New Construction Projects
C01 Stella Brockman Joint-Use Gymnasium - Completed

C02 Stella Brockman Annex - Completed

C03 Joshua Cowell Annex – Awaiting New Development to Start

C04 Great Valley Annex - Completed

C05 Lathrop Elementary Joint-Use Gymnasium - Completed

C06 Lincoln HVAC Project - Completed

C07 New Haven Parking Project - Completed


*C08   Sequoia Multi-Purpose Building Conversion (1985 portable) –
     The State of California has approved funding. Planning to take place with architect.

C09 This number was not used.


*C10     Woodward Annex – In Planning
       At this time there is no State Eligibility to move forward with this project. After the formal
       CBEDS in October 2010 is generated and reviewed by the Office of Public School
       Construction, we will determine if we have State Eligibility. School building plans have
       been completed. In 2010-11, we will determine to place a soccer field, baseball field or some
       type of improvement to this site with funds coming from Mello- Roos, CFD 3, or any leftover
       funds from Measure M.


*C11    Lathrop #3 – On Hold
       Need to purchase the site.

C12 Manteca High School Field House – Completed

C13 This number was not used

C14 Sierra High School Faculty Room Conversion – Completed

C15 New Vision (WRHS–Alt. Ed. Center - Phase III) – Completed

C16 Lathrop #2 - Mossdale School – Completed


*C17 Union Ranch – North Manteca – On Hold
       In 2010-11, we will determine to place a soccer field, baseball field, etc. or some type of
       improvement to this site. Funds can come from Mello Roos, CFD 3, or any leftover funds
       from Measure M.

C18 Lathrop High School – Completed


*C19    Rustic School – This property has been licensed to a neighbor and turned into pasture for
        MHS FFA students’ beef cattle.
PREPARED FOR THE SEPTEMBER 2010 MTG
Revised 09/15/2010
                                                 1 OF 2
                        MEASURE “M” PROJECT STATUS UPDATE


C20 S. Manteca High School – This property is currently being leased by a farmer from Manteca.

C21 Weston Ranch Joint-Use Library - Completed

C22 East Union High School Band Room Conversion (1987 portable) – Completed


*C23    French Camp Joint-Use Gymnasium – In Construction
     Additional site, planning and construction costs: engineering costs to connect to the City of
     Stockton water supply for fire suppression, new septic system, asbestos removal, upgrade
     fire and electrical. State Board of Allocation approved 1.5 million dollars for this project,
     which can fund the parking lot.


*C24     Lathrop #1 - Ethel Allen School – On Hold
       Plans and Specifications for this project have been approved by DSA. We are awaiting new
       development and State “New Construction” eligibility. In 2010-11, a water meter was
       purchased to develop a soccer field, baseball field or some type of improvement to this site
       with funds coming from Mello- Roos, CFD 4, or any leftover funds from Measure M.

C25 East Union High School Swimming Pool – Completed

C26 East Union High School HVAC –Boys’ Locker Room – Completed

C27 Neil Hafley Joint-Use Gymnasium – Completed

C28 Shasta Joint-Use Gymnasium – Completed

C29 Lathrop High School Joint-Use Gym – Completed
    Bleachers purchased for the Gymnasium.


*C30  Lathrop High Career Technical Ed – In Planning
     Plans approved by DSA. OPSC has approved funding. Form 50-05 to be submitted to OPSC
     for funding.

C31 EUHS Locker Room Lockers (Phase II) – Complete


Modernization Projects
M01 French Camp Modernization – Completed

M02 Nile Garden Modernization – Completed

M03 Shasta Modernization – Completed

M04 East Union High School/Gymnasium Shop Modernization – Completed

M05 American Disability Improvement - Ongoing

M06 New Haven Modernization - Completed

M07 Neil Hafley Modernization Project – Completed
    The Board of Education approved the Final Notice of Completion on October 5, 2009.