					                                          Summary of Component - C Works as at 30.06.2012

Summary of Road Works

                             Jaffna             Kilinochchi          Mullaitivu           Vavuniya              Mannar                    Total
        Detail          Length   Completed   Length   Completed   Length   Completed   Length   Completed   Length   Completed   Length       Completed
                         (km)      (km)       (km)      (km)       (km)      (km)       (km)      (km)       (km)      (km)       (km)          (km)

Roads                   94.35     63.78      77.98      55.12     186.98    151.32     181.05    156.05     70.80     50.00      611.16           476.27


        Total           94.35     63.78      77.98      55.12     186.98    151.32     181.05    156.05     70.80     50.00      611.16           476.27




                                                                     Page 21
                                                        Ministry of Economic Development
                                                         Emergency Northern Recovery Project
                                                                    Component - C

                                                       Summary of Progress as at 30.06.2012

                                                   Cumulative              Cumulative                           Physical Progress (%)
                                         Total
                              No of                Expenditure Expenditure Expenditure
                                       Estimated
  Sector          District    Works                    as at      2012         as at                               Ongoing Works
                                         Cost
                             Awarded                31.12.2011  (Rs. Mn)    30.06.2012 Completed                                                    Terminated
                                         (Mn)                                                      0 - 25    25 - 50   50 - 75    75 - 99   Total
                                                     (Rs. Mn)                  (Mn)

              Jaffna           15       463.32       231.04      71.15      302.19        9          1         1              -     3        5          1

              Kilinochchi      13       126.56       59.24       16.74       75.98        8              -     1              -         -    1          4

Roads &
              Mullaitivu       27       361.18       222.35      40.80      263.15        20             -     1         1          5        7              -
Bridges

              Vavuniya         19       130.93       73.63       22.95       96.58        18             -     1              -         -    1              -

              Mannar           11       110.64       71.06        6.43       77.49        9          1         1              -         -    2              -

           Sub Total           85      1,192.63      657.32      158.08     815.40        64         2         5          1         8        16         5




                                                                              Page 16
                                                                              Ministry of Economic Development
                                                                               Progress of Jaffna District as at 30.06.2012


                                                                                                                                        Physical
                                                                                                                                                                Cumulative
                                                                                                                                       Target for      Total                      Progress (%)
                                                                                                                                                                Expenditure
                                                                                                                                       the Entire    Estimate
S.No                     Name of Work                           DS Division   Implementing Agency         Name of Contractor                                        as at
                                                                                                                                        Project        Cost
                                                                                                                                                                 30.06.2012
                                                                                                                                         Period      (Rs. Mn)                   Phy          Fin
                                                                                                                                                                  (Rs. Mn)
                                                                                                                                      (km/Nos/etc)

Roads & Bridges

       Rehabilitation of Roads in Maruthankerny Package-
  1                                                          Maruthankerny    R/ACLG                  Master Builders                    5 km         22.63        12.76        95%          56%
       01
       Rehabilitation of Roads in Maruthankerny Package-
  2                                                          Maruthankerny    R/ACLG                  Jathur Enterprises                10.8 km       33.46        30.79        100%         92%
       02
       Reconstruction of Roads in Maruthankerny Jaffna
  3                                                          Maruthankerny    R/ACLG                  Master Builders                    5.3 km       26.53        7.43         25%          28%
       Package 3
       Rehabilitation of Internal Roads in Mathurankerny
  4                                                          Maruthankerny    R/ACLG                  A Group Construction               8.3 km       44.31        31.92        100%         72%
       Package 4, Jaffna
       Rehabilitation of Internal Roads in Maruthankerney,                                            SMA Construction,
  5                                                          Maruthankerny    R/ACLG                                                     6.5 km       35.28        0.30       Terminated     1%
       Jaffna- Package 5                                                                              thalawatugoda
       Rehabilitation of Internal Roads in Maruthankerney,
  6                                                          Maruthankerny    R/ACLG                  Shakthi Civil Construction         5.5 km       33.98        23.05        85%          68%
       Jaffna- Package 6
       Rehabilitation of Internal Roads in Maruthankerney,
  7                                                          Maruthankerny    R/ACLG                  SMA Construction                   5.1 km       33.09        27.36        100%         83%
       Jaffna- Package 7
       Rehabilitation of Internal Roads in Jaffna MC Area,                                            Eurivile Engineers And
  8                                                          Jaffna Town      ACLG                                                       2.4 km       20.47        16.96        100%         83%
       Jaffna                                                                                         Contractors

