WEEKLY INSPECTOR'S FORECAST

Document Sample
WEEKLY INSPECTOR'S FORECAST Powered By Docstoc
					WEEKLY INSPECTOR’S FORECAST
October 24, 2009

FOR WEEK ENDING:                                                                            October 25, 2009
PROJECT NAME:                                                                               Olive Branch and Morgantown Rd.
CONTRACT NO.:                                                                               R-29439-A
PROJECT LOCATION:                                                                           Greenwood, Indiana
OWNER:                                                                                      Johnson County Highway Department
CONTRACTOR:                                                                                 Crider & Crider Inc.
FIELD MANAGER:                                                                              Jeff Reeves
RESIDENT PROJECT REPRESENTATIVE:                                                            Laura Hemming
PROJECT COMPLETION:                                                                         31% (through 8/15/09)
INSPECTION COMPLETION:                                                                      38% (through 8/30/09)
NOTICE TO PROCEED:                                                                          June 9, 2009
FINAL COMPLETION:                                                                           November 10, 2009
________________________________________________________________________
The following notes detail the weekly project status as of the date noted. Notes may include work previously
performed and projected work as determined by the project representative.

Status of Work as of 10/18/2009

Crider & Crider has completed the placement of the Conspan bridge structure. Flowable fill was used to backfill
around the structure. The crew placed the flowable in multiple large pours starting at early morning hours to
complete the work. Crider & Crider has completed most of the concrete driveways. AT&T was not onsite for
relocation work.

Notes on Daily Work for week of 10/19/2009 to 10/25/2009

Crider & Crider set the last of the wingwalls and completed the flowable backfill method. Signal Construction
was onsite to set their conduit. Crider & Crider worked to fine grade the intersection and complete the subgrade
for intermediate paving operations. E&B Paving was onsite to place the first lift of intermediate HMA along
Morgantown Rd and to the west on Olive Branch Rd. Crider & Crider worked to install the 15” RCP storm sewer
to tie into the conspan structure as part of change order #2. Crew then prepped this area for asphalt placement.
AT&T was not onsite for relocation work although a meeting was held to discuss when work would be completed.

Projected Work Forecast and Staffing for week ending 11/01/2009

Crider & Crider will work on grading of slopes and other work to tidy up the intersection as well as prep
driveways for asphalt per plans. E&B paving will be onsite to continue and complete placement of the
intermediate HMA mix. Signal Construction will be onsite to follow E&B with the placement of the signal at the
intersection. Earth Images will also be onsite to work on landscaping.

Structurepoint staffing includes one part time Field Manager, one full time RPR, and one full time Inspector with
no changes required at this time.


                                                                  -END OF REPORT-

                                                            American Structurepoint, Inc.
                                                              7260 Shadeland Station
                                                              Indianapolis, IN 46256



P:\IN2008\1380\G. Construction\Weekly Forecasts\IN20081380.CI.RPT.2009-10-10.Weekly Forecast WE Oct 11.Olive Branch and Morgantown Rd.LJH.doc
                                    OLIVE BRANCH AND MORGANTOWN ROAD PHOTOS




              Grading and placement of #53 stone for pavement grade (looking west on Olive Branch).




                                Grading on top of the conspan structure prior to stone placement.



P:\IN2008\1380\G. Construction\Weekly Forecasts\IN20081380.CI.RPT.2009-10-10.Weekly Forecast WE Oct 11.Olive Branch and Morgantown Rd.LJH.doc
                                    OLIVE BRANCH AND MORGANTOWN ROAD PHOTOS




                                  Grading and stone placement looking east on Olive Branch Rd.




            ABC Cutting Contractors cutting the side of the conspan structure for 15” RCP connection.