									MINNESOTA SPORTS FACILITIES AUTHORITY
MINNESOTA MULTI‐PURPOSE STADIUM
CRITICAL 120 DAY MILESTONES
AUGUST 23, 2013

UA ‐ DA ‐ FINANCING

ACTIVITY                                                                                        DATE                         PREDECESSORS


Vikings Agree to Resume Negotiations on Development Agreement (DA) and Use Agreement (UA)      8/26/2013
Deadline to Receive Requested Due Diligence Information                                        9/1/2013
Finalize DA and UA                                                                             9/15/2013   Resumption of Negotiations
MSFA to Complete Due Diligence                                                                 9/15/2013   Two weeks after Receipt of All Documents
MSFA Board Approval Deadline for DA and UA                                                     9/27/2013   Finalize DA and UA and Complete Due Diligence
MSFA Board Approval Deadline for Employee Assistance Firm (EAF) Contract                       9/27/2013
MSFA Board Approval Deadline for East Village Parking Agreement & Park Use Term Sheet          9/27/2013
MSFA Board Approval Deadline for Guaranteed Maximum Price (GMP) Amendment                      11/1/2013   Execute DA and UA
Close on Team/Private Financing                                                                11/2/2013   Execute DA, UA and GMP
Start Construction                                                                             11/7/2013   Execute GMP and Close on Team Financing
State Bond Proceeds Available by                                                              11/30/2013   Close on Team Financing
Substantial Completion                                                                         7/1/2016




CONSTRUCTION

ACTIVITY                                                                                        DATE                         PREDECESSORS


Provide Final Direction to HKS for GMP Design Documents                                        9/9/2013
HKS Issues Final GMP Design Documents                                                         10/1/2013    Final Direction
Mortenson submits GMP Proposal                                                                10/17/2013   Final GMP Design Documents
MSFA Board Approves GMP Amendment                                                              11/1/2013   Receive and Negotiate GMP
Start Construction                                                                             11/7/2013   Execute GMP
Begin Demolition of Metrodome                                                                  2/1/2014
Substantial Completion                                                                         7/1/2016




                                                                                Page 1 of 1

								