									                                 Testbeam



                           HCAL Main meeting at DESY
                                  April 28, 2005




Felix Sefkow   April 28, 2005                  HCAL Main Meeting   1
                                           Sites


                                •   DESY

                                •   Fermilab

                                •   CERN




Felix Sefkow   April 28, 2005                  HCAL Main Meeting   2
                                        DESY testbeam

• Shutdown mid November – mid December

• ECAL plans
       – Run in June: “probability is very weak” (JCB) due to delays in wafer
         delivery
       – Request run November or later

• HCAL options
       – 1st cassette end May
       – Up to 3 layers in existing stack possible
               • Needs mass-produced electronics (August or later)
       – Larger stack in final stack support with ~ 10-15 layers
               • To be evaluated
       – Cosmics with full stack and NIU trigger layers


Felix Sefkow    April 28, 2005                         HCAL Main Meeting        3
                                Fermilab testbeam

•     Visit on March 16
•     Close collaboration with FNAL engineers
•     Installation problems can be solved
•     Solution for RPC electronics found




Felix Sefkow   April 28, 2005              HCAL Main Meeting   4
               CALICE Setup V-Trial at FNAL MTBF

                     Tail Catcher
                                       HCAL

                                                                  Electronic Racks




                                    ECAL



                                                                  Beam
Felix Sefkow    April 28, 2005                HCAL Main Meeting                      5
         Planning Document to FNAL
•   Initial draft written at the
    ANL workshop in Sept.
    –    As agreed at ECFA
         meeting
•   Result of the World-wide
    LC CAL/Muon TB
    Working Group
    –    Many thanks….
•   Total of 25 pages w/
    –    Overview of TB plans and
         requirements
    –    Will be followed by detailed
         MOUs
•   Submitted to FNAL on
    Feb. 22, 2005
              J. Repond
    Felix Sefkow   April     HCAL Main MeetingTB Summary,   6
    28, 2005                          LCWS2005
                                Duty cycle




Felix Sefkow   April 28, 2005       HCAL Main Meeting   7
                                Other limitations




Felix Sefkow   April 28, 2005           HCAL Main Meeting   8
                                Other possibilities


• Fermilab beam line M-center
       – Is shorter, higher rates at low energies
       – same spill structure
       – MIPP continuation not approved, but other parties show interest,
         too.
       – Details being investigated


• CERN
       – SPS will run in 2006 (May - )
       – Informal contacts
       – Details being investigated



Felix Sefkow   April 28, 2005                  HCAL Main Meeting            9
                                Detector R&D: Packed agendas


• 36 talks on calorimetry and muons                          (16 at LC99 Sitges)

• 32 talks on tracking and vertexing                         (13 at LC99 Sitges)

• 25 talks on simulation and reconstruction

• 20 talks on machine detector interface

• 15 talks on DAQ               We know the bunch structure now


• 7 talks on testbeam

Felix Sefkow   April 28, 2005                    HCAL Main Meeting                 10
                                       Calorimeter R&D

•     ECAL: main option Si W
       – Demonstrate feasibility of ultra-
         compact systems
       – CALICE test beam at DESY
       – SLAC Oregon test wafers
       – Korean groups testbeam at CERN
•     HCAL: gaseous or scintillator,
       – Understand hadron showers
       – Gaseous: RPC and GEM R&D
       – Scintillator: Prototype
         construction at DESY
•     Photodector R&D
       – Hamamatsu SiPMs,
       – Colorado 7 pixel counters
•     Particle flow
       – Not yet converging
Felix Sefkow   April 28, 2005                HCAL Main Meeting   11
                                   Barry Barish to lead GDE

First statements on timeline of GDE

• Snowmass (2nd ILC meeting) is important
       – Fix ILC baseline configuration
       – Yet, keep open for improvements


• CDR target date: end of 2006
       – But: with price tag
       – Site dependent: sample sites
               • Understand geological / political constraints


• TDR in 2008


Felix Sefkow    April 28, 2005                        HCAL Main Meeting   12
                                Milestones of ILC (by sugimoto)
                  2004             2005         2006             2007            2008        2009           2010

                                                GDE (Design)                                   (Construction)
   Technology              Acc.           CDR                      TDR            Start Global Lab.     Changes
   Choice                                                                                               acc. To BB
                           Det.           Detector Outline         CDRs           LOIs
   Done!                                   Documents


                                 Detector R&D Panel

                                                                    Collaboration
       Detector                  R&D Phase                          Forming                      Construction

                                                                                             Tevatron
                                                                                    SLAC B
                                                                      HERA           LHC
                                                                                       T2K

Felix Sefkow   April 28, 2005                                                                                 13

                                            HCAL Main MeetingH.Yamamoto, LCWS05 Stanford
                                 Where we are

Entering the prototype mass production stage

•     SiPMs from main batch on tiles

•     Mass-produced front end ASICs

•     Commission readout chain with final electronics

•     Optimize calibration system

•     Cassette No. 1 plus front end prototype to test beam




Felix Sefkow   April 28, 2005              HCAL Main Meeting   14
                                   Things to come

• Software!
       – Comes with testbeam
• Scheduling
       – Next months: establish a smooth production chain
       – Adjust start-up and laminar stream (SiPMs, tiles, cassettes)
• Test beam planning
       – Other talk
• R&D planning
       – Other meeting
• Organizational:
       – Cost to completion review in May (DESY)
       – CALICE technical review in (beginning of) October
       – CALICE @ DESY PRC on November 10