					Facility Maintenance
                              
Typical Job Categories for Maintenance
 
Plant Maintenance
Electricians                       
                        Bricklayers                   
                                           Heavy Movers
Tinsmiths                      
                        Painters                        
                                           Window Washers
Welders                        
                        Glaziers                  
                                           Janitors
            
Pipe fitters                          
                        Concrete Workers   Gardeners
                  
Fire/emergency People             
                        Carpenters
Steam fitters           Millwrights 
 
Machine Maintenance
                
General Mechanics
         
Machinists
                  
Sheet Metal Workers
       
Welders
                    
Electronic Technician
Computer Technicians
MAINTENANCE PROCEDURES
·        Emergency Maintenance
·        Preventative Maintenance
                Emergency – Standby Capacity




Probability that Number of Machines will be broken: Total =100%
      Cost to Rent Number of Machines Out of Order
    We have a line with 50 robot GMA welders
·The cost to do a preventative maintenance overhaul 
         on each machine is $200/machine
·Average breakdown repair costs are $700/machine

Objective:  Calculate the cost if we elect to repair only 
when a machine breaks down.  How much must we set 
                  aside each month?
       Probability of 
       Breakdown as a 
       function of months 
       after overhaul of all 
       machines.
       They Add to 100%
       The months time the 
       probability results in 
       the partial expected 
       time for failure.
        Since the partial 
        probabilities add to 
        100%, the partial times 
        add to the expect time 
1.00
        for a failure = 8.42 
        months
The cost of repair-on-breakdown then = 
($700/machine) /(8.42 months) * 50 machines
                            = $4157/month
 
Thus, we better place $4157 in a fund every 
month if we decide to do repair-on-
breakdown policy.  
    We have a line with 50 robot GMA welders
·The cost to do a preventative maintenance overhaul 
         on each machine is $200/machine
·Average breakdown repair costs are $700/machine

  Objective:  Calculate if preventative maintenance 
should be done and if so what the schedule should be.
       Calculate Cost for Preventative
               Maintenance
 For every preventative maintenance overhaul we do it 
                       will cost:
        = $200/machine  * 50 machines  = $10,000


If we do a preventative maintenance every month, it will 
                   cost $10,000/month
 If we do a preventative maintenance every 2 months, it 
               will cost $5,000/month, etc.
Even though we do preventative maintenance, we 
can expect some breakdowns to occur anyway.  
We can calculate the number of expected 
breakdowns each month using the following 
equation.
 


          Where:
                   Bn = expected number of breakdowns
                   N = number of machines
                   Pn = probability of machine 
                           breakdown in period n

                       ®    That is, 2.5 breakdowns in the 
                       first month




               ®    That is, 3.63 breakdown in first 2 
               months
                                                                        PLOT
Expected Cost = Ave. Number * $700/machine = 2.5 * $700 = $1750
Total Cost = Expected Cost + Prev. Maint. Cost = 1750 + 10000 = 11750
$4157

				