       Repair of Interior Roads within the Jaffna Teaching
  9                                                          Jaffna Town      GA, Jaffna              HDS, Teaching Hospital Jaffna     0.25 km        3.02        2.78         100%         92%
       Hospital

       Rehabilitation of Internal Road in Valikamam North,
 10                                                        Tellipalai         ACLG                    Master Builders                    6.9 km       30.24        20.37        80%          67%
       Jaffna- Package 1
       Rehabilitation of Internal Roads in Valikamam North,
 11                                                         Tellipalai        ACLG                    Leading Crusher Works              5.7 km       24.75        20.93        100%         85%
       Jaffna- Package 2
       Rehabilitation of Internal Roads in Valikamam North,
 12                                                         Tellipalai        ACLG                    Leading Crusher Works              5.3 km       21.03        16.88        100%         80%
       Jaffna- Package 3
       Rehabilitation of Internal Roads in Valimamam East,
 13                                                        Kopay              ACLG                    Koneswaran Engineering             7.9 km       37.84        30.05        100%         79%
       Jaffna




                                                                                                    Page 23
                                                                                                                               Physical
                                                                                                                                                       Cumulative
                                                                                                                              Target for      Total                   Progress (%)
                                                                                                                                                       Expenditure
                                                                                                                              the Entire    Estimate
S.No                     Name of Work                           DS Division   Implementing Agency       Name of Contractor                                 as at
                                                                                                                               Project        Cost
                                                                                                                                                        30.06.2012
                                                                                                                                Period      (Rs. Mn)                 Phy         Fin
                                                                                                                                                         (Rs. Mn)
                                                                                                                             (km/Nos/etc)
       Rehabilitation of Internal Roads in Valikamam South,
 14                                                         Uduvil            ACLG                   Benaal construction       10.7 km       45.52        40.78      100%        90%
       Jaffna
       Rehabilitation of Internal Roads in Chavakachcheri,
 15                                                          Chavakachcheri   ACLG                   Benaal construction        8.7 km       51.18        19.80      48%         39%
       Jaffna

             Sub Total - Roads & Bridges                                                                                      94.35 km      463.33       302.16




                                                                                                    Page 24
                                   Ministry of Economic Development
                                  Progress of Kilinochchi District as at 30.06.2012


                                                                                         Physical                  Cumulative
                                                                                                                                       Progress
                                                                                      Target for the     Total     Expenditure
S.No   Name of Work   DS Division Implementing Agency       Name of Contractor        Entire Project Estimate Cost     as at
                                                                                          Period       (Rs. Mn)     30.06.2012
                                                                                       (km/Nos/etc)                  (Rs. Mn)    Phy              Fin




                                                           Page 32
                                                                                                                                   Physical                  Cumulative
                                                                                                                                                                                   Progress
                                                                                                                                Target for the     Total     Expenditure
S.No                     Name of Work                         DS Division Implementing Agency       Name of Contractor          Entire Project Estimate Cost     as at
                                                                                                                                    Period       (Rs. Mn)     30.06.2012
                                                                                                                                 (km/Nos/etc)                  (Rs. Mn)      Phy              Fin


Roads & Bridges

       Rehabilitation of Roads in Karachchi, Kilinochchi-
  1                                                          Karachchi    R/ACLG                A Group (Pvt) Ltd.                  7 km          4.11          3.88         100%             94%
       Pacakge-01
       Rehabilitation of Roads in Karachchi, Kilinochchi-                                       D.S Construction & Earth
  2                                                          Karachchi    R/ACLG                                                   7.5 km         15.30         4.69       Terminated         31%
       Pacakge-02                                                                               Movers
       Rehabilitation of Roads in Karachchi, Kilinochchi-
  3                                                          Karachchi    R/ACLG                C&C Engineering                    7.5 km         14.48         9.99         100%             69%
       Pacakge-03
       Improvement of Approach Road to Co-operative                                             Kilinochchi District Women
  4                                                          Karachchi    RDD                                                      0.9 km         2.98          3.80         100%         128%
       Council in Kilinochchi.                                                                  Development Federation.
       Rehabilitation of Roads in Kandawalai, Kilinochchi-
  5                                                          Kandawalai   R/ACLG                C&C Engineering                    6.26 km        13.82         9.04         100%             65%
       Package-01
       Rehabilitation of Roads in Kandawalai, Kilinochchi-                                      D.S Construction & Earth
  6                                                          Kandawalai   R/ACLG                                                    7 km          12.80         3.12       Terminated         24%
       Pacakge-02                                                                               Movers
       Rehabilitation of Roads in Kandawalai, Kilinochchi –
  7                                                         Kandawalai    R/ACLG                AMM                                 6 km          9.74          9.26         100%             95%
       Package 03
       Rehabilitation of Roads in Kandawalai, Kilinochchi –
  8                                                         Kandawalai    R/ACLG                Vanaja Construction                7.5 km         10.49         10.28        100%             98%
       Package 04
       Rehabilitation of Elephant Pass - Thadduvankoddi
  9                                                          Kandawalai   RDD                   MPCS, Karachchi South              3.22 km        1.93          0.61         30%              32%
       Road, Kilinochchi

