Solar Process Heat in Spain 2011

Document Sample
Solar Process Heat in Spain 2011 Powered By Docstoc
					Solar Process Heat in Spain
  markets and examples


         Francisco Puente, ESCAN,S.A.
            fpuente@escansa.com
             http://www.escansa.com




Conference Solar Process Heat, 03 March



        SOPRO,Wels, 3March2011            16
                   Solar Process Heat in Spain
                     markets and examples

                       Policies
High level of dependance on foreign energy suppliers, and
increasing (energy imported up to 80% national consumption)




                         SOPRO,Wels, 3March2011           17
                             Solar Process Heat in Spain
                               markets and examples

                                 Policies
          Obligations of Directive 2009/28/EC related to RES




RES for electricity (ktoe)

RES for heating (ktoe)

RES for transport (ktoe)


RES TOTAL (ktoe)

RES (% of primary
energy)


                                   SOPRO,Wels, 3March2011      18
                   Solar Process Heat in Spain
                     markets and examples

                        Policies
National Action Plan for RES 2011-2020
        Solar Thermal for Heating and Cooling, in ktoe


                                    x4




                          SOPRO,Wels, 3March2011         19
                 Solar Process Heat in Spain
                   markets and examples

                     Policies
National Action Plan for RES 2011-2020




                       SOPRO,Wels, 3March2011   20
                          Solar Process Heat in Spain
                            markets and examples

                             Situation
Solar Thermal Development during last 6 years, in m2
3.000.000

2.500.000

2.000.000
                                                           Solar Thermal Energy in
1.500.000                                                  Spain Yearly Installed (m2)
                                                           Solar Thermal Energy in
1.000.000                                                  Spain Accumulated (m2)

 500.000                                                Building crisis
                                                        in Spain
       0
            2005   2006    2007    2008   2009   2010



                                  SOPRO,Wels, 3March2011                                 21
                          Solar Process Heat in Spain
                            markets and examples

                             Situation
Solar Thermal Development during last 6 years, in kWt
1.800.000
1.600.000
1.400.000
1.200.000
1.000.000                                                  Yearly Installed (kWt)

  800.000                                                  Accumulated (kWt)
  600.000
  400.000
                                                        Building crisis
  200.000                                               in Spain
       0
            2005   2006    2007    2008   2009   2010



                                  SOPRO,Wels, 3March2011                            22
                        Solar Process Heat in Spain
                          markets and examples

                             Situation
National Action Plan for RES 2011-2020

Main pillars for the development of solar energy in Spain in the next ten
years:
• solar thermal energy for building sector, following the current
regulation:
    • obligation of solar thermal for hot sanitary water in new buildings
    and solar PV in some circumstances
    • solar heating and cooling
• solar thermal energy for industries
• solar thermoelectric energy
                                  SOPRO,Wels, 3March2011                    23
                        Solar Process Heat in Spain
                          markets and examples

                           Situation
Potential of solar process heat in Spain
Study developed in 2010


  Technical potential                         Economic potential
  (without economic                           (with support)
  considerations)                             8,9 TWh heat
  59,9 TWh heat                               14,4 million m2
  97,4 million m2




                              SOPRO,Wels, 3March2011               24
                           Solar Process Heat in Spain
                             markets and examples

                                Projects
                               Project 1


 Name: Solar thermal installation for
Truck vessels washing
 Place: Villamuriel de Cerrato (Palencia)
 System: 72 solar collectors of 1,94 m2
(140 m2) and two 5.000 l accumulators
(10.000 l).
Brief description: the system is part of a
new washing system, constituted by a 2
ways truck vessels washing.



