									W4 ON REGENT STREET NEWSLETTER: September 2013

Dear Neighbour
W4 Regent Street – a development by The Crown Estate, managed by Exemplar

During September, we have made significant progress with the external glass cladding in New Burlington Mews which
is now up to Level 3. This has allowed us to start the internal finishes on these floors with dry lining to the ‘core’
areas and fit out of the toilet areas with the mechanical and electrical items, ceilings, walls, terrazzo troughs and
cubicles now installed to levels 1 and 2.

The Regent Street roof has been completed with slates installed and lead flashing which has allowed us to begin
dismantling the scaffold. The windows and frames and much of the glazing have been installed up to Level 4 on the
majority of the retained and re-built facades.

Also, the highways works on Regent Street and New Burlington Street have begun in earnest, with new paving being
installed along both streets in preparation for the retail units opening in the next few months.




 New cladding installed in New Burlington Mews                 Re-build of the 15/16 New Burlington Street façade




 New render applied in the vaults                              Construction of the new mansard roof to 13/14 New Burlington
                                                               Street
W4 ON REGENT STREET NEWSLETTER: September 2013
Progress on site during August 2013:

• Continuation of the re-build of the 15/16 New Burlington Street façade and new façade to 12 New
  Burlington Street

• Construction of the new cladding to New Burlington Mews

• On-going contraction of the mansard roofs, the new cupola steelwork and plant installation

• Continued installation of shop fronts as well as the timber and metal windows

• Screeding and terrazzo tiling to office floor entrances and toilets

• On-going installation of the hand-made tile wall in the main atrium

• Continuation of external works to Regent and New Burlington Street



Over the coming month, our works will include:

• Continued installation of plant and pipework to the basement and up to sixth floor level

• Continued reconstruction of the façade at 15/16 New Burlington Street

• Removal of the façade retention system on New Burlington Street

• Fit out of the new reception

• Construction of the new external landscape to New Burlington Mews



As always, if you have any queries related to the works please contact either Jon Mingard (Project Manager)
on 07789 956541 or email jon.mingard@macegroup.com, alternatively Laurie Furst (Community Liaison) on
07717 717154 or laurie.furst@macegroup.com.

Kind regards




Jon Mingard- Project Manager, Mace

								