					   September 2013

Overnight concrete pour on Thursday 26 September
As part of the work to build the new Crossrail Western Ticket Hall at                                    Duration of work
Bond Street, our contractor Costain Skanska Joint Venture will be                                     Thursday 26 September
undertaking a large volume concrete pour on the evening of Thursday                                    2013 for one night
26 September 2013.
                                                                                                      From 19:00 on Thursday
We will commence the pour at 19:00 at a rate of four concrete trucks                                   evening to 09:00 Friday
                                                                                                       morning
per hour increasing to eight concrete trucks per hour after 21:00. We
anticipate that all works will be completed by 09:00 the next day.                                       What to expect
Adequate lighting is necessary to ensure a safe working environment.                                  Use of two jet washes to
CSJV will ensure that adequate lighting is provided to the site as and                                 clean vehicles leaving
                                                                                                       site.
when is required. The flood lights will be directed downwards and
inwards so as to mitigate any potential impact to local residents.                                    Use of two concrete
                                                                                                       pumps
                                                                                                      Steady flow of concrete
                                                                                                       trucks overnight.
                                                                                                      Use of lights for
                                                                                                       illumination of working
                                                                                                       areas.
                                                                                                      Traffic management in
                                                                                                       operation.
                                                                                                      Use of a concrete
                                                                                                       testing station

                                                                                                         What we will do
                                                                                                      Ensure the footpaths
                                                                                                       around the worksites
                                                                                                       remain open at all times
                                                                                                      Provide vehicle access
                                                                                                       as required
                                                                                                      Ensure access to
                                                                                                       properties are
We will assist with any special/delivery needs allowing access if                                      maintained
required. We encourage you to call us in advance of these works so                                    Keep noise down to
that we can discuss any necessary arrangements.                                                        minimum
                                                                                                      Ensure site lighting is
                                                                                                       directed downwards and
                                                                                                       into the site.

We apologise in advance for any inconvenience caused as a result of our works. If you have any queries, please contact the
Crossrail 24-hour public helpdesk on 0345 602 3813 or email helpdesk@crossrail.co.uk
Please contact the Crossrail helpdesk if you would like to receive works information via email in advance of the printed copy.
Alternatively you can sign up to receive email notifications about stations of interest by visiting www.crossrail.co.uk/contact
Crossrail services will commence through the central tunnelled section in late 2018
followed by a phased introduction of services along the rest of the Crossrail route.         C411-XRL-Z1-XBU-C125_WS086-50004
About Crossrail
Crossrail is the new high frequency, convenient and
accessible railway for London and the South East.

When the service opens Crossrail trains will travel from
Maidenhead and Heathrow in the west to Shenfield
and Abbey Wood in the east via new twin tunnels
under central London. It will link Heathrow Airport, the
West End, the City of London and Canary Wharf.

Travelling on Crossrail will dramatically reduce journey
times:


                                                         With
 Example journey times in minutes           Now
                                                       Crossrail

 Slough – Tottenham Court Road               55            32

 Romford – Bond Street                       43            35

 Whitechapel – Abbey Wood                    49            15

 Ealing Broadway – Farringdon                38            17

 Heathrow – Liverpool Street                 55            32

 Heathrow – Canary Wharf                     71            40

 Maidenhead – Liverpool Street               71            46

 Paddington - Canary Wharf                   30            16



Drop in to our Visitor Information Centres
West End 16-18 St Giles High Street, WC2H
8LN
Open Tuesdays and Thursdays 11.00 to 19.00
Whitechapel Idea Store, 321 Whitechapel Road,
E1 1BU Open Mondays and Wednesdays 11.00
to 19.00

Bond Street Community Liaison Panel
Crossrail run a quarterly meeting to keep local
community representatives informed of the works
happening in the area. For more information please
contact crossrailliaisonpanels@crossrail.co.uk


                  QR Code
                  Scan with your mobile device to be taken to
                  the ‘Near You’ section of our website



We apologise in advance for any inconvenience caused as a result of our works. If you have any queries, please contact the
Crossrail 24-hour public helpdesk on 0345 602 3813 or email helpdesk@crossrail.co.uk
Please contact the Crossrail helpdesk if you would like to receive works information via email in advance of the printed copy.
Alternatively you can sign up to receive email notifications about stations of interest by visiting www.crossrail.co.uk/contact
Crossrail services will commence through the central tunnelled section in late 2018
followed by a phased introduction of services along the rest of the Crossrail route.         C411-XRL-Z1-XBU-C125_WS086-50004

				
DOCUMENT INFO
Shared By:
Categories:
Tags:
Stats:
views:0
posted:9/16/2013
language:English
pages:2