CDWR PUBLIC S-5 Supply Forms 2-17-09.xls - California Energy by changcheng2

VIEWS: 6 PAGES: 24

									                            Electricity Resource Planning Form S-5
                     Bilateral Contracts and Power Purchase Agreements

     Filing LSE:                    California Department of Water Resources
     Date:                          February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.
CEC staff identified highlighted data as publicly available as of May 19, 2009.

Supplier / Seller:                  Morgan Stanley Capital Group Inc.

Start Date:

Expiration Date:                    December 31, 2010

Contract / Agreement Capacity:

Scheduling Coordinator:

Fuel Type:

Delivery Point(s):

Locational Attributes of Unit(s):

Contract / Agreement Product(s):


Availability of Products:


Must Take:

Generating Unit(s) Specified:

Capacity of the Unit(s):

Availability of the Unit(s):

Unit Contingent / LD Contract:

Firm:

Contract / Agreement Type:
    Filing LSE:                   California Department of Water Resources
    Date:                         February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.

Transmission Contingent & Path:

Termination & Extension Rights:

Performance Requirements:

Notes:
fornia Department of Water Resources
ruary 13, 2009




gan Stanley Capital Group Inc.
                            Electricity Resource Planning Form S-5
                     Bilateral Contracts and Power Purchase Agreements

     Filing LSE:                    California Department of Water Resources
     Date:                          February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.
CEC staff identified highlighted data as publicly available as of May 19, 2009.

Supplier / Seller:                  Morgan Stanley Capital Group Inc.

Start Date:

Expiration Date:                    December 31, 2015

Contract / Agreement Capacity:

Scheduling Coordinator:

Fuel Type:

Delivery Point(s):

Locational Attributes of Unit(s):

Contract / Agreement Product(s):


Availability of Products:


Must Take:

Generating Unit(s) Specified:

Capacity of the Unit(s):

Availability of the Unit(s):

Unit Contingent / LD Contract:

Firm:

Contract / Agreement Type:
    Filing LSE:                   California Department of Water Resources
    Date:                         February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.

Transmission Contingent & Path:

Termination & Extension Rights:

Performance Requirements:

Notes:
nia Department of Water Resources
ry 13, 2009




n Stanley Capital Group Inc.
                        Electricity Resource Planning Form S-5
                 Bilateral Contracts and Power Purchase Agreements

     Filing LSE:                    California Department of Water Resources
     Date:                          February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.
CEC staff identified highlighted data as publicly available as of May 19, 2009.

Supplier / Seller:                  Kings River Conservation District (KRCD)

Start Date:                         1984

Expiration Date:                    March 31, 2034

Contract / Agreement Capacity:      165 MW

Scheduling Coordinator:

Fuel Type:                          Hydroelectric

Delivery Point(s):                  CAISO, NP15


Locational Attributes of Unit(s):   CAISO NP15


Contract / Agreement Product(s):

Availability of Products:

Must Take:

Generating Unit(s) Specified:       Pine Flat Powerplant

Capacity of the Unit(s):            165 MW

Availability of the Unit(s):

Unit Contingent / LD Contract:      Unit Contingent, Pine Flat Powerplant

Firm:
    Filing LSE:                   California Department of Water Resources
    Date:                         February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.
Contract / Agreement Type:

Transmission Contingent & Path:


Termination & Extension Rights:


Performance Requirements:

Notes:
California Department of Water Resources
February 13, 2009




Kings River Conservation District (KRCD)




Hydroelectric

CAISO, NP15


CAISO NP15




Pine Flat Powerplant




Unit Contingent, Pine Flat Powerplant
                      Electricity Resource Planning Form S-5
               Bilateral Contracts and Power Purchase Agreements

     Filing LSE:                    California Department of Water Resources
     Date:                          February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.
CEC staff identified highlighted data as publicly available as of May 19, 2009.