 10    Rehabilitation of Roads in Poonery, Package 01        Poonakary    R/ACLG                Edward & Christie                  9.18 km        10.48         8.49         100%             81%

 11    Rehabilitation of Road in Poonaryan Package 02        Poonakary    R/ACLG                Land Mark Eng.                     4.67 km        8.49          7.45       Terminated         88%

 12    Rehabilitation of Road in Poonaryan Package 03        Poonakary    R/ACLG                Subramaniam Civil Engineering      6.19 km        9.57          0.29       Terminated         3%

 13    Rehabilitation of Road in Poonaryan Package 04        Poonakary    R/ACLG                Ragal Construction                 5.06 km        12.37         9.60         100%             78%

             Sub Total - Roads & Bridges                                                                                          77.98 km       126.56        80.50




                                                                                                  Page 33
                                    Ministry of Economic Development
                                    Progress of Mullaitivu District as at 30.06.2012


                                                                                          Physical                 Cumulative
                                                                                                          Total                    Progress
                                                                                       Target for the              Expenditure
                                         Implementing                                                   Estimate
S.No   Name of Work   DS Division                              Name of Contractor      Entire Project                  as at
                                           Agency                                                         Cost
                                                                                           Period                   30.06.2012
                                                                                                        (Rs. Mn)                 Phy          Fin
                                                                                        (km/Nos/etc)                 (Rs. Mn)




                                                           Page 44
                                                                                                                               Physical                 Cumulative
                                                                                                                                               Total                     Progress
                                                                                                                            Target for the              Expenditure
                                                                              Implementing                                                   Estimate
S.No                     Name of Work                          DS Division                       Name of Contractor         Entire Project                  as at
                                                                                Agency                                                         Cost
                                                                                                                                Period                   30.06.2012
                                                                                                                                             (Rs. Mn)                 Phy           Fin
                                                                                                                             (km/Nos/etc)                 (Rs. Mn)

Roads & Bridges

       Rehabilitation of Internal Roads in Thunukkai -
  1                                                         Thunukkai        R/ACLG          Lanka Machine Leasers            10.25 km        19.04        8.01       64%           42%
       Package 1

  2    Rehabilitation of Roads in Thunukkai- Package 2      Thunukkai        R/ACLG          Mega Construction                  7 km          15.07        8.68       81%           58%

  3    Rehabilitation of Roads in Thunukkai- Package 3      Thunukkai        R/ACLG          SMS Construction                  8.4 km          9.53        6.39       100%          67%

  4    Rehabilitation of Roads in Thunukkai- Package 4      Thunukkai        R/ACLG          K.P.K.Construction                 5 km          13.08        12.44      100%          95%

  5    Rehabilitation of Roads in Thunukkai- Package 5      Thunukkai        R/ACLG          Theepan Engneering.               5.25 km         9.79        8.95       100%          91%

  6    Rehabilitation of Roads in Thunukkai- Package 6      Thunukkai        R/ACLG          K.P.K.Construction                5.2 km         10.20        9.83       100%          96%

  7    Rehabilitation of Roads in Thunukkai- Package 7      Thunukkai        R/ACLG          Jana Agency.                       6 km          15.59        14.23      100%          91%

  8    Rehabilitation of Roads in Manthai East- Package 1   Manthai East     R/ACLG          SMA Construction                   4 km          12.13        10.19      100%          84%

  9    Rehabilitation of Roads in Manthai East- Package 2   Manthai East     R/ACLG          Leading Crusher Works.           13.75 km        13.99        13.30      100%          95%