                                   SOPRO,Wels, 3March2011   25
Solar Process Heat in Spain
  markets and examples

    Projects
   Project 1




      SOPRO,Wels, 3March2011   26
                        Solar Process Heat in Spain
                          markets and examples

                                   Projects
                               Project 1

kW h             DEMANDA SATISFECHA CON LA INSTALACIÓN SOLAR
18.000

16.000

14.000

12.000

10.000

 8.000

 6.000

 4.000

 2.000

       0
           Ene   Feb   Mar   Abr   May   Jun   Jul   Ago   Sep   Oct   Nov   Dic
                                   Demanda     Aporte Solar




                                    SOPRO,Wels, 3March2011                         27
            Solar Process Heat in Spain
              markets and examples

                Projects
               Project 1

Investment         Subsidy          Final Cost
 85.374 €          34.150 €             51.224 €


        Savings            Pay-back
       7.161 €/year           7 years




                  SOPRO,Wels, 3March2011           28
                          Solar Process Heat in Spain
                            markets and examples

                                Projects
                              Project 2



 Name: Solar thermal installation for car
industry
 Place: Valladolid
 System: 120 solar collectors of 2,03 m2
(244 m2 ) and three 5.000 l accumulators
(total 15.000 l).
Brief description: the system provides
heat to the painting process




                                  SOPRO,Wels, 3March2011   29
Solar Process Heat in Spain
  markets and examples

    Projects
   Project 2




      SOPRO,Wels, 3March2011   30
                  Solar Process Heat in Spain
                    markets and examples

                         Projects
                        Project 2

             DEMANDA ENERGÉTICA / APORTE SOLAR (MWh/mes)
30
25

20
15
10

5
0
     1   2    3     4      5     6      7      8      9    10   11   12

                   Demanda (MWh/mes)   Aporte (MWh/mes)

                           SOPRO,Wels, 3March2011                         31
         Solar Process Heat in Spain
           markets and examples

              Projects
             Project 2

Investment         Subsidy        Final Cost
 147.577 €         45.076 €        102.501 €


         Savings          Pay-back
       9.200 €/year       11 years




                SOPRO,Wels, 3March2011         32
                            Solar Process Heat in Spain
                              markets and examples

                                Projects
                              Project 3



 Name: Solar thermal installation for
food industry (chocolate)
 Place: Alcaudete (Jaén)
 System: 132 solar collectors of 2,01 m2
(265 m2 ) and one 15.000 l accumulator.
Brief description: the system provides
heat to the raw material preparation and
for the cleaning process




                                  SOPRO,Wels, 3March2011   33
            Solar Process Heat in Spain
              markets and examples

                Projects
Project 3




                  SOPRO,Wels, 3March2011   34
                                   Solar Process Heat in Spain
                                     markets and examples

                                              Projects
                                         Project 3

                                      Demanda energética y aporte solar

      40.000
                                         DEMANDA                      SOLAR
      35.000

      30.000

      25.000
kWh




      20.000

      15.000

      10.000

       5.000

          0




                                                                                                     e
                                                                lio
                                                          o
                           o
                o




                                 zo


                                        ril




                                                                                                    e
                                                                                     e
                                                 o




                                                                                                   re
                                                                           to




                                                                                                  br
                         er




                                                       ni
             er




                                                                                                  br
                                                                                   br
                                              ay
                                      Ab




                                                              Ju




                                                                                                ub
                                                                        os
                               ar




                                                     Ju




                                                                                                m
                      br
           En




                                                                                               em
                                                                                   m
                                              M
                               M




                                                                      Ag




                                                                                              ct


                                                                                             vie
                    Fe




                                                                                 ie




                                                                                            ci
                                                                                           O
                                                                              pt




                                                                                         No


                                                                                         Di
                                                                            Se


                                                              Mes




                                                  SOPRO,Wels, 3March2011                                 35
         Solar Process Heat in Spain
           markets and examples

              Projects
             Project 3

Investment         Subsidy          Final Cost
 180.000 €         70.000 €             110.000 €


         Savings          Pay-back
      14.000 €/year           8 years




                SOPRO,Wels, 3March2011              36
Solar Process Heat in Spain
  markets and examples

Dissemination




      SOPRO,Wels, 3March2011   37
            Solar Process Heat in Spain
              markets and examples



              THANK YOU !


You are welcomed to ask any question on Spanish
situation:
           Francisco Puente, ESCAN,S.A.
              fpuente@escansa.com
               http://www.escansa.com




                   SOPRO,Wels, 3March2011         38

				