Supplier / Seller:                  NV Energy (formerly Nevada Power Company)

Start Date:                         1983

Expiration Date:                    July 25, 2013

Contract / Agreement Capacity:

Scheduling Coordinator:

Fuel Type:                          Coal

Delivery Point(s):                  CAISO SP15
                                    El Dorado

Locational Attributes of Unit(s):   WALC LC1
                                    Reid Gardner #4, Nevada Power, Moapa Valley, Nevada

Contract / Agreement Product(s):

Availability of Products:

Must Take:

Generating Unit(s) Specified:       Reid Gardner Unit #4

Capacity of the Unit(s):


Availability of the Unit(s):


Unit Contingent / LD Contract:      Unit Contingent, Reid Gardner Unit #4

Firm:
    Filing LSE:                   California Department of Water Resources
    Date:                         February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.

Contract / Agreement Type:

Transmission Contingent & Path:

Termination & Extension Rights:   Contract will terminate in 2013.

Performance Requirements:


Notes:
California Department of Water Resources
February 13, 2009




NV Energy (formerly Nevada Power Company)



July 25, 2013




Coal

CAISO SP15
El Dorado

WALC LC1
Reid Gardner #4, Nevada Power, Moapa Valley, Nevada




Reid Gardner Unit #4




Unit Contingent, Reid Gardner Unit #4
Contract will terminate in 2013.
                      Electricity Resource Planning Form S-5
               Bilateral Contracts and Power Purchase Agreements

     Filing LSE:                    California Department of Water Resources
     Date:                          February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.
CEC staff identified highlighted data as publicly available as of May 19, 2009.

Supplier / Seller:                  Metropolitan Water District of Southern California (MWD)

Start Date:                         Apirl 1, 1983

Expiration Date:                    Indefinite

Contract / Agreement Capacity:      29.87 MW

Scheduling Coordinator:

Fuel Type:                          Hydroelectric

Delivery Point(s):                  CAISO SP15 (at the power plants)

Locational Attributes of 5 Units:   CAISO SP15




Contract / Agreement Product(s):

Availability of Products:

Must Take:

Generating Unit(s) Specified:



Capacity of the Unit(s):



Availability of the Unit(s):
    Filing LSE:                   California Department of Water Resources
    Date:                         February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.

Unit Contingent / LD Contract:

Firm:

Contract / Agreement Type:

Transmission Contingent & Path:

Termination & Extension Rights:   Termination in whole or part by either party with 10 years notice.

Performance Requirements:

Notes:
California Department of Water Resources
February 13, 2009




Metropolitan Water District of Southern California (MWD)




Hydroelectric

CAISO SP15 (at the power plants)

CAISO SP15
Termination in whole or part by either party with 10 years notice.
                        Electricity Resource Planning Form S-5
                 Bilateral Contracts and Power Purchase Agreements

     Filing LSE:                    California Department of Water Resources
     Date:                          February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.
CEC staff identified highlighted data as publicly available as of May 19, 2009.

Supplier / Seller:                  Los Angeles Department of Water & Power

Start Date:                         1971

Expiration Date:

Contract / Agreement Capacity:

Scheduling Coordinator:

Fuel Type:                          Hydroelectric

Delivery Point(s):                  LADWP, CAISO SP15
                                    Sylmar switching station

Locational Attributes of Unit(s):   LADWP, CAISO SP15
                                    Castaic, CA

Contract / Agreement Product(s):    Forward energy and capacity

Availability of Products:

Must Take:

Generating Unit(s) Specified:       Castaic Powerplant

Capacity of the Unit(s):

Availability of the Unit(s):        Hydrology and water operations dependent

Unit Contingent / LD Contract:      Unit Contingent, Castaic Powerplant

Firm:
    Filing LSE:                   California Department of Water Resources
    Date:                         February 13, 2009

CDWR designated this worksheet confidential on May 15, 2009.
Contract / Agreement Type:      Joint development; shared benefits.

Transmission Contingent & Path:


Termination & Extension Rights:


Performance Requirements:

Notes:
California Department of Water Resources
February 13, 2009




Los Angeles Department of Water & Power




Hydroelectric

LADWP, CAISO SP15
Sylmar switching station

LADWP, CAISO SP15
Castaic, CA

Forward energy and capacity




Castaic Powerplant



Hydrology and water operations dependent

Unit Contingent, Castaic Powerplant
Joint development; shared benefits.

								
To top