 10    Rehabilitation of Roads in Mantha East- Package 3    Manthai East     R/ACLG          Pupethira Civil Engineering.       2 km           9.37        8.70       100%          93%

 11    Rehabilitation of Roads in Manthai East- Package 4   Manthai East     R/ACLG          D & D Construction                3.5 km         10.30        9.62       100%          93%

 12    Rehabilitation of Roads in Manthai East- Package 5   Manthai East     R/ACLG          SMA Construction                  5.2 km         13.15        12.21      100%          93%

 13    Rehabilitation of Roads in Manthai East- Package 6   Manthai East     R/ACLG          SMA Construction                  2.75 km        13.58        12.55      100%          92%

 14    Rehabilitation of Roads in Manthai East- Package 7   Manthai East     R/ACLG          Mega Construction                 7.7 km         19.09        12.54      98%           66%

 15    Rehabilitation of Roads in Manthai East- Package 8   Manthai East     R/ACLG          Koneswaran Engineering            8.91 km        24.17        7.22       45%           30%

       Construction of Bridge across the left bank main
 16                                                         Manthai East     DDI             RDS, Selvapuram                    1 No           1.52        1.46       100%          96%
       channel at Vavunikkulam




                                                                                             Page 45
                                                                                                                                 Physical                 Cumulative
                                                                                                                                                 Total                     Progress
                                                                                                                              Target for the              Expenditure
                                                                              Implementing                                                     Estimate
S.No                     Name of Work                          DS Division                       Name of Contractor           Entire Project                  as at
                                                                                Agency                                                           Cost
                                                                                                                                  Period                   30.06.2012
                                                                                                                                               (Rs. Mn)                 Phy           Fin
                                                                                                                               (km/Nos/etc)                 (Rs. Mn)

 17    Rehabilitation of Roads in Oddusuddan- Package 1     Oddusuddan       R/ACLG          K.R.Lanka (pvt) Ltd                  11 km         12.49        11.43      100%          92%

 18    Rehabilitation of Roads in Oddusuddan- Package 2     Oddusuddan       R/ACLG          S.Subramaniam Civil Eng.            4.5 km         17.02        14.71      100%          86%

 19    Rehabilitation of Roads in Oddusuddan- Package 3     Oddusuddan       R/ACLG          A Group Construction               16.75 km        15.95        13.79      100%          86%

 20    Rehabilitation of Roads in Oddusuddan- Package 4     Oddusuddan       R/ACLG          J.K.Construction                    6.5 km         11.26        9.27       100%          82%

 21    Rehabilitation of Roads in Oddusuddan- Package 5     Oddusuddan       R/ACLG          Thurai Construction                  12 km         12.91        11.67      100%          90%

 22    Rehabilitation of Roads in Oddusuddan- Package 6     Oddusuddan       R/ACLG          S. Subramaniam Civil Engineers      6.7 km         12.97        10.98      100%          85%

       Rehabilitation of internal roads in Maratimepattu,
 23                                                         Maritimepattu    ACLG            K.R.Lanka PVT(LTD)                  7.7 km         15.65        1.71       93%           11%
       Mullaitivu Package 1
       Rehabilitation of internal roads in Maratimepattu,
 24                                                         Maritimepattu    ACLG            K.R.Lanka PVT(LTD)                  6.5 km         15.21        8.54       98%           56%
       Mullaitivu Package 2
       Renovation of internal roads in Maratimepattu,
 25                                                         Maritimepattu    ACLG            Master Construction                 3.8 km         17.56        12.98      100%          74%
       Mullaitivu Package 3
       Rehabilitation of internal roads in Maratimepattu,
 26                                                         Maritimepattu    ACLG            Babithan Construction               12.2 km        14.45        10.03      85%           69%
       Mullaitivu Package 4
       Rehabilitation of Internal Roads in Maritimepattu,
 27                                                         Maritimepattu    ACLG            Yansika Construction                4.42 km         6.14        5.09       100%          83%
       Mullaitivu - Package 5

             Sub Total - Roads & Bridges                                                                                       186.48 km       361.21       266.52




                                                                                             Page 46
                                    Ministry of Economic Development
                                    Progress of Vavuniya District as at 30.06.2012

