm/yr

1995

PRC

Harbin Water Supply

Instream

No

450 tcm/day 2007 450 tcm/day 2019

2025

VIE

Phuoc Hoa Multipurpose Water Resources

Instream

Yes - 65 cumecs capacity from Be river 48,130 ha irig to Saigon & Vam Co WS transfer Dong Basin

2032

PRC

Gansu Clean Energy Development

Instream

No

None

2162

LAO

GMS Nam-Theun II Hydropower Development

Instream

Yes - approx 220 cumecs from Nam None Theun to Xe Bang Fai Basin

PIPELINE
IND PRC PRC SAM Uttaranchai Power sector development Rural Electrification Development Project (formerly Renewable Energy in Rural Areas) Guiyang Integrated Water Resources Management Savaii Renewable Energy

20

Draft - 31 August 2005

1922

PRC

Hebei Zhanghewan Pumped Storage Project

2477

25 Feb - 12 Mar 2002

NR

23-Apr-02

18-Oct-02

1995

PRC

Harbin Water Supply

3571

14 - 29 Jun 2002

18 - 29 Sep 2002

29-Jul-02

11-Mar-03

2025

VIE

Phuoc Hoa Multipurpose Water Resources

2775

22 Apr - 10 May 2002

29 Oct - 4 Nov 2002

8-May-03

27-Nov-03

2032

PRC

Gansu Clean Energy Development

3730

15 - 24 Jan 2003

NR

30-Apr-03

5-Dec-03

2162

LAO

GMS Nam-Theun II Hydropower Development

4323

27-30 Jan 2004

31 Jan - 12 Feb 2004

29-Nov-04

4-Apr-05

PIPELINE
IND PRC PRC SAM Uttaranchai Power sector development Rural Electrification Development Project (formerly Renewable Energy in Rural Areas) Guiyang Integrated Water Resources Management Savaii Renewable Energy

21

Draft - 31 August 2005

1922

PRC

Hebei Zhanghewan Pumped Storage Project

16-Jan-04

1995

PRC

Harbin Water Supply

7-Jan-04

2025

VIE

Phuoc Hoa Multipurpose Water Resources

23-Aug-04

2032

PRC

Gansu Clean Energy Development

4-Aug-04

2162

LAO

GMS Nam-Theun II Hydropower Development

30-May-05

PIPELINE
IND PRC PRC SAM Uttaranchai Power sector development Rural Electrification Development Project (formerly Renewable Energy in Rural Areas) Guiyang Integrated Water Resources Management Savaii Renewable Energy

22

Draft - 31 August 2005
Rural Electrification and Renewable Energy Hydropower and Transmission Project Kerala Power Sector Development Project Song Bung 4 Hydropower Project MWSS - New Water Source Development

NEP AFG IND VIE Tentative depending on outcome of feasibility study

40 100 200 180

2006 2007 2007 2007

firm medium firm high standby PPTA studies TA Loan studies ongoing.

HP

HP

165 MW capacity

PHI

WS

** Pipeline list based on PPIS as of 26 August 2005

23

Draft - 31 August 2005
Rural Electrification and Renewable Energy Hydropower and Transmission Project Kerala Power Sector Development Project Song Bung 4 Hydropower Project MWSS - New Water Source Development Dam - 120m 621 mcm resr. New dam or upgrading existing Dam, power station and transmission lines 1000 people approx.

NEP AFG IND VIE Tentative depending on outcome of feasibility study

PHI

** Pipeline list based on PPIS as of 26 August 2005

24

Draft - 31 August 2005
Rural Electrification and Renewable Energy Hydropower and Transmission Project Kerala Power Sector Development Project Song Bung 4 Hydropower Project MWSS - New Water Source Development Enhamcement of indigenous communities Yes

NEP AFG IND VIE Tentative depending on outcome of feasibility study

PHI

** Pipeline list based on PPIS as of 26 August 2005

25

Draft - 31 August 2005
Rural Electrification and Renewable Energy Hydropower and Transmission Project Kerala Power Sector Development Project Song Bung 4 Hydropower Project MWSS - New Water Source Development Instream No, power diversion approx 4km downstream None

NEP AFG IND VIE Tentative depending on outcome of feasibility study

PHI

** Pipeline list based on PPIS as of 26 August 2005

26

Draft - 31 August 2005
Rural Electrification and Renewable Energy Hydropower and Transmission Project Kerala Power Sector Development Project Song Bung 4 Hydropower Project MWSS - New Water Source Development

NEP AFG IND VIE Tentative depending on outcome of feasibility study

PHI

** Pipeline list based on PPIS as of 26 August 2005

27

Draft - 31 August 2005
Rural Electrification and Renewable Energy Hydropower and Transmission Project Kerala Power Sector Development Project Song Bung 4 Hydropower Project MWSS - New Water Source Development

NEP AFG IND VIE Tentative depending on outcome of feasibility study

PHI

** Pipeline list based on PPIS as of 26 August 2005

28


				
DOCUMENT INFO
Shared By:
Tags: dams, -Dams
Stats:
views:96
posted:11/28/2009
language:English
pages:28
Description: dams,-Dams-since-1994---Asian-Development-Bank-(ADB)---Fighting-