                                                                                       Physical
                                                                                                               Cumulative
                                                                                      Target for      Total                   Progress (%)
                                                                                                               Expenditure
                                         Implementing                                 the Entire    Estimate
S.No   Name of Work   DS Division                              Name of Contractor                                  as at
                                           Agency                                      Project        Cost
                                                                                                                30.06.2012
                                                                                        Period      (Rs. Mn)                 Phy        Fin
                                                                                                                 (Rs. Mn)
                                                                                     (km/Nos/etc)




                                                          Page 54
                                                                                                                           Physical
                                                                                                                                                   Cumulative
                                                                                                                          Target for      Total                    Progress (%)
                                                                                                                                                   Expenditure
                                                                                Implementing                              the Entire    Estimate
S.No                     Name of Work                           DS Division                        Name of Contractor                                  as at
                                                                                  Agency                                   Project        Cost
                                                                                                                                                    30.06.2012
                                                                                                                            Period      (Rs. Mn)                 Phy         Fin
                                                                                                                                                     (Rs. Mn)
                                                                                                                         (km/Nos/etc)

Roads & Bridges
       Rehabilitation of Roads in Vavuniya District –                                           V.V. Ramanthan &
  1                                                          Vavuniya North   R/ACLG                                      12.55 km       12.58        12.27      100%        98%
       Package 1                                                                                Company(pvt)Ltd
       Rehabilitation of Roads in Vavuniya District –                                           V.V. Ramanthan &
  2                                                          Vavuniya North   R/ACLG                                       9.75 km       13.96        12.69      100%        91%
       Package 2                                                                                Company(pvt)Ltd
       Rehabilitation of Roads in Vavuniya District –                                           V.V. Ramanthan &
  3                                                          Vavuniya North   R/ACLG                                       10.7 km       13.44        12.29      100%        91%
       Package 3                                                                                Company(pvt)Ltd

       Formation & Gravelling of Resettlement area Roads at
  4                                                         Vavuniya North    R/ACLG            MPCS, Vavuniya North        4.4 km        4.66        3.83       100%        82%
       Karappukuththi Periyamadu road in Vavuniya

       Formation & Gravelling of Resettlement area Roads at
  5                                                         Vavuniya North    R/ACLG            MPCS, Vavuniya North        3 km          2.56        1.43       100%        56%
       Keerisuddankiramam in Vavuniya North
       Formation & Gravelling of Resettlement area Roads at
  6    Kurisuddakulam Ampal nagar and Panaininran kulam Vavuniya North        R/ACLG            MPCS, Vavuniya North       5.65 km        4.53        3.89       100%        86%
       roads in Vavuniya North
       Cleaning & Reformation of VNPS area Roads
  7                                                          Vavuniya North   R/ACLG            MPCS, Vavuniya North        23 km         3.78        2.87       100%        76%
       Vavuniya North

  8    Rehabilitation of Roads in Vavuniya North package 4 Vavuniya           R/ACLG            Edward & christie           25 km        19.59        4.83       35%         25%

       Formation and gravelling of resettlement area road at
  9                                                          vavuniya         R/ACLG            MPCS, Vavuniya              4 km          3.81        3.31       100%        87%
       Salampaikulam Roads
       Formation and Gravelling of Resettlement area road at                                    Vevakanantha Community
 10                                                          Vavuniya         R/ACLG                                        5.4 km        5.08        4.15       100%        82%
       Nochchimoddai & Veemankal in Vavuniya                                                    Center
       Formation & gravelling of resettlement area road at                                      Vevakanantha Community
 11                                                          Vavuniya         R/ACLG                                        1.1 km        3.15        2.85       100%        90%
       Paranaddakal Roads                                                                       Center
       Formation and gravelling of resettlement area at
 12                                                          vavuniya         R/ACLG            MPCS, Vavuniya              1.1 km        2.77        2.61       100%        94%
       omanthai Roads
       Urgent clearing and reformation of VSTPS area in
       vavuniya(illamaruthankulam internal roads,
 13                                                          Vavuniya         R/ACLG            MPCS, Vavuniya              29 km         4.15        3.52       100%        85%
       Nochchikulam roads, Kothanda Nochchikulam
       Approach & Internal road)

 14    Renovation of Kallikulam Internal Road in Vavuniya Vavuniya            ACLG              FO, Kallikulam              4.5 km        3.17        2.82       100%        89%




                                                                                               Page 55
                                                                                                                          Physical
                                                                                                                                                  Cumulative
                                                                                                                         Target for      Total                    Progress (%)
                                                                                                                                                  Expenditure
                                                                                Implementing                             the Entire    Estimate
S.No                    Name of Work                            DS Division                        Name of Contractor                                 as at
                                                                                  Agency                                  Project        Cost
                                                                                                                                                   30.06.2012
                                                                                                                           Period      (Rs. Mn)                 Phy         Fin
                                                                                                                                                    (Rs. Mn)
                                                                                                                        (km/Nos/etc)

       Formation and Gravelling of resettlement area roads at
 15                                                           Cheddikulam     R/ACLG            MPCS, Cheddikulam          6 km          4.56        4.38       100%        96%
       Periyathampanai & Piramanalankulam Roads

       Formation and Gravelling of Resettlement area road at
 16                                                          Cheddikulam      R/ACLG            MPCS, Cheddikulam          3 km          3.87        3.73       100%        96%
       Kanthasamynagar in VCK
       Formation and Gravelling of Resettlement area road at
 17                                                          Vavuniya South   R/ACLG            RDS, Palaiyaurava         8.15 km        4.57        4.10       100%        90%
       Palairuva & Track 07 Roads
       Formation and Gravelling of Resettlement area road at
 18                                                          Vavuniya South   R/ACLG            WRDS, Awaranthulawa       4.75 km        2.38        2.16       100%        91%
       Awaranthulawa Roads

 19    Rehabilitation of roads in Galabogaswewa Road        Vavuniya South    ACLG              WMB Contractors            20 km        19.14        8.85       100%        46%


            Sub Total - Roads & Bridges                                                                                 181.05 km      131.75       96.58




                                                                                               Page 56
                                                                              Ministry of Economic Development
                                                                              Progress of Mannar District as at 30.06.2012


                                                                                                                                          Physical
                                                                                                                                                                  Cumulative
                                                                                                                                         Target for      Total                    Progress
                                                                                                                                                                  Expenditure
                                                                                                                                         the Entire    Estimate
S.No                     Name of Work                           DS Division      Implementing Agency          Name of Contractor                                      as at
                                                                                                                                          Project        Cost
                                                                                                                                                                   30.06.2012
                                                                                                                                           Period      (Rs. Mn)                 Phy      Fin
                                                                                                                                                                    (Rs. Mn)
                                                                                                                                        (km/Nos/etc)

Roads & Bridges

  1    Rehabilitation of Roads in Manthai West- Package 1    Manthai West      R/ACLG                     A Group (Pvt) Ltd.               5 km          7.05        6.73       100%     95%

  2    Rehabilitation of Roads in Manthai West- Package 2    Manthai West      R/ACLG                     Sanjeeve Construction.           4.5 km        7.29        6.97       100%     96%

  3    Rehabilitation of Roads in Manthai West- Package 3    Manthai West      R/ACLG                     Mahadevan Contractors.           3 km          7.37        7.51       100%    102%

  4    Rehabilitation of Roads in Manthai West- Package 4    Manthai West      R/ACLG                     R&S Eng.Construction.            5.7 km        8.16        7.15       100%     88%

       Rehabilitation of Internal Roads in Manthai West -
  5                                                          Manthai West      R/ACLG                     Edward & Christie               10.8 km       21.21        8.37       50%      39%
       Package 5

  6    Rehabilitation of Roads in Madhu- Package 1           Madhu             R/ACLG                     Santhiyapillai &Sons             4.5 km        6.44        6.13       100%     95%

  7    Rehabilitation of Roads in Madhu- Package 2           Madhu             R/ACLG                     Sri Arans Civil Contractors      7 km          7.61        5.25       100%     69%

  8    Rehabilitation of Roads in Madhu- Package 3           Madhu             R/ACLG                     Jana Civil Works.                5.5 km        7.70        7.31       100%     95%

  9    Rehabilitation of Roads in Madhu- Package 4           Madhu             R/ACLG                     Jana Civil Works.                3 km          3.62        3.45       100%     95%

       Rehabilitation of Internal Roads in Madhu - Package
 10                                                          Madhu             R/ACLG                     Leading Crusher Works           11.8 km       15.95        11.71      100%     73%
       5

 11    Rehabilitation of Internal Roads in Musali, Mannar    Musali            R/ACLG                     Edward & Christie                10 km        18.23        3.57       20%      20%

             Sub Total - Roads & Bridges                                                                                                 70.8 km       110.63       74.15